Citation : 2010 Latest Caselaw 1229 Del
Judgement Date : 4 March, 2010
#F-14
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P. 287/2000
M/S. NATIONAL AGRICULTURE
CO-OPERATIVE MARKETING
FEDERATION OF INDIA LIMITED ..... Petitioner/Objector
Through Mr. Shiv Khorana with
Mr. Ashish Khorana, Advocates
versus
UNION OF INDIA ..... Respondent
Through: Mr. A.S. Chandiok, ASG with
Mr. Anuj Aggarwal, Ms. Vibha
Dhawan, Mr. Sandeep Bajaj,
Mr. Gurpreet Prawanda and
Mr. Gaurav Khanna, Advocates
% Date of Decision : March 4, 2010
CORAM:
HON'BLE MR. JUSTICE MANMOHAN
1. Whether the Reporters of local papers may be allowed to see the judgment? No.
2. To be referred to the Reporter or not? No.
3. Whether the judgment should be reported in the Digest? No.
JUDGMENT
MANMOHAN, J (ORAL)
1. Present petition has been filed under Section 34 of the Arbitration
and Conciliation Act, 1996 (hereinafter referred to as "Act, 1996")
challenging the arbitral Award dated 4th August, 2000 passed by the
Sole Arbitrator, Mr. B.L. Nishad, Additional Legal Adviser, Ministry of
Law and Justice.
2. Briefly stated the facts of the present case are that on 2nd
February, 1996 a tender enquiry bearing No. J-12016/1/96-Pur.III was
floated for procurement of 10000 MTs Barley by the Army Purchase
Organisation with the following schedule :-
Delivery Period Quantity
16-31 March, 1996 2500 MT
01-15 April, 1996 2500 MT
16-30 April, 1996 2500 MT
01-15 May, 1996 2500 MT
3. On 19th March, 1996, the contract for supply of 9000 MTs Barley
was placed upon the petitioner-claimant vide Acceptance of Tender
bearing No. J-13016/2/70/96-Pur.III dated 19th March, 1996 with the
following details:-
Delivery Period Quantity (MT) Rate/Qtl. (Rs.)
16-31.3.96 2500 Rs. 477/-
01-15.4.96 2500
16-30.4.96 2000
01-15.5.96 2000
4. On 26th March, 1996, petitioner-claimant acknowledged the
acceptance of tender but requested the respondent-UOI for rescheduling
the delivery period from 15th March, 1996 to 15th April, 1996.
5. Thereafter on 9th April, 1996, 28th May, 1996, 10th July, 1996 and
20th September, 1996 respondent-UOI granted repeated extension of
time to petitioner-claimant to supply the contracted quantity of Barley.
Each of the abovementioned extensions was granted at the petitioner-
claimant's request and was subject to respondent-UOI's right to levy
liquidated damages upto 2% per month.
6. On 22nd October, 1996, respondent-UOI at petitioner-claimant's
request granted fifth extension of time upto 30th November, 1996 for
delivery of balance quantity of Gram Whole.
7. On 4th November, 1996, petitioner-claimant acknowledged and
accepted fifth extension upto 30th November, 1996. But by this letter,
petitioner-claimant once again requested for extension of time for
supply of balance quantity of Barley upto March and April, 1997. The
said letter dated 4th November, 1996 reads as under :-
"No. DLI/MK/67/96-97/1390 4.11.1996
The Jt. Secretary (AFO),
Ministry of Defence,
South Block,
New Delhi.
Sub: Supply of 9000 MT of Barley against
A.T. No. J-13016/2/70/ 96.PUR-III dt. 19.3.96.
Dear Sir,
We are thankful to you for granting us extension upto 30.11.96 for the balance quantity of 2173 MTs of Barley against the above mentioned A.T. You will kindly appreciate that we have already supplied to you a qty of 6827 MTs, which works out to 76%. Only a balance qty of 24% is to be supplied.
We had requested you vide our letter of even no. dated 4.10.1996 for granting us extension upto 30.4.1997 because of non-availability of stocks as per your specifications. In case extension for the balance qty is not possible upto 30.4.97 we shall request you to please divide the above balance qty in two months i.e. March ‟97 and April ‟97.
Further, we undertake the guarantee to supply you the above goods in case emergency arises within a month‟s time on receiving your instructions. As you are kindly aware we are suffering heavy losses in the above supplies. We shall be highly thankful to you if you kindly consider condoning LD charges charged against the above supplies.
Thanking you,
Yours faithfully,
Sd/-
(D.N. GUPTA) BRANCH MANAGER
CC: The Chief Director of Purchase, Govt. of India, Ministry of Defence, Army Purchase organization, Krishi Bhawan, New Delhi - for kind favour.
Sd/-
BRANCH MANAGER"
(emphasis supplied)
8. On the basis of assurance given by petitioner-claimant during the
meeting held on 5th November, 1996, respondent-UOI asked the
petitioner-claimant to complete the supply of balance quantity of 2173
MTs of Barley by 31st January, 1997 by way of Final Extension-cum-
Performance Notice dated 11th November, 1996. It was once again
clarified that liquidated damages would be imposed on delayed supply
at the rate of 2% per month.
9. However, petitioner-claimant supplied only 6455.604 MTs as
against the contracted quantity of 9000 MTs thereby leaving an
unsupplied balance of 2544.396 MTs. This shortfall in supply was
there, despite repeated opportunities given by respondent-UOI to
complete the contract.
10. As there was an inordinate delay in completion of supplies and as
petitioner-claimant had not completed the contract even after sixth
extension, the respondent-UOI cancelled the contract for the balance
quantity at the risk and cost of petitioner-claimant. Even the bank
guarantee furnished by petitioner-claimant for a sum of
Rs. 42,93,000/- was encashed by the respondent-UOI.
11. On 2nd April, 1997, respondent-UOI floated a Risk Purchase (in
short "RP") Tender Enquiry for balance quantity of 2544.396 MTs of
Barley. On 22nd April, 1997, respondent-UOI supplied a set of
documents pertaining to the said tender to the petitioner-claimant. It
was specifically stated in the said letter that in case the petitioner-
claimant's offer was accepted, it would have to furnish security deposit
equivalent to the difference between its quotation and the next best
quotation or 10% of the proposed contract value whichever was higher
by a specified date before placement of contract on it failing which its
offer would be ignored.
12. On 15th May, 1997, respondent-UOI sent a telegram calling
petitioner-claimant to deposit advance security by 26th May, 1997. It
was specifically mentioned in the said telegram that petitioner-
claimant's failure to deposit the security would lead to its tender offer
being ignored and the orders would be placed on the best acceptable
offers at its risk and cost.
13. However, instead of depositing the security amount asked for,
petitioner-claimant sought further time of three to four days to deposit
the said security. Respondent-UOI rejected said request and RP
contracts were awarded to M/s. Gujrat Cooperative Grain Growers Fed.
Ltd. for supply of 1200 MT @ Rs. 600/- P.Q. and to M/s STC for
supply of 1344.396 MTs @ Rs.648/- P.Q. vide A/T No. J-
13016/2/70/96-RP/4/123/97-Pur.III dated 26.05.97 and J-
13016/2/70/96-RP/3/122/97.Pur.III dated 26.05.97 respectively.
14. On 8th May, 1998, petitioner-claimant was asked by respondent-
UOI to deposit a sum of Rs. 42,26,616/- being the amount of loss
suffered by the respondent-UOI in RP of Barley.
15. Since disputes had arisen between the parties, respondent-UOI on
24th February, 1999 appointed Mr. B.L. Nishad as Sole Arbitrator to
adjudicate upon the same.
16. By way of the impugned Award dated 4th August, 2000, the Sole
Arbitrator rejected the petitioner-claimant's claims but allowed the
counter-claim of respondent-UOI and thereby awarded a sum of Rs.
42,26,616/- being the total loss incurred by respondent-UOI on RP
contracts, after adjusting earnest money.
17. Mr. Shiv Khorana, learned counsel for petitioner-claimant
submitted that the impugned Award was liable to be set aside as the
Arbitrator had perused the purchase file of the respondent-UOI behind
the back of petitioner-claimant's counsel. He stated that this amounted
to violation of principles of natural justice and Section 24 of Act, 1996.
In this connection, he placed reliance upon a judgment of this Court
passed in OMP No. 150/2000 titled as MP State Co-Operative Oil Seed
Growers' Fed. Ltd. Vs. Union of India & Anr. decided on 13th
November, 2009.
18. Mr. Khorana also contended that the Award was antedated as the
impugned Award had been despatched by the Arbitrator on 22nd
August, 2000 even though the Award was dated 4th August, 2000. In
this connection, Mr. Khorana relied upon the despatch envelope as well
as the petitioner-claimant's application dated 21st August, 2000 filed
before the Arbitrator.
19. Mr. Khorana further submitted that the Arbitrator had failed to
discharge his legal obligation as he had not called for record with
regard to manner of procurement of Barley even though the petitioner-
claimant had made an allegation in its written submissions with regard
to violation of undertaking by successful RP tenderers. Mr. Khorana
pointed out that the Arbitrator had failed to appreciate that petitioner-
claimant's lowest offer under the RP tender was ignored even though
petitioner-claimant had only asked for three to four days time to furnish
security. In this connection, Mr. Khorana relied upon the petitioner-
claimant's letter dated 27th May, 1997 which reads as under :-
"HO/FG/Barley/APO/96-97 27.5.1997
The Chief Director of Purchase,
Army Purchase Organisation,
Ministry of Defence,
Krishi Bhawan,
New Delhi - 110001
Sub: Supply of Barley to APO and trade enquiry No. J-12016/2/97-PUR-III dt. 2.4.1997
Dear Sir,
This is in continuation of our letter of even number dated 23.5.97. We have to inform you that we are ready and willing to furnish the security amount in any other form provided in the purchase tender enquiry. We should be given the time of 3-4 days to furnish the said security.
2. Awaiting for an early reply.
Thanking you,
Yours faithfully,
Sd/-
(S.C. SONDHI) GENERAL MANAGER (PUL)
20. According to Mr. Khorana, the impugned Award was a non-
reasoned one and further that the Arbitrator had given no reasons for
rejecting petitioner-claimant's claim for refund of liquidated damages
and security deposit amounts. In this connection, he relied upon a
judgment passed by a learned Single Judge of this Court in CS(OS)
449A/1997 titled as U.O.I. Vs. M/s. P.L.B. Industries decided on 26th
October, 2009.
21. On the other hand, Mr. A.S. Chandiok, learned Additional
Solicitor General for the respondent-UOI submitted that the petitioner-
claimant's allegation that the Arbitrator had perused the purchase file
behind the back of petitioner-claimant's counsel was frivolous and
baseless. In this connection, he referred to the reply filed by the
respondent-UOI to the present objection petition, which reads as
under:-
„REPLY TO THE GROUNDS
xxxx xxxx xxxx xxxx
It is submitted that all these averments of the Petitioner are absolutely preposterous, totally misleading and intentional misrepresentation of the facts and a clear cut suppression of the material on record. Further these are all very vague allegations without production of a single document in defence of their contentions. Hence these averments are vehemently denied by the Respondent. It is submitted that the petitioner in their written pleadings before the Sole Arbitrator alleged that vide their letter dated 02.07.96, they requested the Respondent for a Delivery Period extension without levying liquidated damages and produced before the Arbitrator in their written pleadings the copy of the letter as per their records. In the reply filed before the Arbitrator, the Respondent contended that in the letter received from the
Petitioner, the last five words - "without levy of Liquidated Damages" - were struck off before the letter was signed and sent to the Respondent and a copy of the said letter as available on the contract file,(as original files were seized by CBI after the Respondent retained the Photocopy of the contract files) was produced by the respondent before the learned arbitrator. Both these documents which were attached to the written pleadings to the Arbitrator in the very presence of the advocates on behalf of the Petitioner and pleaded with the Arbitrator to see for himself which party has tampered with the document. At this, the Petitioner‟s advocate wanted the original file from the Respondent to be submitted to the Arbitrator. The Respondent informed the Learned Arbitrator that the original files were seized by CBI in the criminal case registered by them against the Petitioner/Claimant, NAFED and hence only the photocopy of the contract file was available. In response to this pleading of the Respondent, the learned Arbitrator orally directed the Respondent to show him the photocopy of the contract file in the next hearing and adjourn the hearing. During the hearing, the learned Arbitrator never could suspect the integrity of the Officers of the Respondent and he made it clear in the hearing that the photocopy of the file would be enough for his perusal as he refused to suspect the Respondent and he also made it clear that in case if any doubt arises in his perusal of the file, he would be at liberty to call for the original file. Accordingly, during the next hearing, the Respondent produced the photocopy file to the learned Arbitrator in the very presence of the Petitioner and their advocates. Learned Arbitrator perused the document which was alleged by the Petitioner to have been tampered with and he also perused the document produced by the Petitioner along with their written pleadings. As a single glance at these two documents clearly reveals as to which party tampered with the document, the learned Arbitrator accepted the pleading of the Respondent that the document produced by the petitioner was the one which was tampered with and accordingly he summarily dismissed the allegation of the Petitioner that the document was tampered by the Respondent."
(emphasis supplied)
22. He further pointed out that even if petitioner-claimant's
allegation was correct, it did not cause any prejudice to petitioner-
claimant as the Arbitrator had not rendered any finding on the basis of
the said file.
23. Mr. Chandiok emphatically denied that the Award was antedated.
He drew my attention to Sub-sections (1) and (5) of Section 31of Act,
1996 to show that there was a distinction between despatch and writing
and signing of an arbitral award. According to Mr. Chandiok, the date
of despatch and the date of publishing of an award need not be the
same. He laid emphasis on the fact that the impugned Award had been
passed on stamp paper which had been purchased in the month of June,
2000. Mr. Chandiok also denied that respondent-UOI had ignored the
petitioner-claimant's lowest offer. In this connection, he referred to the
respondent-UOI's letter dated 22nd April, 1997, which reads as under :
Dated 22.4.97 To
M/s NAFED, 2423/29, Surekha Building, Shradhanand Marg, Delhi-6.
Subject:- Tender Enquiry for Risk Purchase of 2544.396 MT Barley against A/T No. J-13016/2/70/96- Pur III Dated 19.3.96 for Defence Services.
Dear Sir,
I am directed to invite your attention to this organisation‟s letter No.J-13016/2/70/96-Pur III dated 26.3.97 and to state that 2544.396 MT Barley against A/T No. J-13016/2/70/96-Pur III dated 19.3.96 was cancelled at your risk and cost. A copy of Tender Enquiry No. J-12016/2/97- Pur III dated 2.4.97 for repurchase of 2544.396 MT Barley is enclosed.
2. Your attention is also invited to clause 5 of the Invitation to Tender and Instructions to Tenderers and Clause 20 of the Terms and Conditions sent alongwith Tender Enquiry No. 12016/2/97-Pur III dated 2.4.97 which is reproduced below:-
"In case of risk purchase, if the quotation of the defaulting firm happens to be the lowest acceptable, they will be required to furnish security deposit equivalent to the difference between his quotation and the next best quotation or 10 % (Ten Percent) of the proposed contract value whichever is more by which their offer will be ignored and placement of the contract on the next best offer will be considered. Bank Guarantee will not be an acceptable form of Security Deposit."
3. This is without prejudice to the rights and remedies available to the Government under the terms and conditions of contract and any other rights which are hereby fully reserved.
Yours faithfully, Sd/-
(SUSHMA RATH) SECTION OFFICER (PURCHASE) FOR AND ON BEHALF OF THE PRESIDENT OF INDIA TELE: 3383911/4252
(emphasis supplied)
24. Mr. Chandiok pointed out that subsequent to the said letter, as
petitioner-claimant's offer was the lowest, respondent-UOI issued a
telegram dated 15th May, 1997 giving the petitioner-claimant time till
26th May, 1997 to furnish security in accordance with the tender terms.
He stated that it was not possible for the respondent-UOI to grant any
further extension of time for furnishing the security as offers received
under the RP tender were only valid upto 28th May, 1997.
25. Mr. Chandiok also contended that the Arbitrator was not obliged
to call for the record with regard to procurement of Barley under the RP
tenders as there was no challenge filed by petitioner-claimant before the
Arbitrator to the placement of RP tenders. In any event, he submitted
that even if there was any violation of any undertaking given by a third
party to the respondent-UOI, petitioner-claimant could not derive any
benefit from the same.
26. Mr. Chandiok also submitted that from a reading of the Award,
the thought process of the Arbitrator was clear. Mr. Chandiok stated
that the petitioner-claimant's claim for refund of liquidated damages
was baseless. He pointed out that the liquidated damages had been
deducted by respondent-UOI from the petitioner-claimant's running
bills without any protest. He laid emphasis on the fact that in none of
the contemporaneous correspondence exchanged between the parties,
petitioner-claimant had never raised any objection with regard to
periodic deduction of liquidated damages. Consequently, he submitted
that the petitioner-claimant had waived its rights to raise any objection
with regard to levy of liquidated damages.
27. Having heard the parties at length and having perused the
impugned Award, I am of the view that it would be appropriate to first
outline the circumstances in which a Court can interfere with an arbitral
award passed under the Act, 1996. The Supreme Court in Delhi
Development Authority Vs. R.S. Sharma and Company, New Delhi
reported in (2008) 13 SCC 80 after referring to a catena of judgments
including Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd.
reported in (2003) 5 SCC 705 has held that an arbitral award is open to
interference by a court under Section 34(2) of the Act, 1996 if it is:-
(i) contrary to substantive provisions of law; or
(ii) contrary to the provisions of the Arbitration and Conciliation Act, 1996; or
(iii) against the terms of the respective contract; or
(iv) patently illegal; or
(v) prejudicial to the rights of the parties.
28. The Supreme Court has further held in the aforesaid judgment
that an award can be set aside if it is contrary to:
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality.
29. In fact, the Supreme Court in McDermott International Inc. Vs.
Burn Standard Co. Ltd. & Ors. reported in (2006) 11 SCC 181 has
succinctly summed up the scope of interference by this Court by stating
" the 1996 Act makes provision for the supervisory role of courts, for
the review of the arbitral award only to ensure fairness. Intervention of
the court is envisaged in few circumstances only, like, in case of fraud
or bias by the arbitrators, violation of natural justice, etc......"
30. In fact, upon perusal of the arbitral record, it is apparent that the
petitioner-claimant failed to supply the contracted quantity of Barley
despite the delivery period being extended vide respondent-UOI's
letters dated 9th April, 1996, 28th May, 1996, 10th July, 1996, 20th
September, 1996, 22nd October, 1996 and 11th November, 1996.
Consequently, respondent-UOI in accordance with the contract rightly
cancelled the contract and floated a risk purchase tender after deduction
of liquidated damages.
31. Moreover, upon perusal of the Award, it cannot be assumed that
the Arbitrator had perused the files behind the back of petitioner-
claimant's counsel. Also, the said fact is vehemently denied by the
respondent-UOI in its reply to the present objection petition. Moreover,
even if the petitioner-claimant's allegation is taken to be correct, I am
of the view that files must have been perused by the Arbitrator by way
of abundant precaution. In any event, perusal of an official record
which has been contemporaneously maintained, cannot be termed as
either misconduct or violation of principles of natural justice especially
when the said record does not form the basis of any finding in the
impugned Award. Accordingly, the judgment relied upon by Mr.
Khorana has no application to the facts of the present case.
32. Further, petitioner-claimant's allegation that the Award had been
passed on 22nd August, 2000 to render infructuous petitioner-claimant's
application dated 21st August, 2000 is based on surmises and
conjunctures. I am also of the view that an award of this nature could
not have been passed in one day's time as alleged by learned counsel
for petitioner-claimant. I am of the opinion that the date of despatch of
Award would not prove that Award had been passed on the said date.
Writing, signing and publishing of an award is distinct from its
despatch as rightly pointed out by Mr. Chandiok. Sub-sections (1) and
(5) of Section 31 of Act, 1996 read as under :-
"31. Form and contents of arbitral award. -(1) An arbitral award shall be made in writing and shall be signed by the members of the arbitral tribunal.
xxxx xxxx xxxx xxxx
(5) After the arbitral award is made, a signed copy shall be delivered to each party.
33. I am also of the opinion that the Arbitrator rightly did not call for
the record with regard to manner of procurement of Barley by the
successful RP tenderers as, firstly, no such allegation had been made by
petitioner-claimant in its claim statement. Secondly, the said allegation
had not been substantiated by any evidence by petitioner-claimant.
Thirdly, there was no challenge by petitioner-claimant to the Award of
RP tenders. In any event, even if the RP tenderer had violated any term
of contract executed between them and respondent-UOI, petitioner-
claimant would not be absolved of its obligation to pay liquidated
damages. In fact, from the documents on record, it is apparent that the
petitioner-claimant's offer under the RP tender was not ignored by
respondent-UOI. On the contrary, in accordance with Clause 5 of the
Invitation to Tender and Instructions to Tenderers and Clause 20 of
Terms and Conditions of Tender Enquiry dated 2nd April, 1997,
petitioner-claimant was asked to furnish security by 26th May, 1997 -
which the petitioner-claimant admittedly failed to furnish.
34. I am further of the opinion that the respondent-UOI acted
reasonably and fairly in rejecting petitioner-claimant's request for
further extension of three to four days time as the offers received under
the RP tender were open only till 28th May, 1997 and in case orders had
not been placed on 27th May, 1997 against the RP tender, the whole RP
exercise would have had to be carried out once again.
35. I am also of the view that the petitioner-claimant's submission
that the impugned Award was a non-reasoned one and/or the Award did
not indicate the Arbitrator's thought process is contrary to facts and
untenable in law. An arbitrator is not expected to write a judgment like
a Court of law. Even though it is obligatory for an arbitrator to state
reasons, it is not obligatory for him to give a detailed judgment (refer to
Ircon International Ltd. Vs. Arvind Construction Company Ltd. &
Anr. reported in 1999 (81) DLT 268, Indian Oil Corporation Vs.
Indian Carbon Ltd. reported in AIR 1988 Supreme Court 1340 and
College of Vocational Studies Vs. S.S. Jaitely reported in AIR 1987
Delhi 134). In the present case, I find that the Arbitrator has given
cogent and concise reasons for allowing Counter Claim No.1 of
respondent-UOI and for rejecting petitioner-claimant's claims. In any
event, as held by the Supreme Court in M/s. Sudarshan Trading Co.
Vs. Government of Kerala and Anr. reported in (1989) 2 SCC 38,
reasonableness of reasons cannot be challenged in an objection petition
filed against an arbitral award.
36. As far as rejection of petitioner-claimant's claim for refund of
liquidated damages is concerned, I am of the opinion that the petitioner-
claimant was estopped from raising this claim as during the
contemporaneous period when liquidated damages were deducted,
petitioner-claimant had never raised any objection. Consequently, in
my view, petitioner-claimant has waived its right to claim refund of
liquidated damages. In any event, I find that petitioner-claimant did not
lead any evidence to show that petitioner-claimant had not breached its
original contract dated 19th March, 1996. In fact, as pointed out
hereinabove, petitioner-claimant had never challenged the award of RP
tender before the Arbitrator.
37. Consequently, keeping in view the aforesaid the impugned
Award dated 4th August, 2000 is upheld. Accordingly, present petition
is dismissed but with no order as to costs.
MANMOHAN,J MARCH 4, 2010.
rn
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!