Citation : 2010 Latest Caselaw 206 Del
Judgement Date : 15 January, 2010
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ FAO(OS) 434/2009
M/S JIALALL KISHORI LALL PVT. LTD. ..... Appellant
Through: Mr. T.K. Ganju, Sr. Adv. with Ms. Divya Kesar,
Adv.
versus
MUNICIPAL CORPORATION OF DELHI ..... Respondent
Through: Mr. H.S. Phoolka, Sr. Adv. with Ms. Mini
Pushkarna, Adv.
CORAM:
HON'BLE THE CHIEF JUSTICE
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
ORDER
% 15.01.2010
This appeal under Section 37 of the Arbitration Act, 1996 has been preferred
against the dismissal of petition for interim measures under Section 9 of the Act. The
Appellant sought to restrain the Respondent MCD from invoking or receiving payments
under the bank guarantees for mobilization advance furnished at the instance of the
Petitioner to the Respondent MCD. The learned single Judge finding no case of fraud or
irretrievable injustice having been made out, dismissed the petition.
2. This Court while issuing notice of the appeal to the Respondent on 24th
September, 2009 recorded the statement of the counsel for the Appellant that the bank
guarantees in question shall be kept alive. On the said statement, encashment of the bank
guarantee was stayed. On 8th January, 2010 it was stated by the counsel for the
Respondent MCD that the Appellant had failed to keep the bank guarantees alive. The
matter was as such posted for 11th January, 2010. The senior counsel for the Appellant
on 11th January, 2010 informed that the bank guarantees had been got revalidated and
shall be kept alive as assured to this Court. The senior counsel for the parties have been
heard.
3. The contention of the senior counsel for the Appellant is that the bank guarantees
are titled "Bank guarantee for mobilization advance"; it is contended that such bank
guarantees are obtained and furnished to secure the mobilization advance. It is further
contended that however the invocation of the bank guarantee is not for non-utilization or
mis-appropriation of mobilization advance but for other reasons. Reliance is placed on
the letter dated 30th March, 2009 of the MCD of invocation of the bank guarantees and
wherein it is stated that the Appellant has failed to complete the work within the agreed
time and 10% compensation had been levied on the Appellant for delay in work and
which the Appellant had failed to pay to MCD. It is contended that the bank guarantees
could be invoked only for recovery of unutilized mobilization advance or on account of
mis-appropriation thereof and not for recovery of liquidated damages for the alleged
delay in completion of the work. Reliance is placed on Hindustan Construction
Company Limited v. State of Bihar, (1999) 8 SCC 436 in this regard. To satisfy the
conscience of this Court that the entire mobilization advance has been already recovered,
reference is made to the letter dated 3rd July, 2009 of the MCD to the Appellant
confirming that 32% of the work had been executed and furnishing particulars of the final
measurements. It is contended that not only has the mobilization advance against which
the guarantees were furnished been so recovered by the MCD but there are unpaid bills of
the Appellant against the MCD.
4. The invocation letter dated 30th March, 2009 (supra) relied upon by the Appellant
is in continuation of the earlier letter dated 27th March, 2009. The counsel for the
Respondent during the hearing has handed over in Court a copy of the letter dated 27th
March, 2009 of the MCD to the bank. In the said letter, the reason for encashing the
bank guarantee is given as the Appellant having failed to utilize the said advance for the
purposes of the contract. In view of the letter dated 27th March, 2009 which was
suppressed by the Appellant, we are satisfied that the bank guarantee has been invoked
stating the reason as failure of the Appellant to utilize the mobilization advance for the
purposes of the contract. The argument of the Appellant of the invocation being not in
accordance with the terms of the guarantee thus disappears. In terms of the Bank
guarantees, the Respondent is the sole judge of as to whether the Appellant has utilized
the said advance for the purposes of the contract or not and demand of the Respondent is
conclusive on the Bank.
5. We may also notice that the bank guarantees though titled as for mobilization
advance and in recitals guaranteeing the due recovery by the MCD of the said advance
with interest, in para 2 thereof state as under :
"We, the Corporation Bank further agree that the MCD shall be the sole judge of and as to whether the said Contractor has not utilized the said advance or any part thereof for the purpose of the Contract and the extent of loss or damage caused to or suffered by the MCD on account of the said advance together with interest now being recovered in full and the decision of the MCD that the said Contractor has not utilized the said advance or any part thereof for the purpose of the Contract and as to the amount or amounts of loss or damages caused to or suffered by the MCD shall be final and binding on us."
6. It would, thus, be seen that the Respondent MCD was entitled to invoke the
guarantee either for the reason of the Appellant having not utilized the said advance or
any part thereof for the purposes of the contract or also for the recovery of loss for
damage caused to or suffered by the MCD on account of the non-utilization of the
advance. Else the guarantees are unconditional and the Bank had undertaken to make the
payment on demand by the MCD and irrespective of any disputes whatsoever between
the Appellant and the Respondent MCD.
7. The judgment in Hindustan Construction Company Limited (supra) records that
the bank in that case had qualified its liability to pay the amount covered by the guarantee
only if the obligations under the contract were not fulfilled or if any part of the
mobilization advance was misappropriated. On such language of the bank guarantee, the
Supreme Court held the bank guarantee to be not unconditional or unequivocal and the
invocation having been found to be not in accordance with the bank guarantee, was
stayed. However, as noticed above this is not the position here. The bank has guaranteed
payment on the mere statement of the MCD that the Appellant has not utilized the said
advance or any part thereof or that any loss or damage has been suffered by the MCD on
account of the said advance. The letter dated 27th March, 2009 read with the letter dated
30th March, 2009 is found to be in consonance with the terms of the bank guarantee.
Further the bank guarantee is not found to be conditional as in the case before the
Supreme Court. Further, as noticed in the subsequent judgment in Vinitec Electronics
Pvt. Ltd. v. HCL Infosystems Ltd., (2008) 1 SCC 544, in Hindustan Construction Co.
Ltd. case (supra), Clause 9 of the main contract between the parties providing for refund
of mobilization advance in the case of mis-appropriation thereof, was incorporated in the
Bank guarantee therefore and it was for this reason that the Bank guarantee was not held
to be unconditional and held to be invocable only in the circumstances mentioned in the
said Clause 9. The Supreme Court in Vinitec Electronics Pvt. Ltd. (supra), did not find
specific reference to any clause of the main contract in the Bank guarantee in that case
and also did not find reference to any conditions for payment in the operative clause of
the Bank guarantee and thus held the judgment in Hindustan Construction Co. Ltd. to be
not applicable. The same is the position in this case.
8. The law with respect to bank guarantee otherwise not permitting the interim
measures sought, there is no merit in the appeal. The same is dismissed.
CHIEF JUSTICE
RAJIV SAHAI ENDLAW, J JANUARY 15, 2010 dk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!