Citation : 2010 Latest Caselaw 5889 Del
Judgement Date : 24 December, 2010
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Reserved on : 11.11.2010
% Date of decision : 24.12.2010
+ WP (C) No.3823-25/2006
PRITHI PAL SINGH & ORS. ... ... ... PETITIONERS
Through : Mr.Ravinder Sethi, Sr.Adv. with
Rakesh Kumar Garg, Mr.Rajiv Kumar
Ghawana and Mr.Puneet Sharma,
Advocates.
-VERSUS-
LIEUTENANT GOVERNOR & ORS.... ... RESPONDENTS
Through : Mr.Sanjay Poddar, Advocate for R-1
to R-3.
Mr.Ajay Verma and Mr.Amit Mehra,
Advocates for R-4/DDA.
None for R-5.
Ms.Saroj Bidawat and Mr.Hari Om
Sharma, Advocates for R-6/MCD.
CORAM:
HON'BLE MR. JUSTICE SANJAY KISHAN KAUL
HON‟BLE MS. JUSTICE VALMIKI J.MEHTA
Whether the Reporters of local papers
may be allowed to see the judgment? YES
To be referred to Reporter or not? YES
Whether the judgment should be YES
reported in the Digest?
SANJAY KISHAN KAUL, J.
1. The petitioners purchased land measuring 5 bighas
and 2 biswas in khasra no.42/2 situated in the
_____________________________________________________________________________________________
Revenue Estate of Village Humayupur along with some
built up structure vide a sale deed dated 19.10.1951.
2. It is the claim of the petitioners that they constructed
a bunglow and an ice factory on their land and with
the passage of time, an unauthorized colony known as
Krishna Nagar Colony came up on the adjoining land.
The petitioners claim that their land is also a part of
the lay out plan of the said unauthorized colony which
had been regularized by the respondents vide
Resolution No. 62 dated 25.06.1981. A notification
was issued under Section 4 of the Land Acquisition
Act, 1894 („the said Act‟ for short) on 03.09.1957
which included the lands falling in Khasra no.42 of
which the land of the petitioners being khasra no.42/2
was a part.
3. In the meantime, the DDA was constituted under the
Delhi Development Act, 1957 and MPD-1962 came
into force on 01.09.1962. A declaration under Section
6 of the said Act was issued on 20.02.1963 which
included the land measuring 1 bigha and 2 biswas of
the petitioners followed by an award no.1662 dated
15.01.1964 pertaining to the same and possession
was also taken over. The second declaration under
Section 6 of the said Act was, however, issued on
04.01.1969 which included the land measuring 5
bighas and 2 biswas situated in khasra no.42/2. The
_____________________________________________________________________________________________
petitioners claimed silence on the part of the
authorities thereafter till the notices were issued
under Sections 9 and 10 of the said Act on
26.12.1975. The petitioners laid a challenge to the
acquisition proceedings by filing Civil Writ Petition
No.641/1978 but the same was withdrawn on
29.08.1978 as the writ petition was belated. This
resulted in an award bearing no.38/78-79 being
passed on 23.01.1979 in respect of the suit land which
assessed the compensation for the land and structure
thereon.
4. A second endeavour was made by the petitioners by
filing a Civil Suit No.82/1979 before the Sub-Judge
Delhi seeking a declaration that the land acquisition
proceedings culminating in the award dated
23.01.1979 were void, illegal and nullity on account of
unreasonable delay. The petitioners were enjoying
interim relief in the suit stated to be in pursuance to
an order of the Appellate Court.
5. A representation dated 16.07.1998 was, however, filed
to the LG during the pendency of the suit for de-
notification of the land under Section 48 of the said
Act. In pursuance to the representation, the Land and
Building Department of the Govt. of NCT of Delhi
sought some details from the SDM/LAC vide its letter
dated 18.08.1998 including in respect of the
_____________________________________________________________________________________________
possession at site and built up structure on the land in
question. The SDM/LAC vide its letter dated
25.09.1998 confirmed that the possession had not
been handed over to the concerned Department and
that the physical possession of the land in question
was with the petitioner No.1. There was a residential
house and factory like structure with a boundary wall
stated to be constructed on the land in question and
no compensation had been paid. The factum of suit
no.82/1979 pending in the Court of Sub-Judge was also
pointed out. This is also stated to have been
confirmed by the Director (LM) vide letter dated
21.09.1998.
6. In view of the aforesaid facts, the case of the
petitioners was put up before the De-notification
Committee in its meeting held on 27.01.1999 when it
was resolved that the land be inspected by a Sub
Committee and a report be submitted. The Sub
Committee inspected the land on 05.05.1999 and
found that the land within boundary in physical
possession of petitioner No.1 included khasra no.48/4
in addition to khasra no.42/2, possession of which was
reported to be taken over by DDA but continued to be
in unauthorized occupation of petitioner no.1.
However, part portion of khasra no.42/2 fell outside
the boundary wall and formed a part of the service
_____________________________________________________________________________________________
lane. The built up structure within the boundary wall
was found to be 16 biswas. The Sub Committee in its
report dated 13.05.1999 opined that some additional
information be also sought. The relevant portion is
quoted below:
"1. To confirm from the MCD whether the land in question falls within the unauthorized regularized colony of the Krishna Nagar.
2. Whether after regularization of the unauthorized colony, DDA has any role for development of the vacant land falls in the said colony.
3. After regularization of the unauthroize colony whether DDA deletes that portion of land from their Master Plan/Development Area."
7. The report of the Sub Committee is stated to have
been considered by the De-Notification Committee in
its meeting held on 04.06.1999 when it was decided to
elicit views of the Planning Department of the DDA
before recommending any de-notification. The
Director (LM) of the DDA informed Commissioner
(Planning) of the DDA vide letter dated 10.06.1999
that the physical possession of the land measuring 5
bighas and 2 biswas forming subject matter of the
award had not been taken over and at the site there
were structures known as Partap Ice Factory. The De-
notification Committee was seized of the matter and
information was sought whether the land was part of
the approved lay out plan.
_____________________________________________________________________________________________
8. The Secretary (Land) of Govt. of NCT of Delhi sent a
reminder to Commissioner (LM) DDA for requisite
information on 25.06.1999. In the meantime, the
Commissioner (Planning) vide its letter dated
05.07.1999 to Director (LM) of the DDA informed that
the land bearing khasra no.42/2 was not part of
Safderjung Enclave and was on the fringe/periphery of
Krishna Nagar unauthorized regularized colony. It was
further stated the land/area stood transferred to MCD
and as such no current planning was being undertaken
by the Planning Department of the DDA.
9. Secretary (Land) is thereafter stated to have re-
commended the de-notification subject to the
condition that the land of khasra no.42/2 which had
already been utilized by the DDA in construction of
road and by-lanes would be given up, land bearing
khasra no.48/4 belonging to DDA would be parted with
and court proceedings would be withdrawn. However,
when the matter was considered by the LG/competent
authority on 16.07.1999, a query was raised for
ascertaining from MCD whether it required the land for
providing the common facilities. The LG also wanted
to know the exact land use as per the Zonal Plan. This
note records that out of the aspects weighing for de-
notification, the first one of a challenge being laid and
a stay order being obtained from a civil court was not
_____________________________________________________________________________________________
tenable while the aforesaid information was required
for the second aspect i.e. that the DDA had no use of
land because the colony had been handed over to
MCD. This resulted in a communication dated
16.08.1999 by the Secretary (Land) to the MCD to
which a response was sent on 01.12.1999 by the
Commissioner, MCD informing that the site was
earmarked for group housing and the site was not
required for any common facilities as there was no
deficiency in that behalf.
10. In pursuance to the aforesaid developments, the
Land and Building Department of Govt. of NCT of Delhi
addressed a letter dated 24.02.2000 to the petitioners
enquiring as to what project was being proposed by
them on the land in case it is de-notified. This was
responded to on 07.03.2000 stating that the owners
were ready to abide by the requirements of the plan
and accordingly use the land for group housing, the
earmarked purpose. Thereafter, the matter was again
put up to the LG on the earlier de-notification proposal
of the Secretary (Land). The LG in terms of his note
dated 06.04.2000 found that there were some
inconsistencies since the Planning Department of DDA
had opined vide its letter dated 05.07.1999 that the
land was not part of Safderjung Enclave but was in
fringe/periphery of Krishna Nagar unauthorized
_____________________________________________________________________________________________
regularized colony while Commissioner, MCD vide a
DO letter dated 01.12.1999 had opined that the land
in question forms part of the lay out plan of Safderjung
Enclave and that was the basis for stating that the
area was earmarked for group housing. However, no
final picture in this behalf emerged and the original
records produced show that the notings in this behalf
came to an end in December, 2001 with the matter
being never placed before the LG with full information
to take a decision on the issue of de-notification one
way or the other. The civil suit no.82/99 was ultimately
dismissed on 18.08.2005. The petitioners moved a
representation dated 06.09.2005 to the LG once again
raising the issue of the pending representation for de-
notification of land under Section 48 of the said Act.
11. It is the case of the petitioners that the
respondents irked by the second representation
exposing inaction of the administration, instead of
passing an order in respect of the plea of de-
notification, made an endeavour to take over
possession of the land when only paper possession
was taken over on 22.02.2006. The petitioners
approached this Court by filing the present writ
petition under Article 226 of the Constitution of India
when the parties were directed to maintain status quo
_____________________________________________________________________________________________
with regard to the possession in terms of the order
dated 10.03.2006.
12. The pleadings were completed but thereafter
the petitioners amended the writ petition in the year
2010 in view of certain subsequent facts. The
petitioners claim quashing of the notifications along
with the plea to de-notify the land. Thereafter, even
amended pleadings have been filed.
13. The respondents plead that a decision was taken
on the representation of the petitioners under Section
48 of the said Act during the pendency of the petition
which was duly communicated by the Deputy
Secretary (LA) vide letter dated 20.04.2006 which
reads as under:
"I am directed to refer you representation dated 27.09.2005 on the subject cited above and to inform you that case for de-notification of subject land was considered. It has been observed that physical possession of the said land has been taken over by DDA on 22.02.2006. With this acquisition proceedings stands completed. As per provisions of the Land Acquisition Act, 1894, the acquired land cannot be denotified under Section 48 of the LA Act once the acquisition proceedings are completed. Hence, your request for denotification of the said land under section 48 cannot be considered at this stage."
14. It is the submission of the respondents that since
physical possession of the land has been taken over,
_____________________________________________________________________________________________
the acquired land cannot be de-notified under Section
48 of the said Act.
15. When the matter was taken up for hearing on
09.11.2010, learned senior counsel for the petitioners
confined his submissions to a claim that since their
application under Section 48 of the said Act was made
as far back as 1998, comments were called for, and
even De-notification Committee had recommended
release of land, the proceedings for de-notification
ought not to have been made infructuous by seeking
to take possession in the year 2006 without deciding
the application of the petitioners.
16. Learned counsel for the respondents, however,
strenuously contended that the writ petition had no
merit on various grounds as set out in their synopsis.
It is their plea that the petitioners are only name-
lenders as the writ petition has been filed through an
attorney as would be apparent from the affidavit filed
in support of the writ petition. Nothing was disclosed
as to how this attorney got authority, person by the
name of Sh.R.K.Aggarwal who was not related to the
petitioners. The counter affidavit filed on behalf of R-
2 and R-3, in para 10, specifically raised this plea, but
in rejoinder, nothing has been said in this behalf
except to file a copy of the special power of attorney.
The power of attorney does not appear to be
_____________________________________________________________________________________________
registered and is executed on 30.04.2004. The special
power of attorney in favour of Sh.R.K.Aggarwal is very
comprehensive including giving authority to transfer
the property, take all legal steps, appoint arbitrator
and to sign and file applications for de-
notification/release of the land. It also authorizes
engagement of pleaders or advocates and to appoint
or remove further/general special power of attorneys.
In the last para, being para 16, of the power of
attorney it is in fact labeled as a General Power of
Attorney. The stand of the said respondents thus is
that the petitioners have clandestinely sold the land to
the attorney or his nominee for consideration and
have suppressed the other documents executed as
they would show the transfer of land which was
prohibited under the Delhi Lands (Restrictions on
Transfer) Act, 1972. The allegation is of suppression
of the material documents in respect of true nature of
transaction.
17. It is the plea of the respondents that having
failed in the challenge to the acquisition proceedings
in the writ petition, the acquisition proceedings were
challenged in a civil suit where interim orders were
granted of status quo on 29.05.1979 which was
vacated on 22.10.1980. However, in appeal, the
interim orders were restored and were to continue
_____________________________________________________________________________________________
during the pendency of the suit which was finally
dismissed on 18.08.2005. Learned counsel
emphasized that a preliminary issue was framed about
the maintainability of the suit in view of the provisions
of the said Act and despite the pronouncements of the
Supreme Court, in State of Bihar v. Dhirendra Kumar:
AIR 1995 SC 1955, the petitioners continued to
prosecute the suit till its dismissal on 18.08.2005 since
they were enjoying interim orders. It is during the
pendency of the suit that an application was filed on
16.07.1998 seeking de-notification of the land under
Section 48 of the said Act. The possession of the land
is stated to have been taken on 22.02.2006 on the
repeated demands made by the DDA and was
simultaneously handed over to the DDA. Demolition
was also carried out of the unauthorized constructions
raised by the petitioners on 10.03.2006 on which date
the petitioners are alleged to have persuaded this
Court to pass interim order of status quo by
misleading the Court. It is under the garb of this order
that the petitioners are alleged to have tried to regain
possession resulting in police complaint dated
05.05.2006 being filed by DDA. The possession
proceedings have been annexed to the counter
affidavit of the DDA. The absence of any notings in
the file post 2001 is stated to be on account of the fact
_____________________________________________________________________________________________
that as the civil suit was still pending in which interim
orders granted on 29.05.1979 were enuring for the
benefit of the petitioners, the file was not processed
further in respect of the application of the petitioners
under Section 48 of the said Act. It is only on
dismissal of the suit on 18.08.2005 that possession
proceedings were taken out on 22.02.2006. Learned
counsel sought to draw strength from the observations
made by the Division Bench of this Court in Ramjas
Foundation & Anr. versus UOI & Ors.; 110 (2004) DLT
10. In that case, a representation was made in 1995
but was rejected in the year 2002 while in the
meantime, the possession was taken over during the
pendency of the representation. The Division Bench
did not interfere and the SLP (Civil) No.7026/2004
directed against that order was dismissed as
withdrawn on 21.04.2008. It is, however, admitted
that no decision was taken on the application of the
petitioners under Section 48 of the said Act, but the
plea is that the Government had never de-notified the
land and thus the petitioners cannot claim any interest
or equity.
18. Insofar as the notings are concerned, learned
counsel for the respondents sought to rely upon the
observations of the LG on 16.07.1999 when out of the
two proposed grounds for release, the LG disagreed
_____________________________________________________________________________________________
with the first ground i.e. the interim stay and insofar
as the second ground was concerned, asked the
Department to obtain clarifications from MCD and
DDA. Thus, nothing positive in favour of the
petitioners was indicated by the LG in the note. Even
in the subsequent note of the LG dated 23.03.2000,
the file was returned on account of certain
contradictions with the remark "please speak". The
clarifications were sought up to 2001 though they
were not forthcoming and the file again started
moving in the year 2005 on the request of the
petitioners. The meeting was convened by the LG
which was attended by the officials of the DDA and
MCD and finally the LG vide note dated 04.04.2006
approved the view as resolved by the committee on
23.03.2006 and the decision was duly communicated
to the petitioners on 20.04.2006. The subsequent
representation made through an attorney was also
rejected. Learned counsel seeks to emphasize by
reference to the judgment in Shanti Sports Club v. UOI
and Ors; 2009 (15) SCC 705 that even where one
Union Minister had taken a favourable decision which
was revoked by the other, the subsequent decision
was upheld by observing that the only mode of
release of land was by way of notification under
Section 48 of the said Act. No such decision had been
_____________________________________________________________________________________________
taken in the present case. Even on the aspect of
release of other lands being made examples, the
same were rejected by the Supreme Court.
19. In order to appreciate the aforesaid rival
contentions, it is also necessary to record how the file
moved in 2005 after the hiatus period from 2001-
2005. The first note dated 26.04.2005 suggests that
the file appears to have been misplaced and that
immediate steps must be taken to send a reminder to
the Director (LM) of the DDA to send his comments.
Thus, the story of the comments not forthcoming
began once again. In the meantime, the
representation filed on behalf of the petitioners after
dismissal of the suit was also received. A detailed
note on 03.11.2005 records the history and the
factum of report not being sent by Director (LM) till
that date and thus the file has to be placed before the
LG. Once again, reminders were sought to be sent to
the DDA before putting up the file before the LG but
no reply was received and thus it has been recorded
that a meeting ought to be called between the
Commissioner (Lands), DDA and Commissioner, MCD
to clarify its position to be placed before the LG. A
meeting was fixed for 06.03.2006 but did not mature
due to pre-occupation of the Secretary(Land and
Building) and the Additional Commissioner MCD (Land
_____________________________________________________________________________________________
and Building) in some other matter as noted in the
note dated 10.03.2006. It was also noted in the same
note that the LG wants to know about the status of the
case. The meeting was re-scheduled for 16.03.2006
when the only fact noticed is that though no
information was forthcoming from MCD and DDA, the
possession of land having been taken, there was no
force in the representation of the petitioners for de-
notification of the land which was then approved by
the LG.
20. The sum and substance thus is that the
information sought by the LG was not forthcoming
from the MCD and DDA for almost seven years for
different reasons, but at the fag end since possession
was taken over it was stated that the exercise to
obtain information would be a futile one.
21. The question of taking over possession is
seriously disputed by the petitioners. Annexure R-2 is
the only document annexed to the counter affidavit of
DDA on the basis of which it is claimed that possession
was taken over on 22.02.2006. There is nothing else
in the original records produced in the Court. The
possession report shows that at site the respondents
went around the wall containing the structure and the
vacant land and took over the possession. There is
not even a recorded note of opening the gate,
_____________________________________________________________________________________________
entering into the property or physically taking over
possession thereafter. All that is written is that the
possession proceedings are thereafter complete and
the words used are "actual possession". The
possession report mentions the land area as eight
biswas and that there was no resistance to the
possession.
22. In the rejoinder affidavit, the petitioners pleaded
that the respondent-authority seems to have prepared
the report while sitting in their office. There was a
generator room, tube well and one dry well of which
there is no mention in the possession report. The
demarcation report carried out by the officials of the
respondents on 05.05.1999 had referred to the
existing construction to be shown of 16 biswas while
the possession report dated 22.02.2006 mentions it as
eight biswas. The persons deputed by the petitioners
were stated to be residing in the property and there
was an electricity meter of which last reading was
recorded on 07.03.2006. The persons occupying the
property on behalf of the petitioner being Sh.Dalip
Singh and Sh.Ram Bhadur have also filed affidavits
about their being at site on 22.02.2006 when no one
came to the site. It has been pointed out that the
possession report does not bear the signatures of any
Panch or independent witness. There is also no
_____________________________________________________________________________________________
mention of the two gates in the boundary wall for
ingress or egress. It is not the case of the respondents
that they had sought any police protection at the time
of taking over possession while after the alleged date
of taking over possession when they wanted to carry
out demolition, police protection was sought. The
possession report is thus referred to be unbelievable
and a fabrication. Most importantly there was no Halka
Patwari present and it has not even been indicated as
to when the date for taking over possession was fixed
and if the DDA informed to come to the site.
23. It is thus pleaded that these records have only
been created to plead that the LG need not apply his
mind to the application of the petitioners under
Section 48 of the said Act.
24. The last aspect which learned counsel for the
petitioners seeks to emphasize is that there has been
considerable pick and choose on the aspect of release
of land under Section 48 of the said Act and pleaded
there were two glaring examples of the same. The
first one is in the case of Smt.Roshanara Begum in
respect of land measuring 9 bighas and 1 biswas
situated in Village Lado Sarai, which formed subject
matter of dispute in the judgment of the Full Bench of
this Court in Roshanara Begum v.Union of India;
(1996) 61 DLT 204 which was unsuccessfully
_____________________________________________________________________________________________
challenged before the Supreme Court in Murari
v.Union of India; 1997 (1) SCC 15. Despite this, the
land was subsequently released under Section 48 of
the said Act. We have noticed this even in WP(C)
No.2563-66/2005 decided on 04.03.2010.
25. We had called records of Roshanara Begum‟s
case and it transpires that in terms of the order of the
LG dated 18.12.2007 the land was released on a
representation of Sh.Sultan Ahmed and Smt. Saira
Banu, son and daughter of Late Smt. Roshanara
Begum nee Naseem Banu. The area was found to be a
part of the Regional Park and not falling in the ridge.
The de-notification was subject to the land being
maintained as green in consonance with the intent of
the Master Plan, no new permanent structure to be
built, temporary structures to be raised only with the
prior approval of DDA and no claim for compensation
towards damages. The existing structures on the site
are stated to be a kothi, room, boundary wall and hall.
26. The second case referred is the case of Radha
Soami Satsang Beas („RSSB‟) in respect of land
measuring 21 bighas and 8 biswas situated in Dwarka.
The original record of this case shows that the land
was purchased by RSSB in April-May, 1999 prior to the
notification under Section 4 of the said Act dated
13.12.2000. A declaration under Section 6 was issued
_____________________________________________________________________________________________
on 7th December, 2001 when RSSB applied for de-
notification of their land on the ground that it was
required for religious purposes and ought to be
exempted. This request was turned down by the then
LG on 07.11.2002 after receiving recommendation of
the De-notification Committee. The DDA stated
before the De-notification Committee that the land
was required for construction of planned road for
providing connectivity between phases I and II of
Dwarka, for construction of flats to meet pending
public demand and social and physical infrastructure.
The Committee recommended that the RSSB could
approach the DDA for allotment of land in institutional
area. The challenge raised by RSSB of refusal of de-
notification under Section 48 of the said Act in a writ
petition was rejected in May, 2005. Despite this, it
was found that there were certain public policy
dimensions which again need to be re-examined, as
per the note of the LG dated 14.05.2008.
27. Basically, the main ground is stated to be large
functions held by RSSB which required a large area.
The possession of land could not be taken because of
sit in by the followers of RSSB. RSSB offered to give
up possession of this strip of land in lieu of an
equivalent area adjoining their remaining area. It was
found that divesting RSSB of the land was not a
_____________________________________________________________________________________________
workable solution. The objection of DDA that such de-
notification would generate a similar demand from
other parties was also brushed aside as the land was
being used for community purposes in the case. The
earlier order of the then LG dated 07.11.2002 was
hence superseded when the LG passed the order
dated 14.05.2008.
28. On giving our thoughtful consideration to all of
the aforesaid aspects, we consider it appropriate to
deal with the different aspects separately which arise
for adjudication and are germane to the issue.
THE WRIT PETITION BEING FILED THROUGH
POWER OF ATTORNEY
29. The writ petition filed by the petitioners is
through a Power of Attorney - person by the name of
Sh.R.K.Aggarwal. The writ petition was not supported
by the copy of Power of Attorney but when the
objection was raised by the respondents in their
counter affidavit, a copy of the power of attorney was
filed with the rejoinder. It is pertinent to note that
para 10 of the counter affidavit filed by R-2 and R-3
only raises the plea that the petitioners had not filed
any documents on record to show their authority. It is
in response thereto that a copy of Power of Attorney
was filed by the petitioners.
_____________________________________________________________________________________________
30. No doubt ideally a copy of the Power of Attorney
ought to have accompanied the petition, but then
once an objection was raised, the same has been
placed on record. The plea of the learned counsel for
the respondents that the petitioners are only name
lenders did not form the basis of the objection, but the
objection was about the absence of the Power of
Attorney which has since been filed.
31. We may also notice that nothing prevents a
competent authority before passing any order under
Section 48 of the said Act to satisfy itself about the
current title of the property and whether it has been
transferred contrary to the provisions of the Delhi
Lands (Restrictions on Transfer) Act, 1972. No doubt
the Power of Attorney gives extensive powers but
from that alone one cannot derive a presumption in
favour of the property having been transferred. On
the petitioners being called upon to explain their stand
in this behalf, a conclusion regarding title can always
be a factor to be considered in an application under
Section 48 of the said Act. Thus, the factum of the
writ petition having been filed through a power of
attorney by itself cannot shut out the petitioners from
making a grievance about the representation made
under Section 48 of the said Act and the manner of its
disposal.
_____________________________________________________________________________________________
32. We make it clear that it is open to the competent
authority to first satisfy itself that the petitioners
continue to be the owner of the property in question
and that it is not a proxy litigation by a power of
attorney holder who had acquired interest in the
property.
INSTITUTION OF A CIVIL SUIT BY THE
PETITIONERS
33. It is no doubt true that the challenge laid to the
acquisition proceedings by the petitioners through
filing of a civil writ petition No.641/1978 did not
succeed as the same was withdrawn on 29.08.1978 as
the writ petition was belated. Subsequently, award
bearing no.38/78-79 was passed on 23.01.1979.
However, the petitioners filed Civil Writ Petition
No.82/1979 before the Sub Judge, Delhi and were
successful in getting an interim relief by the appellate
court. It is during the pendency of this suit that a
representation dated 16.07.1998 was filed by the
petitioners making a request to the competent
authority/LG for de-notification of the land under
Section 48 of the said Act.
34. We are unable to accept the contention of
learned counsel for the respondents that the
petitioners themselves should have suo motu
withdrawn the civil suit in view of the judgment of the
Supreme Court in State of Bihar v. Dhirendra Kumar‟s _____________________________________________________________________________________________
case (supra). The respondents were also fully aware of
the judgment and nothing prevented them from
bringing that judgment to the notice of the Court
seeking dismissal of the suit on that account. Both the
parties kept silent about that aspect and the
application filed by the petitioners under Section 48 of
the said Act continued to be processed. The
respondents thus cannot absolve themselves of the
responsibility in this behalf or for the delay in disposal
of the suit which came to be dismissed only on
18.08.2005 when interim orders stood vacated.
THE MANNER OF PROCESSING OF THE APPLICATION UNDER SECTION 48 OF THE SAID ACT
35. We have already noticed above that the
application for release of the land under Section 48 of
the said Act through a representation dated
16.07.1998 was filed before the LG. The application
was processed and comments were called from the
various departments including the site position. The
case of the petitioners was also put up before the De-
notification Committee in its meeting held on
27.01.1999 when it was resolved to inspect the land.
The land was duly inspected by the Sub Committee on
05.05.1999 when it was found that a portion of the
khasra no.42/2 (which was in issue) fell outside the
boundary wall and formed a part of the service lane
_____________________________________________________________________________________________
while the remaining portion was within the four walls
of the petitioners and under possession of the
petitioners. It was also noticed that the boundary wall
included land of khasra no.48/4 of which possession
was reported to be taken over but continued to be in
unauthorized occupation. It is in view thereof that the
recommendation was made for de-notification, but
subject to the petitioners giving up the land in respect
of khasra no.48/4 and not claiming any damages in
respect of the land already utilized out of khasra
no.42/2.
36. However, there appeared to be some confusion
about the location of the land and whether it fell
within the jurisdiction of the DDA or MCD. The DDA
was of the view that the land did not form a part of
Safderjung Enclave and was on the fringe/periphery of
Krishna Nagar unauthorized regularized colony. No
planning was being undertaken by the DDA and
opined that the matter really pertained to MCD. This
is clear from the letter of the DDA dated 05.07.1999
which was issued in concurrence with Commissioner-
Planning, DDA. The MCD also took the stand that it
did not require the land in question for any community
services of Krishna Nagar unauthorized regularized
colony on a query being posed from the office of the
LG. It was only in the conspectus of all these facts
_____________________________________________________________________________________________
that the Secretary (Land) of Govt. of NCT of Delhi
thereafter recommended de-notification of the land
falling in khasra no.42/2 subject to terms and
conditions. When the matter reached for final
approval of the LG/competent authority, a query was
posed on 16.07.1999 about the stand of the MCD,
which was clarified as aforesaid and the MCD informed
that the site was earmarked for Group Housing. The
petitioners were also asked to inform the proposed
user of the land in terms of the letter dated
24.02.2000 and they stated that the land would be
used for the earmarked purpose. It is with all this
material that the matter was once again placed before
the LG who found some inconsistencies between the
stand of the Planning Department of the DDA and of
the MCD. It is in view thereof that note was penned
down by the LG on 06.04.2000 seeking a clarification
as to whether the land in question formed a part of
the lay out plan of Safderjung Enclave or not.
Unfortunately, despite repeated reminders, DDA did
not answer this query and the file was not even
processed after December, 2001. None on the part of
the respondents cared to seek appropriate information
to be placed before the LG as per the directions of the
LG. The explanation of the aforesaid, as given by
learned counsel for the respondents, is that this may
_____________________________________________________________________________________________
have happened because of the pendency of the civil
suit where a stay was operating. This plea is only to
be stated to be rejected for the reason that everyone
was aware of the pendency of the civil suit and the
application of the petitioners being processed. It is the
non-adherence of the DDA to the demand from the
LG‟s Office in respect of explanation regarding the
aforesaid aspect which resulted in non-processing of
the file. Once the suit was dismissed, the petitioners
once again represented about the pendency of the
representation.
37. It is no doubt true that the petitioners did not
approach any judicial forum against non disposal of
their representation under Section 48 of the said Act
during the pendency of the suit. It can, however, be
not lost sight of the fact that the representation of the
petitioners under Section 48 of the said Act was, in
fact, being examined by the respondents and queries
were even posed to the petitioners. The petitioners
can hardly expect in such a situation that any action
would be taken without finally deciding their
representation under Section 48 of the said Act.
38. The records show that queries of the LG
remained unanswered even in the year 2005. All that
happened was that it was put up to the LG that the
possession had been taken over of the site on
_____________________________________________________________________________________________
22.02.2006 and thus there could be no question of
release of the land under Section 48 of the said Act.
That is the sole reason for rejection of the application
of the petitioners under Section 48 of the said Act and
not on the merits of the claim laid by the petitioners.
The post dismissal of suit period also saw once again
queries being raised from the DDA and reminders
being sent, but to no avail. A meeting was also
directed to be held between Commissioner (Lands),
DDA and Commissioner, MCD to clarify the position to
be placed before the LG which did not fructify and on
the anvil of the second date fixed, the possession was
stated not to have been taken over making the
discussion infructuous.
39. We have already recorded in para 15 aforesaid
that the learned senior counsel for the petitioners
confined his submission to the claim of non
consideration of the application of the petitioners
under Section 48 of the said Act made as far back as
in the year 1998 for which a recommendation was
made by the concerned authorities of course subject
to the final approval of the competent authority/LG.
We find force in the contention of the learned counsel
for the parties that there has been gross negligence
on the part of the respondents in dealing with the
application of the petitioners under Section 48 of the
_____________________________________________________________________________________________
said Act by keeping it pending with no movement of
the file for a number of years. The file initially moved,
comments were called from all the concerned
departments, clarifications and re-clarifications sought
and it is in pursuance thereto that the
recommendation was made to the LG for de-
notification of the land subject to certain terms and
conditions. The LG only wanted clarification on a
particular aspect which the DDA failed to respond
despite repeated reminders. Instead of obtaining
clarification, the file was put in a cold storage and on a
dismissal of the suit once again the story of certain
clarifications form DDA started but the same was
sought to be defeated by claiming possession having
been taken over. It is not a case where the land
owner having lost throughout has filed an application
under Section 48 of the said Act just prior to the
possession being taken over to defeat the effect of the
loss in the previous litigation. The petitioners were
enjoying interim stay in the civil suit and yet chose to
make a representation for release of the land under
Section 48 of the said Act which was acted upon. The
respondents could have easily dealt with the file
within a reasonable period of time and the LG would
have arrived at a decision but for the file being put in
a cold storage post 2001. There is thus no final
_____________________________________________________________________________________________
decision of the LG on the merits of the application of
the petitioners.
40. A further question thus which would have to be
examined is as to whether the physical possession
was actually taken over from the petitioners making
the application under Section 48 of the said Act
infructuous and whether such an action is sustainable
in law.
POSSESSION PROCEEDINGS
41. The possession proceedings in the present case
are of vital importance.
42. We may note that the possession proceedings
are only of one page which have been annexed as
Annexure R-2 to the counter affidavit of DDA. We had
called for the records and it is not in dispute that there
are no proceedings other than that annexure. There is
some action of demolition subsequently taken but that
is not simultaneous to the possession being taken
over. The records show that there are no
communications really of the DDA in behalf of the
action to be taken to take over possession of the land
in question at that time. On the other hand, the
communications to the DDA had again started seeking
clarification as sought by the LG which remained
unanswered. If the possession report annexure R-2 is
perused, it would show that the representatives of the
_____________________________________________________________________________________________
respondents went around the wall of the property in
question containing the structure and vacant land and
claimed to have taken over possession hence. As to
how taking a circle around the wall would amount to
taking over possession is a moot point. There is no
recording of any gate being opened to enter the
property or to take over physical possession. All that
is written is that the possession proceedings are
complete.
43. We find merit in the plea of the petitioners that
the possession proceedings give no confidence
whatsoever and it appears that the officers merely
went around the property and came back by making a
paper endorsement of having taken over possession.
No proper description is given as to what existed at
site and affidavits have been filed on behalf of the
representatives of the petitioners who stay at site.
The possession report bears no signatures of any
independent witness or Panch and most importantly
there is not even the presence of Halka Patwari.
There are no records to show as to when the date for
taking over possession was fixed and when DDA was
informed to be present at site. In such possession
proceedings, the Halka Patwari should have been
there at the site. There is also strength in the
submissions of the petitioners that the respondents
_____________________________________________________________________________________________
claimed to have sought police protection when the
respondents subsequently fixed a date to carry out
demolition of structure but never sought police
protection at the time of taking over possession of the
property in question. These aspects have not to be
read in isolation but collectively which would show
that physical possession was actually never taken
over and they were only paper proceedings. Other
than the possession proceedings filed with the counter
affidavit, there is no other record to show the intent of
the respondents to take over possession of the
property in question.
44. We have examined the issue of taking over
possession by examining various pronouncements of
the Supreme Court in WP(C) No.1907/1986 Auto Grit
and Ors. V. UOI & Ors., decided on 03.02.2010 and
subsequently in WP(C) No.2563-66/2005 M/s Budh
Singh Gulab Singh and Ors. V. UOI and Ors. decided on
04.03.2010. The Supreme Court has emphasized that
whether possession has been taken over or not would
depend on the facts of each case. We had observed
as under in Auto Grit and Ors. V. UOI & Ors.‟s case
(supra) as under:
"We are conscious of the fact that there are various judgments relating to the aspect of handing over possession and it has been emphasized by the Supreme Court that whether possession has been taken over or not would depend on the
_____________________________________________________________________________________________
facts of each case. This position emerges from the judgment of the Supreme Court in Balwant Narayan Bhagde v. M.D.Bhagwat and Ors.; (1976) 1 SCC 700, National Thermal Power Corporation Ltd.v. Mahesh Dutta and Ors.; 2009 (9) SCALE 591 and Sita Ram Bhandar Society, New Delhi v. Lt. Governor, Govt. of NCT of Delhi & Ors.; 2009 (12) SCALE 550.
Learned counsel for the respondents have emphasized that the recording of panchnama can itself constitute evidence of the fact of possession having been taken over and land has vested absolutely in the Government as per Sita Ram Bhandar Society, New Delhi v. Lt. Governor, Govt. of NCT of Delhi & Ors‟s case (supra).
Learned senior counsel for the petitioners on the other hand has emphasized that possession merely on paper would not be enough and how such a possession may be taken would depend on the nature of the land in view of observations of the Supreme Court in National Thermal Power Corporation Ltd.v. Mahesh Dutta and Ors.‟s case (supra). It was observed that in the case of land lying fallow and there being no crop on it at material times, the act of the Tehsildar in going to the spot and inspecting the land for the purpose of determining what part was waste and arable and should be taken possession of and determining its extent was sufficient to constitute taking possession.
On the other hand, it was observed that the question whether physical possession has been taken in compliance of provisions of Section 17 of the said Act or not would depend on the facts and circumstances of each case. It was further observed that possession was either correct or incorrect and it cannot be partially correct or partially incorrect.
In Balwant Narayan Bhagde v.
M.D.Bhagwat and Ors‟s case (supra), it was observed that when proceedings under the said Act for acquisition of land are initiated, all interests are wiped out _____________________________________________________________________________________________
and actual possession of land becomes necessary for its use for public purpose for which it had been acquired and thus taking over possession under the said Act cannot be symbolic in the sense as generally understood in civil law. It could not be possession merely on paper and what is required under the Act is taking of actual possession on the spot."
(emphasis supplied)
45. In the facts of the present case, we find that
obviously no physical possession of the land was
taken over, but a formality was completed only on the
file. The representatives of the respondents in the
absence of any Halka Patwari just went around the
wall and completed a noting in the file and this cannot
be categorized as sufficient to constitute taking over
possession in view of what we have referred to
aforesaid.
46. We thus come to the conclusion that no physical
possession was taken over of the site of the
petitioners and it is only when the demolition action
was threatened at the site that the petitioners
approached this Court and status quo order was
passed.
47. In view of the aforesaid findings, we are not
inclined to go into the effect of taking over possession
pending consideration of the application of the
petitioners under Section 48 of the said Act in the
given facts of the case. Thus the application under
_____________________________________________________________________________________________
Section 48 of the said Act can be decided on merits
and ought not to have been rejected only on the
ground of possession having been taken over which
was only a ruse to prevent proper consideration of the
application of the petitioners by the LG as per
information sought from the office of the LG.
PLEA OF DISCRIMINATION
48. Lastly we are concerned with the plea of
discrimination as urged by the learned counsel for the
petitioners.
49. We have noticed two examples given by learned
counsel for the petitioners of such discrimination in
para 24 aforesaid and have also noticed as to how
those cases were dealt with in para 25 to 27 aforesaid.
All we can say is that we are surprised that after
having spent valuable judicial time in seeking
authoritative pronouncements in Roshanara Begum v.
Union of India and Ors; AIR 1996 Delhi 206 which was
sustained by the Supreme Court in Murari and Ors v.
Union of India & Ors.; 1997 (1) SCC 15, the land was
released from acquisition even though it was forming a
part of the Regional Park. The effect was that the
existing structure of a kothi, room, boundary wall and
hall would continue to stand in an area earmarked under
the Master Plan and the Zonal Plan for a Regional Park.
Similarly, in RSSB‟ case, there was a negative
recommendation by the De-notification Committee _____________________________________________________________________________________________
unlike the present case and the LG had even turned
down the request for de-notification on 07.11.2002. The
land was required as per the DDA for construction of
planned road and for providing connectivity between
Dwarka Phase I and II. This matter was re-examined on
the spacious plea that the ground reality required a
different view to be taken as taking over possession was
creating difficulty and large tracts of land were required
by RSSB for holding religious and social functions. If
such a plea was to be accepted then any land owner
who uses force to retain possession of the land would
stand to gain by such illegal conduct as against the land
owner who follows the law of the land. Even the
objection of the DDA that such de-notification would
generate similar demands from other parties was
brushed aside by the LG while passing the order dated
14.05.2008 superseding the earlier order of the then LG
dated 07.11.2002.
50. In the present case, the then LG had found that
the pendency of the civil proceedings and the stay
should not be a factor which would weigh in de-
notification but sought clarification in respect of the
other aspect. On the other hand, in RSSB‟s case, forget
any judicial order which was absent, the sit in or
squatting by members of RSSB persuaded the LG to
exercise jurisdiction to release the land.
_____________________________________________________________________________________________
51. We feel that such pick and choose policy naturally
gives rise to resentment and a feeling in public quarters
that the social standing of the owner/organization may
help in release of the land. The de-notification policy
should be strictly adhered to. We say no more as the
petitioners are succeeding in the writ petition in any
case.
CONCLUSION
52. We are of the categorical view that the
application filed by the petitioners under section 48 of
the said Act as far back as on 16.07.1998 read with
the last reminder dated 06.09.2005 are required to be
examined by the LG on the merits and the impugned
decision communicated to the petitioners vide letter
dated 20.04.2006 in terms whereof the representation
of the petitioners has been rejected on the plea of
possession having been taken over cannot be
sustained and is quashed.
53. We have already observed that it is open to the
respondents to verify at the threshold about the
current title of the petitioners to find out that they
continue to be owners and have not sold the property
on a power of attorney basis. A fresh decision should
be taken preferably within three months of the
communication of the order and till then a status quo
order as directed by this Court would continue to
operate. In case of any adverse decision, the status _____________________________________________________________________________________________
quo order would continue to operate for a period of 15
days from the date of receipt of the decision by the
petitioners, a copy of which should also be served on
the counsel for the petitioners.
54. The writ petition is allowed in the aforesaid
terms leaving the parties to bear their own costs.
SANJAY KISHAN KAUL, J.
December 24, 2010 VALMIKI J.MEHTA, J.
dm
_____________________________________________________________________________________________
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!