Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

B.S.E.S. Rajdhani Power Ltd. vs D.R. Bajaj & Another
2010 Latest Caselaw 1529 Del

Citation : 2010 Latest Caselaw 1529 Del
Judgement Date : 18 March, 2010

Delhi High Court
B.S.E.S. Rajdhani Power Ltd. vs D.R. Bajaj & Another on 18 March, 2010
Author: Sanjiv Khanna
*     IN THE HIGH COURT OF DELHI AT NEW DELHI

+     W.P.(C) 1252/2007

      B.S.E.S.RAJDHANI POWER LTD.                  ..... Petitioner
                         Through       Mr. I.S. Alag and Mr. Rishabh
                                       Bhutani, Advocate.

                    versus


      D.R.BAJAJ & ANR.                        ..... Respondent
                             Through

      CORAM:
      HON'BLE MR. JUSTICE SANJIV KHANNA

                             ORDER

%

In spite of service, the respondent No.1 has not entered

appearance and is accordingly proceeded ex-parte.

2. The respondent No.1 had approached the Consumer Grievance Redressal Forum making allegations that the three electronic meters installed in his premises for recording electricity consumption of the ground floor, first floor and second floor were defective and he was wrongly billed and asked to pay excessive amounts. The respondent No.1 had relied upon the average consumption pattern as recorded in the electro mechanical meters before they were replaced by new electronic meters on 10th May, 2005.

W.P.(C) No. 1252/2007 Page 1

3. The Consumer Grievances Redressal Forum got the meter tested

from an independent laboratory, namely, CPRI, Delhi. The meters were

tested in the presence of the SDM of the area to ensure that test was

properly done and there was no tampering. As per the test report given

by the CPRI, the meters were found to be in permissible limits and were

not recording excessive consumption. In view of the said test reports,

the matter was disposed of vide order dated 2nd January, 2006, holding,

inter alia, that the meters were not defective.

4. The respondent No.1 thereafter approached the Ombudsman.

The Ombudsman by the impugned order did not interfere with the

billing tariff/meter in respect of the ground floor and the first floor, but

came to the conclusion that the meter installed on the second floor

was defective and accordingly the petitioner herein was directed to

raise fresh bills for the period May, 2005 to September, 2006 after

taking the average of six months prior to the defective period and

average of six month after the defective period. The reason recorded

by the Ombudsman in the impugned order dated 19th October, 2006 is

that the consumption pattern for the ground floor and the first floor

W.P.(C) No. 1252/2007 Page 2 after replacement of the electro mechanical meters with the electronic

meters, had not shown appreciable jump or increase in consumption

but in the case of second floor, there was substantial increase in

consumption though there was no increase in connected load.

5. The consumption pattern for the months of October and

December 2004-2005 does show some increase but the same cannot

be called abnormal. As per the consumption chart placed on record,

the respondent had consumed 762 and 505 units in the month of

October and December 2004 and 1113 and 765 units in the

corresponding month in the year 2005. Similarly, in February 2005, the

respondent had consumed 497 units and in the month of February

2006 had consumed 1036 units. It is not possible to decipher any fixed

pattern, conclusion or inference from the said figures. It is apparent

that the Ombudsman has proceeded and relied upon irrelevant

material and facts and did not take into account the relevant document

i.e. the CPRI test report. The learned Ombudsman did not even bother

to examine the CPRI meter testing report. It is recorded that the said

report was not available with the Ombudsman.

6. The present writ petition is accordingly allowed and the

impugned order dated 19th October, 2006 passed by the Ombudsman is

W.P.(C) No. 1252/2007 Page 3 set aside and quashed. The petitioners will write a letter to the

respondent No.1 asking him to make payment. In case the respondent

No.1 makes payment within 15 days from the date letter is served, no

late payment surcharge will be demanded/charged. Rs. 5,000/-

deposited in this Court will be refunded to the petitioner.

SANJIV KHANNA, J.

       MARCH 18, 2010
       NA




W.P.(C) No. 1252/2007                                         Page 4
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter