Tuesday, 28, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Gas Authority Of India vs A.K. Gupta And Co.
2010 Latest Caselaw 2472 Del

Citation : 2010 Latest Caselaw 2472 Del
Judgement Date : 7 May, 2010

Delhi High Court
Gas Authority Of India vs A.K. Gupta And Co. on 7 May, 2010
Author: Manmohan
F-48

*      IN THE HIGH COURT OF DELHI AT NEW DELHI


+      O.M.P. 426/2003 & I.A. No. 10776/2003


GAS AUTHORITY OF INDIA                  ..... Petitioner
                  Through: Mr. Naveen Kumar, Advocate.

                      versus

A.K. GUPTA AND CO.                                    ..... Respondent
                               Through: Mr. R.P. Kaushik, Advocate.


%                                 Date of Decision : May 07, 2010


CORAM:
HON'BLE MR. JUSTICE MANMOHAN

1. Whether the Reporters of local papers may be allowed to see the judgment? No.
2. To be referred to the Reporter or not? No.
3. Whether the judgment should be reported in the Digest? No.


                               JUDGMENT

MANMOHAN, J (ORAL)

1) The Petitioner awarded a Contract to the Respondent for

construction of 45 residential flats in the district of Etawa (U.P) through

Work Order dated 18.6.1996 for a Contract Price of Rs.3,31,75,000/-.

2) The work was completed by the Respondent-Claimant on

20.1.1998 and the Final Bill was raised on 25.6.1998.

3) Respondent-Claimant raised certain claims which were not

entertained by the Petitioner. As such, disputes and differences arose

between the parties, the Respondent invoked arbitration vide letter

dated 23.1.2002.

4) During the pendency of the arbitration proceedings, the Dispute

Avoidance & Resolution Team ("DART") constituted by the Petitioner

had reached a broad settlement with the Respondent and the terms of

settlement were duly recorded in a Minutes of Meeting dated

26.05.2003.

5) Based on the said settlement proposals, the Respondent-Claimant

had raised its final claims vide letter dated 29.05.2003, accepting the

settlement terms and also giving-up some of its claims. On the basis of

the said letter, the Respondent-Claimant thereafter revised its claims

before the Ld. Arbitrator, and filed its Amended Statement of Claim on

14.07.2003.

6) The Ld. Arbitrator reserved the Award on 14.07.2003 itself and

finally made his Award on 2nd August, 2003, which has been

challenged by the Petitioner principally on the grounds that the

appointment of the Ld. Arbitrator was not in accordance with the

agreed procedure under the arbitration clause and that it has not been

granted adequate opportunity to present its defence in the arbitration

proceedings.

7) I have heard Ld. Counsel for the parties. The fact that there was a

settlement reached between the parties as recorded in the Minutes of

Meeting dated 26.05.2003 of DART is not in dispute. It is also not in

dispute that the Respondent had accepted the amounts agreed to be paid

to it by the Petitioner in terms of the said settlement. The Respondent

admits that vide its letter of 29.05.2003, while claiming payment of the

said amounts, it had given-up some of its claims, but which have also

been awarded in the impugned Award along with the agreed claims. In

view of the above position claim of the respondent/claimant as

approved by DART and interest on the delayed payment as claimed by

the respondent/claimant on strength of clause 26(d) of the contract is as

under:

Claim Nature of claims Amount Amount settled no claimed by by DART respondent before Arbitrator

1. Balance Final bill 6,02,655 6,02,655

2. Retention for 21,250 21,250 horticulture

3. Wrong full 1,40,323 1,40,323 recoveries

4. Escalation Balance 3,64,766 3,64,766

5. Bonus on early 80,000 80,000 completion

6. Interest on delayed 14,724 14,724 payment & non payment

7. Interest on delayed 1305831 Waived payment & non payment on R.A.





                   bills

       8.         Pedenlite interest    @ 18%         Waived

       9.         Cost of arbitration   100000        Waived

       10.        Total                               12,23,718

       11.        Plus    interest   claimed    by
                  respondent as per clause 26(d) of
                  contract @12% on total amount
                  from 16-06-2003 till the date of
                  actual payment



8)     The terms of settlement reached between the parties on

26.05.2003 would be binding against them, and more so, the

Respondent-Claimant could not have claimed the amounts which it had

itself given-up in its letter of 29.05.2003, and at the same time the

petitioner cannot escape from its admitted liability as acknowledged by

the DART which was constituted by the petitioner itself.

9) In view of the above, the impugned Award is modified to the

extent that Claims No. 7, 8 and 9 are not payable to the Respondent-

Claimant. The other amounts awarded in favour of the Respondent-

Claimant shall be paid by the Petitioner along with interest @ 12% as

agreed under Clause 26 d of the Contract between the parties.

No orders as to cost of the proceedings.

MANMOHAN,J

MAY 07, 2010 js

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter