Citation : 2010 Latest Caselaw 2010 Del
Judgement Date : 19 April, 2010
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ W.P.(C) 2248/2006
% Date of decision: 19th April, 2010
ASHOK KUMAR ARYA ..... Petitioner
Through: Mr. N. Prabhakar, Advocate
Versus
AIRPORT AUTHORITY OF INDIA ..... Respondent
Through: Mr. Raj Birbal, Sr. Advocate with Ms
Raavi Birbal and Mr. Prateek Garg,
Advocates.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? Yes
2. To be referred to the reporter or not? Yes
3. Whether the judgment should be reported Yes
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. The petitioner was on 21st October, 1980 appointed as an Airport Officer
(Operations) with the respondent Airport Authority of India. However, owing to
an incident in the night between 7th and 8th June, 1987, the petitioner on 8th June,
1987 was put under suspension and served with a charge sheet. The Disciplinary
Authority of the respondent Airport Authority on 26th September, 1989 passed an
order of termination of the petitioner. The petitioner preferred W.P.(C)917/1990
in this court against the order of the Disciplinary Authority. During the
pendency of the said writ petition, the departmental appeal of the petitioner was
also turned down on 20th August, 1990. The said writ petition was allowed by a
Single Judge of this court on 9th July, 1998 holding that there was absolutely no
evidence against the petitioner and the order passed by the Disciplinary
Authority was perverse. The respondent Airport Authority preferred LPA
400/1998. The Division Bench vide judgment dated 30th August, 2005, upheld
the order of the Single Judge of setting aside of the order of the Disciplinary
Authority, but only on the ground of non-furnishing of tentative reasons by the
Disciplinary Authority for disagreeing with the report of the Inquiry Officer and
non furnishing of the copy of the inquiry report to the petitioner. Accordingly,
the matter was remanded to the Disciplinary Authority for decision afresh.
While ordering so it was observed "It is also expected that since the matter is
very old, the Disciplinary Authority shall make all endeavour to complete the
proceedings as expeditiously as possible, preferably within a period of three
months from the date of receipt of a copy of this order".
2. The petitioner preferred SLP Civil 25994/2005 to the Supreme Court
against the judgment aforesaid of the Division Bench. The respondent Airport
Authority of India was admittedly unrepresented before the Supreme Court. The
said SLP was disposed of vide order dated 16th January, 2006 without issuance of
notice to the respondent Airport Authority with the following order:
"If no steps are taken within three months' time as granted by the High Court to comply with the High Court's order, liberty granted to the petitioner to ask the High Court for quashing of the proceedings altogether. The Special Leave Petition is disposed of."
It was thereafter that the present writ petition was filed on or about 15th February,
2006. It is the contention of the petitioner that the Disciplinary Authority of
Airport Authority of India having failed to initiate any steps within three months
of the order of the Division Bench in LPA No.400/1998, he has become entitled
to have the disciplinary proceedings against him quashed. Notice of this petition
was issued on 17th February, 2006. On 17th March, 2006 the counsel for the
petitioner contended that the show cause notice given by the Disciplinary
Authority to him on 8th March, 2006 was not in compliance with the directions of
the Division Bench and beyond the time granted by the Supreme Court. After
hearing the counsel for the parties, this court permitted the Disciplinary
Authority to pass an appropriate reasoned order within four weeks from then
without prejudice to the petitioner's right to maintain the present proceedings and
submit that the proceedings before the Disciplinary Authority were initiated
beyond the time granted by the Division Bench. The petitioner was also directed
to present himself before the Disciplinary Authority on 24th March, 2006.
3. It is the admitted position that the Disciplinary Authority again passed an
order on 28th April, 2006 of dismissal of the petitioner. On enquiry it is informed
that the petitioner again preferred a departmental appeal on 30th October, 2006.
The said appeal is informed to have been dismissed on 27th February, 2007. The
counsel for the petitioner also confirms that the petitioner has not preferred any
remedy against the order dated 28th April, 2006 of the Disciplinary Authority or
the order dated 27th February, 2007 of the Departmental Appellate Authority.
The counsel for the respondent Airport Authority on 16th May, 2007 contended
before this court that the petitioner having not challenged the fresh order of
Disciplinary Authority and the Appellate Authority, this writ petition has become
infructuous.
4. The counsel for the petitioner has contended that the present petition has
not become infructuous since the fresh proceedings before the Disciplinary
Authority and the Departmental Appellate Authority were in terms of the order
dated 17th March, 2006 in this petition i.e. without prejudice to the rights of the
petitioner to press the present petition.
5. Thus, the only point for consideration before this court is, whether in
view of the order dated 30th August, 2005 of the Division Bench of this court
directing the Disciplinary Authority to complete the remanded disciplinary
proceedings "preferably" within three months "from the date of receipt of copy
of that order" and / or on the basis of the order dated 16th January, 2006 (supra)
of the Supreme Court, the disciplinary proceedings (even though since concluded
and having attained finality as far back as on 28th April, 2006 and 27th February,
2007) are liable to be quashed for the reasons of the remanded proceedings
having not been completed/initiated within three months. Though neither party
has pointed out the date on which the copy of the order dated 30th August, 2005
was received by the Disciplinary Authority of the respondent and from which
date only the period of three months was to commence, but even if the said three
months is to be counted from the date of the order of the Division Bench, the
same would expire in end November, 2005. The decision dated 28th April, 2006
of the Disciplinary authority is thus delayed by about five months. The effect
thereof is to be seen.
6. As far as the order of the Division Bench is concerned, the same did not
make it mandatory for the Disciplinary Authority to complete the remanded
proceedings within three months. The said order was also not conditional. The
Supreme Court only gave liberty to the petitioner to apply to this court for
quashing of the proceedings "if no steps were taken within three months". The
Supreme Court also did not direct that the proceedings "be quashed" if no steps
were taken within three months.
7. I have inquired from the counsel for the petitioner whether the order dated
16th January, 2006 (supra) of the Supreme Court was communicated to the
respondent or to the Disciplinary Authority. The answer is in the negative. On
the contrary, it is the contention of the counsel for the respondent that the
petitioner intentionally concealed the said order so as to take undue advantage
therefor.
8. I have also inquired from the counsel for the petitioner whether the
petitioner, after the order dated 30th August, 2005 of the Division Bench,
approached the Disciplinary Authority for expediting the proceedings and/or
completing the same within the time of three months as directed by the Division
Bench. The answer is again in the negative. I have also inquired from the
counsel for the petitioner as to what prejudice, if any, has been suffered by the
petitioner by the delay of about five months in conclusion of the remanded
disciplinary proceedings. Except for contending that the petitioner has been
suspended since 1987, no other prejudice has been disclosed. I have also
inquired from the counsel for the petitioner as to what inference is to be drawn
from the petitioner not challenging the fresh decision of the Disciplinary
Authority and the Appellate Authority and allowing it to attain finality. The
counsel states that since the decision was required to be within three months and
there was no order of the Disciplinary Authority within three months he was not
required to challenge the decision rendered after the said period. I have also
inquired whether any time limit is prescribed in any statute or rules and
regulations for conclusion of the disciplinary proceedings. The answer is again in
the negative.
9. I am reluctant to quash the disciplinary proceedings in which the
petitioner has been found guilty, on the mere ground of delay particularly when
delay is not shown to have occasioned any prejudice to the petitioner. It is
significant that the direction of the Division Bench desiring the remanded
disciplinary proceedings to be concluded within three months was of its own
initiative and not at the asking of the petitioner. The petitioner also did not show
any anxiety to enforce the said direction. In fact, the delay by the petitioner of
about six months in preferring the departmental appeal shows that the petitioner
also was not treating time to be of any concern to him. The appeal was preferred
by the petitioner of his own volition and to take a chance therein. The counsel for
the respondent has also contended that the Disciplinary Authority had well prior
to the expiry of three months, even if counted from 30th August, 2005, issued a
show cause notice dated 28th November, 2005 to the petitioner. It is significant
that the Supreme Court also did not direct the disciplinary proceedings "to be
completed" within three months and only permitted the petitioner to apply for
quashing "if no step even in that direction" was taken within the said time of 3
months. Though there is some controversy about the issuance and service of the
said notice dated 28th November, 2005 with the respondent contending that the
petitioner has elsewhere admitted the same and has now falsely denied the
issuance thereof, but in the entirety of the facts aforesaid I do not deem it
appropriate to entertain the said controversy. Any person who is anxious for
expeditious disposal in ordinary course of human behaviour, is expected to bring
the direction of the court to the notice of the Disciplinary Authority for
compliance. The conduct of the petitioner of not communicating the order of the
Supreme Court is found to be intended to steal a march and which cannot be
permitted.
10. Else, it is the right of the employer to, in accordance with rules and
principles of natural justice, proceed against and punish the employee for
misconduct. The facts aforesaid do not make out a case for interfering with such
right of the respondent employer.
11. There is no merit in the petition. The same is dismissed. However no
order as to costs.
RAJIV SAHAI ENDLAW (JUDGE) 19th April, 2010 M
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!