Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Jialall Kishori Lall Pvt. Ltd. vs Municipal Corporation Of Delhi
2010 Latest Caselaw 206 Del

Citation : 2010 Latest Caselaw 206 Del
Judgement Date : 15 January, 2010

Delhi High Court
M/S Jialall Kishori Lall Pvt. Ltd. vs Municipal Corporation Of Delhi on 15 January, 2010
Author: Ajit Prakash Shah
*        IN THE HIGH COURT OF DELHI AT NEW DELHI

+        FAO(OS) 434/2009

         M/S JIALALL KISHORI LALL PVT. LTD.                  ..... Appellant
                          Through: Mr. T.K. Ganju, Sr. Adv. with Ms. Divya Kesar,
                          Adv.

                       versus

         MUNICIPAL CORPORATION OF DELHI                     ..... Respondent
                        Through: Mr. H.S. Phoolka, Sr. Adv. with Ms. Mini
                        Pushkarna, Adv.

         CORAM:
         HON'BLE THE CHIEF JUSTICE
         HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW


                       ORDER

% 15.01.2010

This appeal under Section 37 of the Arbitration Act, 1996 has been preferred

against the dismissal of petition for interim measures under Section 9 of the Act. The

Appellant sought to restrain the Respondent MCD from invoking or receiving payments

under the bank guarantees for mobilization advance furnished at the instance of the

Petitioner to the Respondent MCD. The learned single Judge finding no case of fraud or

irretrievable injustice having been made out, dismissed the petition.

2. This Court while issuing notice of the appeal to the Respondent on 24th

September, 2009 recorded the statement of the counsel for the Appellant that the bank

guarantees in question shall be kept alive. On the said statement, encashment of the bank

guarantee was stayed. On 8th January, 2010 it was stated by the counsel for the

Respondent MCD that the Appellant had failed to keep the bank guarantees alive. The

matter was as such posted for 11th January, 2010. The senior counsel for the Appellant

on 11th January, 2010 informed that the bank guarantees had been got revalidated and

shall be kept alive as assured to this Court. The senior counsel for the parties have been

heard.

3. The contention of the senior counsel for the Appellant is that the bank guarantees

are titled "Bank guarantee for mobilization advance"; it is contended that such bank

guarantees are obtained and furnished to secure the mobilization advance. It is further

contended that however the invocation of the bank guarantee is not for non-utilization or

mis-appropriation of mobilization advance but for other reasons. Reliance is placed on

the letter dated 30th March, 2009 of the MCD of invocation of the bank guarantees and

wherein it is stated that the Appellant has failed to complete the work within the agreed

time and 10% compensation had been levied on the Appellant for delay in work and

which the Appellant had failed to pay to MCD. It is contended that the bank guarantees

could be invoked only for recovery of unutilized mobilization advance or on account of

mis-appropriation thereof and not for recovery of liquidated damages for the alleged

delay in completion of the work. Reliance is placed on Hindustan Construction

Company Limited v. State of Bihar, (1999) 8 SCC 436 in this regard. To satisfy the

conscience of this Court that the entire mobilization advance has been already recovered,

reference is made to the letter dated 3rd July, 2009 of the MCD to the Appellant

confirming that 32% of the work had been executed and furnishing particulars of the final

measurements. It is contended that not only has the mobilization advance against which

the guarantees were furnished been so recovered by the MCD but there are unpaid bills of

the Appellant against the MCD.

4. The invocation letter dated 30th March, 2009 (supra) relied upon by the Appellant

is in continuation of the earlier letter dated 27th March, 2009. The counsel for the

Respondent during the hearing has handed over in Court a copy of the letter dated 27th

March, 2009 of the MCD to the bank. In the said letter, the reason for encashing the

bank guarantee is given as the Appellant having failed to utilize the said advance for the

purposes of the contract. In view of the letter dated 27th March, 2009 which was

suppressed by the Appellant, we are satisfied that the bank guarantee has been invoked

stating the reason as failure of the Appellant to utilize the mobilization advance for the

purposes of the contract. The argument of the Appellant of the invocation being not in

accordance with the terms of the guarantee thus disappears. In terms of the Bank

guarantees, the Respondent is the sole judge of as to whether the Appellant has utilized

the said advance for the purposes of the contract or not and demand of the Respondent is

conclusive on the Bank.

5. We may also notice that the bank guarantees though titled as for mobilization

advance and in recitals guaranteeing the due recovery by the MCD of the said advance

with interest, in para 2 thereof state as under :

"We, the Corporation Bank further agree that the MCD shall be the sole judge of and as to whether the said Contractor has not utilized the said advance or any part thereof for the purpose of the Contract and the extent of loss or damage caused to or suffered by the MCD on account of the said advance together with interest now being recovered in full and the decision of the MCD that the said Contractor has not utilized the said advance or any part thereof for the purpose of the Contract and as to the amount or amounts of loss or damages caused to or suffered by the MCD shall be final and binding on us."

6. It would, thus, be seen that the Respondent MCD was entitled to invoke the

guarantee either for the reason of the Appellant having not utilized the said advance or

any part thereof for the purposes of the contract or also for the recovery of loss for

damage caused to or suffered by the MCD on account of the non-utilization of the

advance. Else the guarantees are unconditional and the Bank had undertaken to make the

payment on demand by the MCD and irrespective of any disputes whatsoever between

the Appellant and the Respondent MCD.

7. The judgment in Hindustan Construction Company Limited (supra) records that

the bank in that case had qualified its liability to pay the amount covered by the guarantee

only if the obligations under the contract were not fulfilled or if any part of the

mobilization advance was misappropriated. On such language of the bank guarantee, the

Supreme Court held the bank guarantee to be not unconditional or unequivocal and the

invocation having been found to be not in accordance with the bank guarantee, was

stayed. However, as noticed above this is not the position here. The bank has guaranteed

payment on the mere statement of the MCD that the Appellant has not utilized the said

advance or any part thereof or that any loss or damage has been suffered by the MCD on

account of the said advance. The letter dated 27th March, 2009 read with the letter dated

30th March, 2009 is found to be in consonance with the terms of the bank guarantee.

Further the bank guarantee is not found to be conditional as in the case before the

Supreme Court. Further, as noticed in the subsequent judgment in Vinitec Electronics

Pvt. Ltd. v. HCL Infosystems Ltd., (2008) 1 SCC 544, in Hindustan Construction Co.

Ltd. case (supra), Clause 9 of the main contract between the parties providing for refund

of mobilization advance in the case of mis-appropriation thereof, was incorporated in the

Bank guarantee therefore and it was for this reason that the Bank guarantee was not held

to be unconditional and held to be invocable only in the circumstances mentioned in the

said Clause 9. The Supreme Court in Vinitec Electronics Pvt. Ltd. (supra), did not find

specific reference to any clause of the main contract in the Bank guarantee in that case

and also did not find reference to any conditions for payment in the operative clause of

the Bank guarantee and thus held the judgment in Hindustan Construction Co. Ltd. to be

not applicable. The same is the position in this case.

8. The law with respect to bank guarantee otherwise not permitting the interim

measures sought, there is no merit in the appeal. The same is dismissed.

CHIEF JUSTICE

RAJIV SAHAI ENDLAW, J JANUARY 15, 2010 dk

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter