Citation : 2010 Latest Caselaw 2292 Del
Judgement Date : 29 April, 2010
#F-28B
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P. 366/2002
MMTC LIMITED ..... Petitioner
Through Mr. Parag P. Tripathi, ASG with
Mr. Manish Sharma, Advocate
versus
LEGEND HOLDINGS PTE.
LTD. ..... Respondent
Through Mr. Jayant Tripathi with
Ms. Prabhsahay Kaur, Advocates
% Date of Decision : April 29, 2010
CORAM:
HON'BLE MR. JUSTICE MANMOHAN
1. Whether the Reporters of local papers may be allowed to see the judgment? Yes.
2. To be referred to the Reporter or not? Yes.
3. Whether the judgment should be reported in the Digest? Yes.
JUDGMENT
MANMOHAN, J (ORAL)
1. This is a Petition under Section 34 of the Arbitration and
Conciliation Act, 1996 filed by the petitioner, MMTC Limited
(„MMTC‟) against M/s. Legend Holdings Pte. Ltd. („Legend‟). The
petitioner challenges the Award dated 29th July, 2002 wherein a sum of
USD 294,505.26 has been awarded at the then prevailing exchange rate
along with an interest of 18% per annum.
2. This Award relates to the deduction of an amount equivalent to
the Discharge Port Demurrage paid by petitioner.
3. All the other Claims of the respondent were rejected along with
all counter claims of the petitioner.
4. I may point out that the respondent had also challenged the same
Award to the extent of the other claims of the respondent which were
rejected by the Arbitral Tribunal in the Bombay High Court. The
Section 34 petition was dismissed on 24th February, 2003 and the
appeal preferred against it was also dismissed. It appears that the
matter was not taken up any further by the respondent and that part of
the matter attained finality.
5. Earlier, my predecessor had directed the examination of the issue
as to whether this matter should also be transferred to the Bombay High
Court. Now it transpires that the present objections were filed in the
Delhi High Court prior to the filing of Section 34 objections by the
respondent in the Bombay High Court. Therefore, the jurisdiction of
this Court is not ousted. Also, both parties have no objection to the
present Section 34 petition being heard and disposed of by this Court.
6. The facts entailing the dispute are as follows:
(i) On 23rd November, 1995, MMTC entered into a contract with
M/s. National Food Authority of Philippines ("NFA") for supply of
75,000 MT of Indian Non-Basmati Superfine White Rice to
Philippines. Legend offered MMTC to perform the Contract on a Back
to Back basis, which was agreed to by MMTC. A Back to Back
Contract was entered into between MMTC and Legend on 11 th
December, 1995. Under the terms of this Back to Back Contract,
MMTC was to get USD 8.00 per MT on the total sale made to NFA as
their service charges.
(ii) Legend in its turn entered into contracts with five Indian rice
suppliers and Letters of Credit (LCs) were opened in their favour by
MMTC as desired by Legend. These five suppliers on whom Legend
placed the initial contracts to supply rice failed to perform their
Contract within the stipulated time.
(iii) Non supply of rice to NFA resulted in their invoking the Grain
and Food Trade Association (GAFTA) provisions as per the
preliminary contract and in the reduction of the price of rice from USD
343.00 per MT, originally agreed, to USD 337.86 per MT with
extended time for shipment. To ensure the supply of the contracted
quantity, fresh contracts were awarded by Legend to seven Indian rice
suppliers. Fresh LCs were opened by MMTC in favour of these parties.
The supply of rice was completed. Admittedly NFA made payment of
the rice purchased from MMTC in the sum of Rs. 88,32,72,532/-.
(iv) Disputes arose between MMTC and Legend on the amount to be
paid to Legend out of the price received from NFA. Legend made a
claim against MMTC. MMTC in its turn made a counter claim against
Legend. These disputes were referred for arbitration to the Arbitral
Tribunal comprising Justice S. Ranganathan, Justice Avadh Behari
Rohatgi, and Justice R.C. Srivastava.
(v) Legend was wound up by an order dated 16th April, 1999 of the
High Court of Singapore and the Official Liquidator (Receiver) was
appointed. The Official Receiver was thus a party to the Arbitration
and was representing Legend.
(vi) Price Waterhouse was given the task of examining the books of
accounts and records. The summary of the report has been extracted in
para 12 of the Arbitral Award.
(vii) After the receipt of the report from Price Waterhouse, Legend
confined its claim to following three items :
a) Bank Charges for Non Operating L/Cs.
b) Pre-berthing Demurrage and Discharge Port Demurrage.
c) Other Expenses.
7. The Claim as to the Discharge Port Demurrage was allowed by
the Arbitral Tribunal. All the other Claims of the Respondent were
rejected along with all the Counter Claims of the petitioner.
8. The principle arguments which have been canvassed by Mr.
Parag P. Tripathi, learned ASG appearing on behalf of petitioner are
that the payment of Discharge Port Demurrage was made by the
petitioner as a "Settlement" in terms of the undated letter referred to in
para 71 of the Award. The respondent had specifically agreed that it
would be bound by any settlement made by MMTC while finalizing the
claims of the Seven Shippers who had provided the ships for transport
of rice from India to Philippines. It is submitted by Mr. Tripathi that
this Settlement, i.e., the payment of Discharge Port Demurrage, has to
be understood as a settlement contemplated and provided for in the said
undated letter. A copy of the said undated letter is to be found on the
record of the Arbitral Tribunal at Exhibit D-V at page 26 of the
Evidence Volume along with the affidavit evidence of Mr. D.S. Gulati,
Chief General Manager, MMTC.
9. At first blush, the argument may look attractive. However, on an
examination of the Award, it is clear that the Award proceeds on the
basis that NFA itself has admitted that the payment for Discharge Port
Demurrage was to be made by NFA (para 77 page 53). Therefore, on
the basis that since this payment was admitted by NFA, MMTC cannot
be allowed to mulct the liability on Legend and debit this payment to
the account of Legend.
10. It has been further contended by the learned Counsel for MMTC
that MMTC had communicated the message received from NFA by its
letter of 31.10.1997 to the respondent. The said letter of MMTC
extracted in full, the communication received from NFA to MMTC.
This letter of MMTC is extracted at para 40 of the Award. This
communication is in the form of a Table/Chart which in Column 3
makes it clear that even as per NFA‟s own computation, the Discharge
Port Demurrage was payable by NFA to the tune of USD 2,34,052.10.
11. Further, in Column 4, as per NFA calculation, after deducting
this amount, the balance dues payable to NFA by MMTC were USD
303,866.52.
12. Once this is so, it follows that as per NFA‟s own computation,
NFA was liable to pay Discharge Port Demurrage though only to the
extent of USD 234,052.10. In this background, the decision of the
Tribunal that this money could not be withheld by MMTC from Legend
on the ground that NFA had not actually paid this amount, appears to
me not only to be a plausible view but in fact the correct view. Once
NFA itself has admitted in writing that the sum of USD is payable by
NFA towards Discharge Port Demurrage, then surely irrespective of
whether or not, MMTC decided to litigate with NFA, MMTC cannot be
allowed to recover these monies from Legend. This contention
therefore is without any merit and is rejected.
13. The second contention raised by MMTC is that there is an
overlap between the Claims of the respondent and the counter claims
raised by MMTC. Therefore, it is argued on behalf of MMTC that
since all the other Claims of the respondent have been rejected, the
corresponding counter claims of the petitioner should be accepted. The
Arbitral Tribunal has proceeded on the basis that by a letter dated
25.5.1996, MMTC itself returned the Bank Guarantee to Legend which
had been furnished to MMTC for the performance of the Back to Back
Contract, by stating that the Contract was completed by Legend "in
full". The Tribunal invoking the principle of estoppel, proceeded to
hold that since the bank guarantee was discharged on account of the
contract being performed in full, MMTC was not be allowed to turn
back and raise counter claims.
14. I find no fault with the approach adopted by the Arbitral
Tribunal. It is settled law that if the view of the arbitrator is a plausible
one, the Court cannot substitute its own view in its place and would not,
therefore, merit any interference. (Refer Smita Conductors Ltd. Vs.
Euro Alloys Ltd. reported in (2001) 7 SCC 728, para 15, page 739;
BOC India Ltd. Vs. Bhagwati Oxygen Ltd. reported in (2007) 9 SCC
503, para 27, page 512).
15. I am also reminded of what Colman J. in his Master‟s Lecture
delivered in London on 14th March, 2006 on the subject "Arbitration
and Judges - How much interference should we tolerate?" had to say on
the question of error apparent and the jurisdiction which the Court
should exercise while examining a challenge to an arbitration award:
"What is obviously wrong? Is the obviousness something which one arrives at .... On a first reading over a good bottle of Chablis and some pleasant smoked salmon, or is „obviously wrong‟ the conclusion one reaches at the twelfth reading of the clauses and with great difficulty where it is finely balanced. I think it is obviously not the latter." (Refer to Russell on Arbitration, Twenty-Third Edition, Chapter 8-
138)
16. In this view of the matter, there is no need to further examine the
contention of MMTC that the counter claims ought to have been
allowed in view of the rejection of the claims of Legend.
17. However, before concluding, there are two other arguments of
Mr. Tripathi which require consideration. Firstly, it is contended by him
that since the Arbitral Tribunal has proceeded on the basis that NFA
itself has admitted its liability to pay the Discharge Port Demurrage, the
Award could be limited only to the extent of the admission. The
admitted amount, as mentioned in para 40 of the Award is USD
234,052.10. The amount awarded by the Arbitral Tribunal is USD
294,505.26. This latter figure seems to have arisen from the counter
claim made to this effect by the petitioner, which has been extracted as
Counter Claim no. 4 in para 80 to the Award. There is merit in this
submission and I accordingly reduce the Award amount of USD
294,505.26 to 234,052.10.
18. The second point of contention is that the interest granted by the
Arbitral Tribunal @ 18% per annum is excessive. As far as the award
of interest is concerned, I deem it appropriate to reduce the rate of
interest to 9% per annum simple interest for the period for which
interest has been awarded. The Supreme Court in Rajendra
Construction Co. Vs. Maharashtra Housing & Area Development
Authority and Ors. reported in (2005) 6 SCC 678; McDermott
International Inc.‟s case (supra) and Rajasthan State Road Transport
Corporation Vs. Indag Rubber Ltd. reported in (2006) 7 SCC 700 has
reduced the rate of interest. In fact, in Krishna Bhagya Jala Nigam
Ltd. vs. G. Harischandra Reddy & Anr. reported in (2007) 2 SCC 720
the Supreme Court has held as under :-
"11. ...... here also we may add that we do not wish to interfere with the award except to say that after economic reforms in our country the interest regime has changed and the rates have substantially reduced and, therefore, we are of the view that the interest awarded by the arbitrator at 18% for the pre-arbitration period, for the pendente lite period and future interest be reduced to 9%."
19. Consequently, keeping in view the aforesaid judgments and the
current rate of interest, I reduce the interest from 18% per annum to 9%
per annum from 1st January, 1997 (i.e. from the date when the monies
were withheld by MMTC) till the date of payment.
20. Accordingly, present petition is disposed of with aforesaid
modification.
MANMOHAN,J April 29, 2010.
rn
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!