Citation : 2010 Latest Caselaw 3450 Del
Judgement Date : 23 July, 2010
IN THE HIGH COURT OF DELHI AT NEW DELHI
W.P.(C) 9451/2009 & CM APPL Nos. 7309-12/2009
Reserved on: July 8, 2010
Decision on : July 23, 2010
D.D.BHALLA ..... Petitioner
Through Mr. Vinay Mohan Sharma with
Mr. Ravinder Yadav, Mr. Joydeep
Bhattacharya, Ms. Neha Sharma,
Ms. Shalini Agnihotri and
Mr. Anil Jain, Advocates
versus
AIRPORTS AUTHORITY OF INDIA
& ORS ..... Respondents
Through Ms. Anjana Gosain with
Ms. S. Fatima, Advocate
CORAM: JUSTICE S. MURALIDHAR
1. Whether Reporters of local papers may be
allowed to see the judgment? No
2. To be referred to the Reporter or not? No
3. Whether the judgment should be reported in Digest? No
JUDGMENT
23.07.2010
1. The Petitioner was awarded a contract by the Respondent No. 1
Airports Authority of India („AAI‟) for providing CNS facilities in the
new runway 29/11 at the IGI Airport, New Delhi on 3 rd November
2008 for an amount of Rs. 41,79,126/-. By the impugned order dated
19th March 2009, the AAI cancelled the said contract and the
Petitioner has filed this petition challenging the said order. Also
challenged in this writ petition is a show cause notice dated 6 th April
2009 issued by the AAI to the Petitioner asking him to show cause
why he should not be debarred from participating in the AAI Tenders
and the subsequent order dated 6th May 2009 passed by the AAI
debarring him from participating in AAI tenders for a period of three
years. The fourth prayer is for a direction to the Respondent AAI to
open the tenders of the Petitioner that have already been received but
not processed.
2. Mr. Vinay Mohan Sharma, learned counsel appearing for the
Petitioner first submits that a show cause notice dated 29th December
2008 issued by the AAI to the Petitioner has been taken as the notice
preceding the termination of the contract. AAI has proceeded on the
basis that the Petitioner‟s reply to the said show cause notice was not
found satisfactory. It is pointed out that the Senior Manager
Engineering (E) AAI, Respondent No. 4 herein, referred to a letter
dated 1st January 2009 of the Petitioner and described it as reply to the
show cause notice dated 29th December 2008 whereas that letter was
a request by the Petitioner for issuance of gate passes. It is claimed
that the dispute regarding non-supply of 13 qualified personnel by the
Petitioner was sorted out by the Petitioner with the Respondent at a
personal meeting on 30th and 31st December 2008 itself. Mr. Sharma
therefore, submits that any allegation contained in the show cause
notice dated 29th December 2008 stood wiped out and the said
document could not be relied upon. In fact subsequent thereto, on 16 th
January 2009 a formal agreement was signed between the parties. Mr.
Sharma submits that if the AAI proposed to terminate the contract
with reference to show cause notice dated 29th December 2008, it
could not have signed an agreement on 16th January 2009 with the
Petitioner herein. It is accordingly contended that there is no basis
whatsoever for cancelling the contract dated 19th September 2009.
3. According to the Petitioner, the action of Respondent No. 4 in
engineering the termination of the contract was malafide because the
Petitioner had in 2007 made a complaint against the misdeeds of
Respondent No. 4 in relation to tampering with the bids submitted
pursuant to the earlier tenders floated. The Petitioner also made a
specific complaint against one Shri V.K. Gupta regarding
reimbursement of certain payments. The third submission made by
Mr. Sharma is that the order dated 6th May 2009 debarring the
Petitioner from participating in the AAI tenders for a period of three
years is wholly without jurisdiction. It is submitted that the General
Manager Engg (E) was not the „accepting authority‟ and, therefore,
had no power to debar the Petitioner in terms of the contract. Such
power vested only with the Senior Manager Engg (E) i.e. the
Respondent No. 4.
4. Without prejudice to the above submissions, it is submitted that the
order dated 6th May 2009 "is conspicuously vague and essentially
non-speaking, arbitrary, unreasonable and discriminatory as it fails to
deal even with a single point/contention of the Petitioner raised by
him in his reply to show cause notice dated 6th April 2009." It is
submitted that the allegation that gate passes were only for five
persons and insufficient in terms of the contract was "taken wholly
out of context and without any relevance or linkage to the alleged
non-performance of contract by the Petitioner." It is the Petitioner‟s
case that he was never allowed to commence work in spite of repeated
requests. It is submitted that the Respondent No. 4 without the
Petitioner‟s consent extended another contract, namely, ARMO of 11
KV Sub-station Internal and External E.I., Operational area by one
month up to 5th April 2009 knowing fully well that the Petitioner had
to depute that staff for the contract in question i.e. provisions of CNS
facilities for new runway at IGI Airport. It is submitted that the
Petitioner had more than the requisite manpower to start the work. It
is submitted that the intimation regarding debarment of the Petitioner
was sent to other government departments where he had worked as a
contractor with a view to defame and embarrass him and tarnish his
reputation. It is submitted that the debarment of the Petitioner is
disproportionate and harsh.
5. It is submitted that the Petitioner has been singled out for the
purpose of debarment. Out of a total of five electrical contracts that
were cancelled on the ground that the work had not commenced, only
the Petitioner has been debarred. Finally, it is submitted that the
response of the vigilance department after rejecting the Petitioner‟s
complaint dated 5th February 2008 was an attempt to „cover-up‟ the
misdeeds of the Respondent No. 2 and this was surprisingly done on
the same date the Petitioner was debarred for a period of three years.
6. According to learned counsel for the Petitioner, the central issue in
the present case is that of corruption and when the Petitioner picked
up courage to point it out he was punished by the Respondents by not
only terminating his contract but debarring him from participating in
tenders for a period of three years. It is alleged that for the very same
work, a fresh contract consequent upon the termination of the
Petitioner‟s contract was awarded and the government exchequer
suffered a loss of over Rs.2.82 lakhs on that score.
7. In reply to above submission, Ms. Anjana Gosain, learned counsel
for the Respondents submits that the Petitioner was aware of the terms
and conditions of the contract on 3rd November 2008 itself and that it
was only a formal agreement which was required to be signed
subsequently. In terms of the contract, the Petitioner had to take over
the site on 18th November 2008. Despite reminders being sent on
several dates i.e. 12th, 24th and 25th November 2008, the Petitioner did
not take over the site. The work of runway 29/11 at the IGI airport
was a time bound one and no delay in commencing the work could be
tolerated. In those circumstances, another reminder was sent on 10th
December 2008 with a further request to send the stamp paper on
which the agreement had to be drawn. It was made clear that if the
labour was not deployed by 18th December 2008 a show cause notice
would be served.
8. Thereafter when no steps were taken, a show cause notice was
issued to the Petitioner on 29th December 2008 requiring a reply
within seven days. Although no formal reply was received, a letter
dated 1st January 2009 giving the names of five employees was
received. This was followed by letters dated 13th February 2009, 16th
February 2009 and 9th March 2009 giving details of the staff.
However, in these letters the Petitioner did not indicate the
preparedness to undertake the work. In view of the urgency and the
fact that the contract was a time-bound one, a letter terminating the
contract was issued and a short notice tender was floated on 20 th
March 2009.
9. Ms. Gosain submitted that since despite the first show cause notice
dated 29th December 2008 the Petitioner did not commence work, it
was decided to terminate the contract. Thereafter a show cause notice
dated 6th April 2009 was issued to the Petitioner to which a reply was
received on 13th April 2009. Consequent thereto, the impugned order
dated 6th May 2009 debarring the Petitioner for a period of three years
was passed.
10. Since the Petitioner had made serious allegations in his complaint
which included charges of corruption, his complaint was referred to
the Vigilance Department. The question of debarment of the Petitioner
was considered by a Committee of three persons. The decision was
left to the General Manager since the Petitioner had levelled
allegations against the accepting authority. This in fact demonstrated
the fairness of the procedure. Six months‟ time had been lost before
the debarment of the Petitioner. In the circumstances, it was submitted
by the learned counsel for the Respondent that the decision taken by
the AAI to terminate the contract debarring the Petitioner for a period
of three years was justified. She relied upon the judgment of this
Court in Integrated Techno Systems Pvt. Limited v. New Delhi
Municipal Council 143 (2007) DLT 541.
11. The Petitioner does not deny that at no point in time he was able
to provide 13 qualified persons as required under the contract. His
case was that he was prepared to provide five persons at any point in
time. Over three shifts he would provide ten. However, this did not
meet the requirement of having to make available 13 qualified persons
for the contract. Once having accepted the contract, the Petitioner
cannot go back and interpret the contract just to suit his convenience.
Clearly there was an unpreparedness on the part of the Petitioner to
undertake the work in terms of the contract.
12. This Court has considered the above submissions. The work of
construction of the new runway at the IGI airport is certainly a time
bound one. Any delay in the completion of the said work would entail
adverse consequences for the AAI including loss of time and money.
If the AAI insisted on zero tolerance in completing the work on time,
no fault can be found with such decision. If the AAI does take specific
action pursuant to its show cause notice dated 29th December 2008
then certainly such action could not be termed as arbitrary. It appears
that the Petitioner was nevertheless given sufficient opportunities to
fulfill its obligation.
13. Also the Petitioner‟s allegation that the action was malafide only
because he made a complaint of corruption against the senior officers
of AAI is also without merit. Those complaints were taken seriously
and examined by the Vigilance Department. The report of the
Vigilance Department showed that these complaints were not
substantiated. Faced with this situation, the Petitioner is now seeking
to blame the Vigilance Department for "covering up" the misdeeds of
the officials of the AAI. This Court fails to appreciate the Petitioner
not sparing the Vigilance Department as well. Such a plea has to be
substantiated by some positive material. The Petitioner has failed to
discharge the burden.
14. This Court has examined the decisions in Sahara India (Firm),
Lucknow v. Commissioner of Income Tax, Central-I (2008) 14 SCC
151, S. Brahmanand v. K.R. Muthugopal (Dead) (2005) 12 SCC
764, Tata Cellular v. Union of India (1994) 6 SCC 651, Meerut
Development Authority v. Association of Management Studies 2009
(6) SCALE 49, Southern Painters v. Fertilizers & Chemicals
Travancore Limited 1994 Supp (2) SCC 699, Mahabir Auto Stores v.
Indian Oil Corporation (1990) 3 SCC 752, Raghunath Thakur v.
State of Bihar (1989) 1 SCC 229 and Harbanslal Sahnia v. Indian
Oil Corporation Limited AIR 2003 SC 2120. While it is the settled
law, as explained in the above decisions that an instrumentality of the
State has to be fair and reasonable in its dealings, it is the validity of
the order of termination in the circumstances of the present case
which is required to be examined. In the considered view of this
Court, the Petitioner has not been able to persuade the Court to hold
that the action of the Respondent No. 1 terminating the contract and
debarring him for a period of three years suffers from unfairness or
arbitrariness. Further, no fault can be found with the procedure
adopted in arriving at the said decisions.
15. Consequently, this Court finds no merit in the writ petition. This
petition is dismissed with costs of Rs. 5,000/- which will be paid by
the Petitioner to the Respondents within a period of four weeks.
16. The writ petition and the pending applications are dismissed.
S. MURALIDHAR, J JULY 23, 2010 rk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!