Citation : 2010 Latest Caselaw 946 Del
Judgement Date : 18 February, 2010
* HIGH COURT OF DELHI : NEW DELHI
+ OMP No.469/2006
Gas Authority India Ltd. ...Petitioner
Through : Mr. Prag P. Tripathi, ASG with
Mr. Atul Sharma and Ms.
Arti Gupta, Advs.
Versus
M/s. Himachal Futuristic
Communications Ltd. ...Respondent
Through : Mr. Biswajit Bhathacharya, Sr. Adv.
with Mr. Debashis Mukherjee and
Mr. Ajay Singh, Advs.
Decided on: February 18, 2010
Coram:
HON'BLE MR. JUSTICE MANMOHAN SINGH
1. Whether the Reporters of local papers may
be allowed to see the judgment? No
2. To be referred to Reporter or not? Yes
3. Whether the judgment should be reported Yes
in the Digest?
MANMOHAN SINGH, J.
1. The present petition has been filed by the Petitioner under
Section 34 of the Arbitration and Conciliation Act, 1996 for setting aside
of the arbitral awards dated 16th November, 2005 and 2nd June, 2006
whereby the learned Arbitrator awarded to the claimant a sum of Rs.
1,10,96,933/- (as value of work completed) and Rs. 40,77,290/-
(encashment of bank guarantee along with interest) and allowed the
counter claim of only Rs. 6,00,000/- out of the total amount of the
counter claim i.e. Rs. 6,14,19,981/-.
2. The brief facts of the matter necessary for considering the
present petition are thus. The Petitioner issued a tender for the laying of
HDPE Duct, blowing and splicing of Optical Fiber Cable („OFC‟ for
brevity). The offer of the respondent was accepted and a letter of intent
dated 15th March, 2002 was issued by the Petitioner to the respondent for
laying of permanently lubricated HDPE Duct and splicing of OFC for
the stretch of Thane-Lonavale (85 Km.) and Lonavale-Pune (80 Km.)
The parties entered into a contract on 20th May, 2002. As per the
contract, the period for completion of the work was six months from the
date of issuance of the letter of intent, i.e. on or before 15th September,
2002. As per the contract, various permissions were to be obtained by
the respondent for furtherance of the work, including permissions from
Government departments and corporations.
3. The Petitioner sent a letter dated 3rd April, 2002 to the
Government of Maharashtra asking its permission to lay the OFC, at the
same time sending a copy of the letter to the respondent and asking it to
follow up with the same. The Petitioner also requested the respondent to
submit the details of the length of the stretch to be built based on the
route survey to the Government of Maharashtra in the permitted format.
The Government of Maharashtra vide letter dated 29th April, 2002 asked
the Petitioner to submit the route details etc, i.e. the details that the
Petitioner had asked the respondent to submit. Due to such permission
related and other problems, the contracted work was not completed till
the designated time, i.e. 15th September, 2002. Thereafter, the Petitioner
extended the time for completion of the project till 2nd December, 2002.
Since the work was incomplete even after that, the date of completion
was provisionally extended up till 31st December, 2002. The work being
incomplete, the parties continued to exchange correspondence and the
respondent sought another extension up to 30th April, 2003. Vide its
letter dated 7th February, 2003, the Petitioner warned the respondent that
non-progress of the work and stagnation in the same might constrain the
Petitioner to get its work done through another agency. The respondent
reiterated that it would complete the work in its letter dated 12th
February, 2003.
4. However, the Petitioner did not grant any further extension
and by its letter dated 25th February, 2003 terminated the contract
between the parties in accordance with Clause 29 of the General
Conditions of Contract as in 11 months, the respondent had been able to
complete only 82 of the 157 kilometers of the stretch to be constructed,
i.e. less than 35% of the total work had been done.
5. The Petitioner thereafter followed the due process of
tendering and awarded the balance work to a new contractor. Further, the
performance guarantee was encashed by the Petitioner as provided for in
the contract. The Petitioner suffered heavy losses due to the inaction and
incompetence of the respondent on account of which the respondent was
asked to pay damages worth Rs. 2 Crore, which the respondent has
failed to pay.
6. Thereafter the respondent herein filed a claim before the
learned Arbitrator praying for an award of Rs. 490,17,404/- in its favour
as opposed to which the Petitioner herein filed its counter claim for Rs.
620,19,981/-. At the end of the arbitral proceedings, the Learned
Arbitrator passed an award of Rs. 1,10,96,933/- in favour of the
respondent on account of value of work done and Rs. 40,77,290/- on
account of encashment of bank guarantee along with interest and
rejected the counter claims of the Petitioner.
7. The Petitioner moved an application under Section 33 of the
Arbitration and Conciliation Act, 1996 for correction of the arbitral
award on 15th December, 2005. Thereafter, the respondent also moved
an application under Section 33 of the Arbitration and Conciliation Act,
1996 for correction of the arbitral award on 21st December, 2005. These
applications were decided by the learned Arbitrator vide award dated 2nd
June, 2006.
8. By this award, the Learned Arbitrator reconsidered and
allowed the Petitioner‟s counter claim no. 2 to the extent of Rs.
6,00,000/- which was directed to be adjusted from the amount payable
by the Petitioner out of the total counter claim of the sum of Rs.
6,20,19,981/-. The respondent had, in its application, pointed out an
arithmetic error and the same was corrected. After deducting the amount
allowed for counter claim no. 2, the learned Arbitrator held that the
amount payable to the respondent would be Rs. 1,04,96,933/-.
9. It is submitted by the Petitioner that the arbitral awards dated
16th November, 2005 and 2nd June, 2006 must be set aside as the learned
Arbitrator has failed to appreciate the material fact that the Petitioner
suffered heavy losses due to the inaction of the respondent. The
respondent raised the issue of agreement with the Government of
Maharashtra in August 2002, i.e. one month before the completion of
time of the project stating that the requisite permissions from the latter
were pending supply of a copy of the agreement to it. It is stated that the
said excuse is sham and is bogus. The learned Arbitrator has further
failed to appreciate that the delay caused in the working of the project
could not have been due to the Petitioner as it was the obligation of the
respondent to obtain all the necessary permissions, in which obligation
the respondent failed and therefore, the learned Arbitrator erred in
holding that the Petitioner was partly to be blamed.
10. It is alleged that there are certain contradictions in the arbitral
award dated 16th November, 2005 in so far as the learned Arbitrator has
given a finding at page 17 of the award that the work schedule has not
been followed by the respondent but has then given the ultimate finding
that the Petitioner contributed to the delay. It is argued by the Petitioner
that if a party is responsible for the delay, it cannot avail the benefit of
delay as held by this Court in the case of Mecon Ltd. Vs. Pioneer
Fabricators Pvt. Ltd., 2007(4) Arb.L.R. 323 (Delhi) at page 338
para 31. As per Petitioner, the learned Arbitrator completely
overlooked the fact that the Petitioner had been reminding the
respondent from day one that it had to obtain the requisite permissions in
spite of which the respondent did nothing to change its lackadaisical
manner. Further, on the one hand the learned Arbitrator has held that the
termination of contract by the Petitioner was legal and justified but on
the other hand, damages have not been awarded to the Petitioner for the
losses suffered by it and in fact, encashment of bank guarantee has been
held to be bad.
11. The amount awarded to the respondent was not as per the
agreed tender rates and the same was awarded at an increased rate.
12. It was further submitted that the learned Arbitrator went
beyond the scope of reference in observing that the Petitioner, instead of
giving 2-3 months extension to the respondent, cancelled the contract
and awarded the new tender to some other contractor.
13. It is argued that the learned Arbitrator failed to appreciate
that the respondent came to know/understand about the requirement of
the agreement with the GoM only on 20th September, 2002 despite being
reminded by the Petitioner repeatedly from day one, which proves that
the respondent was not aware of the requirement for completion of
project which caused the delay in the implementation of project. The
Petitioner suffered due to the delay caused by the respondent in
implementation of the project.
14. It is also contended by the Petitioner that the learned
Arbitrator passed the award on the premises that the Petitioner was
under an obligation to take permission and enter into an agreement
with the Government of Maharashtra. Whereas under the contract
volume 2 of 2, chapter 3, 3.0 Scope of Work, Clause 3.1.1.1A, inter alia,
it states that to seek ROW/permission was in the scope of the
contractor/respondent herein. Not only this, even the parties to the
contract acted and understood the contract as above. The Petitioner
told the respondent repeatedly to take permission from the GoM and as
per its own admission, the respondent had been pursuing the
GoM/ROU authorities. As such the above finding is contrary to the
terms of the contract and liable to be set aside.
15. The Arbitrator on one hand held the termination of the
contract/tender by the Petitioner as legal and justified and on the other
hand rejected the counter claim of damages and losses of the Petitioner
suffered by it due to the delay and non completion of the work in terms
of the tender.
16. It is argued that since the learned Arbitrator held the
termination of contract valid, not upholding the invocation of contract
performance bank guarantee of Rs.40,77,290/- is bad and contrary to the
findings, therefore, the award is liable to be set aside.
17. It is further argued by learned counsel for the Petitioner that
the arbitral awards dated 16th November, 2005 and 2nd June, 2006 ought
to be set aside as only those bills were to be admitted which had been
jointly signed by both the parties. In fact, the learned Arbitrator decided
upon the sum of Rs. 1,45,55,204/- stating it to be on the basis of joint
admission/statement of the parties despite the fact that some of the bills
were not signed by both parties and were even denied by the Petitioner.
18. In its reply, the respondent has submitted that the averments
made in the present petition are bald averments, none of which can
invoke the jurisdiction of this Court under Section 34 of the Arbitration
and Conciliation Act as no ground raised by the Petitioner falls under the
circumstances carved by the Apex Court for setting aside of an arbitral
award under Section 34 of the Arbitration and Conciliation Act.
19. The respondent submitted that the learned Arbitrator has
considered all aspects, contractual terms, principles enunciated in case
laws propounded by the Supreme Court, and has then given an
interpretation in favour of the claimant. The learned counsel for the
respondent relied upon several case laws to contend that a Civil Court
has very limited jurisdiction to interfere with an arbitral award.
20. It is submitted by the respondent that its claim has been
allowed only in respect of item Nos. 1(i), 1(ii), 4 and 5. With regard to
item numbers 1(i) and 1(ii), it is submitted that the work done by the
claimant has been jointly valued and certified by the claimant and TCIL
(the agency which was overlooking the work done for the Petitioners).
Thus, this claim has been granted by the learned Arbitrator on the basis
of admitted joint measurement done along with Project Manager, TCIL
and the Petitioner. No exception can be taken to this finding of the
learned Arbitrator.
21. The learned counsel for the respondent submitted that it was
disabled by the Petitioner from performing the contract within the
scheduled time. The learned Arbitrator held that delay had indeed been
caused due to the fault of the Petitioner, and in fact, by the acts of both
sides. It has been further submitted that the value of the work executed
by the claimant amounts to Rs.1.75 crores but it has been paid only
Rs.31.7 lac and thus the expenditure involved in execution of the
balance job is expected to be partly covered through the payments due
to the claimant by way of unpaid jobs and encashment of bank guarantee
for security deposit available with GAIL.
22. The respondent objected to the present petition on the
grounds, inter alia, that the petition is not maintainable as it questions
interpretation of the contract which is in the exclusive domain of the
Arbitrator. While disposing of the application under Section 33 of the
Arbitration and Conciliation Act, 1996, filed by GAIL, it has been
conceded/admitted by GAIL as follows :
".....it is this figure [Rs.1,07,72,403/-] which should have been awarded rather than Rs.1,45,55,204/-". At this page 116, it has been further conceded/admitted by GAIL as follows :
".....measurement certified by both sides is
Rs.1,07,72,403/-"
The learned Arbitrator further held as follows :
"......during the arguments....certification was admitted by both sides."
23. I have perused the contentions of both the parties. One of the
disputes between the parties is that as per the Petitioner, two of the bills
which have led to the amount awarded i.e. 1,45,55,204/-have not been
signed by its representative/project manager and therefore, the same
cannot be deemed to be „admitted‟ or „joint certification‟ of both the
parties.
24. The Petitioner‟s main contention is that the two bills of the
amounts Rs. 87,35,714/- and Rs. 58,19,489/- have not been signed by its
Project Manager and therefore cannot be a „joint‟ admission, it is very
clearly observed with regard to these two bills in the arbitral award dated
2nd June, 2006 (page 2 thereof) as follows :
"I may, in this connection, clarify that during the arguments reference was made to these pages and the certification was admitted by both the sides. Along with the papers at pg. 698 Vol. II a figure of Rs. 87,35,714/- was mentioned as an amount due on account of Thane-Lonewale section. Similarly, at pg. 701 a figure of Rs. 58,19,489.91/- was given as Lonewale-Pune section. My recollection is that though the GAIL had certainly mentioned that the figure at pg. 698 and 701 bore the endorsement both of Project Manager, GAIL and TCIL but it was not signed, of course GAIL had denied any certification by TCIL. But no attempt was made to produce from the record or from any witness that these calculations which bear the Project Manager‟s endorsement was not signed by anyone on behalf of GAIL. I, therefore, took it that this figure of Rs. 14555204/-, represented the amounts due on account of work done as certified at pages 698, 699, 700, 702 and 703. ........
As no objection was raised at that time and the claimant has not claimed beyond that amount and the four payments mentioned, thus making a total of Rs. 1,45,55,203,/-, no discussion took place on these items. But if GAIL had sought to reduce this amount awarded by me and it would have open to the claimant to justify the said amount by invoking the items mentioned at pg. 698 and 701 as mentioned earlier. GAIL before me has not disputed the
figures and the details of the survey and ROU bills. Its only objection being that the amounts could only be paid if the claimant had completed the work satisfactorily. This argument has already been rejected by me."
25. The learned Arbitrator considered the amount of
Rs.1,45,55,204/- as reasonable because Tender Committee of GAIL
admitted that :
"Value of job executed by M/s. HFCL is Rs.1.75 crore."
Further, the question of the two bills being signed/unsigned
has been brought up before the learned Arbitrator in the application
under Section 33 of the Arbitration and Conciliation Act and the learned
Arbitrator has given a speaking order as regards the same.
26. It appears that the amount awarded by the leaned Arbitrator
has been awarded on the basis of admission and evidence and therefore
cannot be interfered with under the law.
27. The next question involved in the matter is as to whether
signing of agreement with GoM was a pre-requisite for entering into a
contract with HFCL and also for obtaining ROU/ROW permission from
various authorities. The case of the respondent before the Arbitrator was
that the agreement with the GoM was mandatory before any work could
be started and until that was done by the respondent, the work could not
have been contracted. On the other hand the case of the petitioner is that
the agreement with GoM was an independent agreement and had nothing
to do with the responsibility of the HFCL for obtaining ROW/ROU and
hence delay in signing the agreement with GoM, even if correct, has no
relevance in determining the question of delay. The learned Arbitrator,
after hearing the learned Counsel for the parties, has relied upon GoM
Resolution dated 22.11.2001 which inter alia reads as under:
"...Public Works Deptt. Zilla Parishads, Municipal Authorities, Revenue and Forest Departments, other Govt. and Semi Govt. bodies will give permission to lay cable/duct only after applicant entities have entered into agreement with the Govt. for obtaining such Right of way (emphasis supplied)."
28. It is also held that there was no way in law that the ROW
permission could be granted prior to the signing of agreement with
GoM. The learned Arbitrator has also given his findings in this regard,
the relevant portion of which reads as under:
"....it cannot thus be denied that agreement with GoM in terms of GoM Resolution dated 22.11.2001 was essential before any authorities could give permission to lay cables...admittedly land belonging to NHAI fell within Thane to Pune in the State of Maharashtra. GoM Resolution of 22.11.2001 makes no distinction who was in the management or to whom the land belonged. The mere fact of land belonging to NHAI did not take it out of the purview of GoM Resolution of 22.11.2001."
29. The learned Arbitrator has given his finding that signing of
agreement with GoM in terms of resolution dated 22.11.2001 was
necessary condition for obtaining ROW/ROU from various authorities
including NHAI and in view of that, GoM agreement was signed in
September/October which necessarily delayed the matter. It was also
observed by the Arbitrator that no work could be done even though
permission had been taken from the authorities concerned till the
agreement was signed by GoM and GAIL and the same process was
completed in September/October, 2002. Therefore, the respondent could
not have even commenced work before September/October, 2002 when
the petitioner and GoM executed the contract in terms of GoM resolution
dated 22.11.2002. Therefore, the Arbitrator has given the specific
finding that blame has to be placed on both the sides. Not only that, the
learned Arbitrator has commented upon the conduct of the petitioner
while terminating the contract and assigned reason in various paragraphs
of the Award as regards the said delay and then held that since both
parties were to blame for the delay, no party could claim damages.
30. The finding of the learned Arbitrator appears to be legally
sound and reasonable and cannot be interfered with as counter claims
have been rejected since these arose out of the same issues and are
based on no evidence. The next point for discussion in the matter is
about Claim No.4 i.e. performance of Bank Guarantee encashment. The
following is the finding of the Arbitrator on this aspect which reads as
under:
"....the only reason for encashment of bank guarantee claimed by the respondent is that as the balance work had to be got completed which would have entailed excess expenditure .... the bank guarantee was encashed to partly reimburse the loss that it says it has suffered....I have also found that the rate at which the balance work was got done by GAIL not done in a businesslike manner and leaves great scope for the finding of arbitrariness in the allotment of work. On these basis, as I cannot find the fault lies only with the contractor, the question of encashing the bank guarantee by the GAIL in exercise of its rights to forfeit it for non-performance is not established.... It has been admitted by
GAIL that the work which had been performed by the contractor, the value of that comes to Rs.1.45 crores. Of this admittedly only Rs. 35,58,271/- had been paid... there was no justification to encash the bank guarantee."
I do not find any fault in the said finding of the Arbitrator and
it cannot be interfered with in the present petition.
31. The scope for setting aside an arbitral award under Section 34
of the Arbitration and Conciliation Act, 1996 is very limited, as is
obvious from the various judgments referred. The grounds given by the
Petitioner are in the way of an appeal and it has been held in a catena of
judicial pronouncements that a Civil Court will not sit in appeal over the
decision of the Arbitrator as it is not to re-appraise evidence or facts and
merely because the Court would come to a different conclusion on the
available material is not enough ground to interfere with the award.
32. It is well settled that the jurisdiction of the court when called
upon to decide the objection raised by a party against an arbitral award is
limited as expressly indicated in the Arbitration and Conciliation Act,
1996. The court has no jurisdiction to sit in appeal and examine the
correctness of the award on merits with reference to the materials
produced before the Arbitrator. It cannot sit in appeal over views of the
Arbitrator by re-examining and re-assessing the materials. (see Puri
Construction (P) Ltd. Vs. Union of India (1989) 1 SCC 411).
33. In my view, the scope of interference by this Court with an
Arbitrator‟s award under Section 34 of the Arbitration and Conciliation
Act, 1996 has been extensively dealt with by the Supreme Court in Oil
and Natural Gas Corporation Ltd. Vs. Saw Pipes Ltd., (2003) 5 SCC
705. The relevant observations of the Supreme Court in the said
judgment are reproduced hereinbelow :
"31. Hence, in our view in addition to narrower meaning given to the term „public policy‟ in Renusagar‟s case it is required to be held that the award could be set aside if it is patently illegal. The result would be - award could be set aside if it is contrary to :
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality, or
(d) in addition, if it is patently illegal.
XXX XXX XXX XXX
A. (1) The court can set aside the arbitral award under Section 34 (2) of the Act if the party making the application furnishes proof that :
(i) a party was under some incapacity, or
(ii) the arbitration agreement is not valid under the
law to which the parties have subjected it or, failing any indication thereon, under the law for the time being in force; or
(iii) the party making the application was not given proper notice of the appointment of an Arbitrator or of the arbitral proceedings or was otherwise unable to present his case; or
(iv) the arbitral award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration.
(2) The court may set aside the award :
(i) (a) if the composition of the Arbitral Tribunal was not in accordance with the agreement of the parties,
(b) failing such agreement, the composition of the Arbitral Tribunal was not in accordance with Part I of the Act.
(ii) if the arbitral procedure was not in accordance with :
(a) the agreement of the parties, or
(b) failing such agreement, the arbitral procedure was
not in accordance with Part I of the Act.
However, exception for setting aside the award on the ground of composition of arbitral tribunal or illegality of arbitral procedure is that the agreement should not be in conflict with the provisions of Part I of the Act from which parties cannot derogate.
(c) If the award passed by the Arbitral Tribunal is in contravention of the provisions of the Act or any other substantive law governing the parties or is against the terms of the contract.
(3) The award could be set aside if it is against the public policy of India, that is to say, if it is contrary to :
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality; or
(d) if it is patently illegal.
(4) It could be challenged :
(a) as provided under Section 13(5); and
(b) Section 16(6) of the Act."
34. In the case of Food Corp. of India Vs. Arosan Enterprises
Ltd. ILR (1996) 1 Del. 185, it has been laid down that the approach of
the court must be to support the award if it is reasonably possible, rather
than to declare it illegal. It is not permissible to reappraise the evidence
or to go into the questions of quality and quantity of evidence. If two
views are possible, the court even if inclined to take a view different
from that taken by the Arbitrator is not entitled to substitute its view
over that of the Arbitrator. But at the same time, assuming it to be an
award which sets out reasons, though it is not permissible to go into the
reasonableness of the reasons yet this court can set aside the award on
finding errors apparent on the face of the award or if there is an error
of law on the face of the award.
35. The Apex Court in the case of D.D. Sharma Vs. Union of
India, 2004 (5) SCC 325 held that the jurisdiction of the court to set
aside an award is well settled. An Arbitrator being a Judge chosen by
the parties, his decision would ordinarily be final unless one or the other
conditions contained in Section 30 of the Arbitration Act, 1940 is
satisfied for the purpose of setting aside his award. Interpretation of a
contract is a matter for the Arbitrator to determine, even if it gives rise to
determination of a question of law. It is also trite that correspondences
exchanges by the parties are required to be taken into consideration for
the purpose of construction of a contract. Once it is held that the
construction of an agreement fell for consideration of the Arbitrator, the
determination thereupon shall not ordinarily be interfered with. The
court‟s jurisdiction in this behalf is merely to see whether the
Arbitrator has exceeded his jurisdiction or not.
36. In BOC India Ltd. Vs. Bhagwati Oxygen Ltd., 2007 (9) SCC
503, the Court refused to set aside the award of the Arbitrator and held
that when the Arbitrator had considered all the aspects of the matter
including the terms of the contract and all the materials on record and
the statement of claim and had come to a conclusion of fact, it cannot
but be held that the award was not based upon a proposition of law
which is unsound or an error of law must have appeared from the award
itself or from any document or note incorporated in the award or
appended to it. When the Arbitrator had taken a plausible view on
interpretation of contract, it is not open to the court to set aside the
award on the ground that the Arbitrator had misconducted himself in
the proceedings.
37. Recently in the case of Sethi Engineering Corp. Vs. Delhi
Development Authority, 158 (2009) DLT 19 a similar question arose
before this Court and damages on account of prolongation of work
beyond the stipulated date of completion were awarded by the Arbitrator
and observations were also made in this regard. This Court refused to
interfere with the findings given by the Arbitrator.
38. Admittedly the contract for the remaining work was given at
almost the double price to M/s. M.Y. Omni and Sujata however, no
justifiable reason has been given by the Petitioner for awarding the
contract at such a higher price. Since no urgency was shown by GAIL to
award the contract at this unjustified excess amount, the learned
Arbitrator rejected the counter claim of the Petitioner. Claim of both the
parties for damages on account of termination of the contract was
rejected by the learned Arbitrator.
39. The learned Arbitrator took this view and no other possible
view can be made by this Court on findings of the Arbitrator. There is
no error apparent on the face of record in the award. It is not against
public policy nor any other defect/error of law exists in the award.
40. In the light of this discussion and the case law on the matter,
nothing more remains to be said. There is absolutely no ground on which
the arbitral awards dated 16th November, 2005 and 2nd June, 2006 can be
set aside. The Petitioner‟s petition under Section 34 of the Arbitration
and Conciliation Act, 1996 is, therefore, dismissed.
MANMOHAN SINGH, J.
FEBRUARY 18, 2010 jk/dp
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!