Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Gee International vs Union Of India & Ors
2010 Latest Caselaw 374 Del

Citation : 2010 Latest Caselaw 374 Del
Judgement Date : 22 January, 2010

Delhi High Court
M/S Gee International vs Union Of India & Ors on 22 January, 2010
Author: Valmiki J. Mehta
*             IN THE HIGH COURT OF DELHI AT NEW DELHI

+                                OMP No. 40/2010

                                                    22nd January, 2010.
M/S GEE INTERNATIONAL                                                ...Petitioner

                           Through:     Dr. G.LAL, Advocate
              VERSUS

UNION OF INDIA & ORS                                                  ....Respondents

Through:

CORAM:

HON'BLE MR. JUSTICE VALMIKI J.MEHTA

1. Whether the Reporters of local papers may be allowed to see the judgment?

2. To be referred to the Reporter or not?

3. Whether the judgment should be reported in the Digest?

    %                            JUDGMENT (ORAL)

VALMIKI J.MEHTA, J



1. By this petition under Section 34, the petitioner challenges the Award dated

31.10.2009 of the sole Arbitrator.

2. The counsel for the petitioner has challenged the findings of the Arbitrator

with respect to Claim No.2(b), Claim No.2(d)(ix), Claim No. 4, Claim No.5, Claim

No.8 and Claim No.10.

OMP No.40/2010 Page 1

3. Claim No.2(b) is a dispute with respect to the award of the substituted work.

The originally contracted work was with respect to providing of precast RCC

manhole covers which was substituted with SFRC manhole covers. The Arbitrator

has given a finding of fact that an analysis of rates showed that payments ought to

have been at Rs.431.87 per manhole cover however by inadvertence and mistake in

the second running bill, payment was made at Rs.834.35 for each manhole cover.

The Arbitrator has therefore held that the petitioner cannot take advantage of the

mistake committed in payment. No factual challenge was laid before me as to why

the analysis of rates of Rs.431.87 was incorrect and why the mistaken rate of

Rs.834.35 per manhole cover is correct. There is, therefore, no illegality or

perversity so far as the finding qua this part of the Award is concerned. The

objection in this regard is rejected.

4. Claim No.2(ix) was with respect to claim of clearing of the road surface.

The Arbitrator has given a finding that claimant has not filed any details of

measurements for the quantity of 9000 sq. m. for which claims are made under

this head by the petitioner. During the course of hearing, I asked the counsel for

the petitioner to show me from the measurement book where this work is recorded

to which the counsel for the petitioner stated that the petitioner cannot be blamed

for the measurements not being recorded in the measurement book. I cannot

OMP No.40/2010 Page 2 understand this argument of the counsel for the petitioner because the Arbitrator

has given a finding that no such work, for which claim is being made has in fact,

been done to the extent of 9000 sq. m. and consequently, the Arbitrator has

rejected this claim. To upset such finding as perverse it was necessary to show that

as per the Measurement Book such work was recorded as being done, and which

is not being shown. Thus, no illegality or perversity in this regard can be said to

have been committed by the Arbitrator for this court to interfere with this part of

the Award. The objection with regard to this claim is also rejected.

5. Claim No.4 was on account of claim of interest of the petitioner for the

amount withheld by the respondent with respect to the third running bill. The

Arbitrator has in fact awarded this amount in favour of the petitioner and has

granted interest at 8% per annum. I, therefore, do not understand that what is the

dispute all about. The counsel for the petitioner sought to invite my attention to

Claim No.4 as made in the statement of claim which reads as under:-

"CLAIM NO.4:

While paying 3rd running account bills on 15.6.2006 the Respondents withheld Rs.1,09,261/-. The aforesaid amount was withheld without any rhyme and reason. The claimant was deprived of the use of this amount and hence is entitled to claim 18% interest. It is requested that the claim may please be decided in favour of the claimant. Interest is claimed from 15.6.2006 till the date of actual payment on Rs.1,09,261/-."

OMP No.40/2010 Page 3 These six lines of Claim No. 4 is again nothing but a claim for interest for

amount which has been withheld and which has been allowed by the Award

accordingly. I, therefore, do not find that the counsel for the petitioner is in any

manner justified in arguing that in view of the aforesaid para of the statement of

claim there is some sort of contradiction in the Award. The objection to this claim

is therefore rejected.

6. Claim No.5 was made by the petitioner before the Arbitrator for damages on

account of machinery and labour cost. The admitted fact is that the contract was

rescinded in 18.7.2006. Under this claim the vouchers which were filed for

claiming of the salary paid to the labour and the charges of the machinery, were 68

in number, and were in fact found not to be of before 18.7.2006 but of the

subsequent period between 7.12.2006 to 7.8.2007. The Arbitrator has then

observed while noticing over-writing on the vouchers that there does not arise any

question of any mistake of the dates because mistake in dates can occur once or

twice but not continuously in all the 68 vouchers. The Arbitrator has therefore held

that these vouchers were prepared in one go at the same point of time for claiming

of charges. No perversity or illegality can therefore be attributed to this finding of

the Arbitrator. Objection with respect to this claim is also rejected.

OMP No.40/2010 Page 4

7. Claim No.8 of the contractor was the claim for loss of profit. This loss of

profit has been denied by the Arbitrator to the contractor by very succinctly

referring to the gist of the legal position under Section 73 of the Contract Act, 1872

and by holding that the petitioner, except filing an arithmetic calculation, has not

proved the loss by showing that the men and machinery could have been use in any

other contract for earning profit. The following paragraph of the Award is relevant

in this regard.

"2.8.3 To provide legal cover to the claim of loss of profit for prolongation of contract, claimants have taken shelter under section 73 of the Indian Contract Act, 1872. Claimants have not placed any material on record to establish that had done planning to take up new works but had to resort to mid-course correction due to the prolongation of the work in question. What needs to be demonstrated is that preparations were made to take up some more works but the resources allegedly blocked in the work in hand came in the way to taking up new works. Claimants want to earn profit without making any effort and investment. This would amount to „unjust enrichment‟. It is well settled in law that even if the actual extent of loss cannot be determined , the party claiming compensation is entitled to succeed only on establishing that some loss was actually sustained. All that claimants have done is to calculate the projected loss only on the basis arithmetical calculations. No evidence of having actually suffered some loss has been brought on record. Thus claimants have failed to substantiate the claim legally as well as on the basis of facts and figures. I, therefore, do not award any sum of money against this claim."

Surely such clear cut finding cannot in any manner be said to as illegal or

perverse. Once the contractor fails to file any proof, surely, an Arbitrator is fully

justified in dismissing a claim which was only hypothetical. Objection to this

claim is also rejected.

OMP No.40/2010 Page 5

8. Claim No.10 is the cost of Arbitration. Costs are in the discretion of the

forum before which the proceedings are conducted. The Arbitrator has denied the

cost of the proceedings to the petitioner. I do not find any illegality with regard to

disallowing of cost to the petitioner.

9. In view of the above, I do not find any merit in the objection petition of the

contractor which is dismissed with costs of Rs.25,000/- to be paid in favour of the

Registrar General of this Court for being utilized towards Juvenile Justice within a

period of two weeks from today.

I.A.No. 729/2010 in OMP No. 40/2010

10. Since the petition is dismissed, this application does not survive and is

disposed of as such.




                                                     VALMIKI J.MEHTA, J


January 22, 2010
ib




OMP No.40/2010                                                                  Page 6
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter