Citation : 2010 Latest Caselaw 1829 Del
Judgement Date : 8 April, 2010
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ ARB. P.No. 53/2009
8th April, 2010
JINDAL STEEL & POWER LTD. ...... Petitioner
Through: Mr. A.S. Mathur, Advocate
VERSUS
N.S.ATWAL, SOLE PROPRIETOR,
GURU MEHAR CONSTRUCTION ....Respondent
Through: Mr. Siddharth Aggarwal, Mr. Simon Benjamin, Advocates CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see the judgment?
2. To be referred to the Reporter or not? Yes
3. Whether the judgment should be reported in the Digest? Yes
% JUDGMENT(ORAL)
VALMIKI J. MEHTA, J
Review Application No. 3/2010
1. A petition under Section 11 of the Arbitration and Conciliation Act, 1996
was filed by the review petitioner for reference of various disputes to arbitration.
This petition was disposed of vide order dated 03.12.2009 and the petition was
ARB. P.No. 53/2009 Page 1 dismissed. The order dated 03.12.2009 dismissed the petition as what was argued
was that those disputes be referred to arbitration which pertained to a loan given
by the petitioner to the respondent. It was found that the Loan Agreement was
much subsequent to and independent of the principal contract/work order dated
02.3.2001 placed upon the respondent by the petitioner (under which the
respondent was to carry out various services of excavation for the petitioner at a
site near Dongamohua Village District Raigarh, M.P.) and only the principal
contract contained the arbitration clause, whereas there was no arbitration clause
in the subsequent loan transaction.
2. Now, the present review application is filed pointing out a mistake that the
disputes which were sought to be referred through the petition under Section 11
of the Arbitration and Conciliation Act, 1996 were the disputes not only for the
Soft Loan Agreement but also with respect to the Agreement originally entered
into on 02.03.2001 and thereafter extended vide letter dated 17.7.2006 and
followed up by a work order dated 04.08.2006. In substance, what is stated in the
review application is that the petition under Section 11 was in two parts. The first
part sought reference of the disputes pertaining to the excavation works and the
second part sought reference of the disputes under the Soft Loan Agreement to
arbitration. Though the disputes under the Soft Loan Agreement were not
referred to arbitration, but, the disputes with respect to the original Agreement of
ARB. P.No. 53/2009 Page 2 excavation ought to have been referred to arbitration. It is not disputed by counsel
for the review petitioner that at the time of hearing which led to the passing of the
order dated 03.12.2009, arguments were only advanced for reference of the
disputes to arbitration with respect to the Soft Loan Agreement and not with
respect to the disputes pertaining to the Excavation Agreement. It is pleaded that
this is a bona fide mistake committed by the petitioner inasmuch as a reference to
the petition under Section 11 shows that what was sought to be referred to
arbitration were the disputes not only of the Soft Loan Agreement but also the
disputes arising out of the principal contract of excavation and as continued in
2006. It is contended that this mistake falls within the meaning of the expression
"any other sufficient reason" as found under Order 47 of the Code of Civil
Procedure, 1908 (CPC).
Notice was issued in this review application and time for reply was taken by
the respondent on 16.02.2010. Three weeks time was given to file a reply on
16.02.2010. However, till date no reply has been filed by the respondent. I am,
therefore, proceeding to dispose of the review application inasmuch as the
opportunity of filing the reply has not been availed by the respondent. In fact,
today, further time was sought for filing of the reply to the review application and
which I have declined.
ARB. P.No. 53/2009 Page 3
3. The counsel for the respondent vehemently argues for dismissing of the
review application and contends that the disputes with respect to the Agreement
of Excavation cannot be referred to arbitration inasmuch as the original contract
with respect to excavation activities containing the arbitration clause is dated
2.3.2001 and which stood expired after the four years period thereof. It is
contended that though the subsequent renewal letter dated 17.7.2006 was received
by the respondent, however, the consequent work order dated 4.8.2006, which
contained the Arbitration Clause, was not received by the respondent. It is,
therefore, contended that since the work order dated 04.08.2006 has never been
received by the respondent and since the respondent has not acted on that basis
disputes cannot be referred to arbitration pursuant to the work order dated
04.08.2006.
4. I do not agree with the contention of the learned counsel for the respondent
for the reason that even assuming that the work order dated 04.08.2006 is not
received by the respondent, it is not disputed that the letter dated 17.07.2006 has
been received by the respondent. This letter dated 17.07.2006 reads as under :-
"JSPS/VG/ORDER/2006/1707 July 17, 2006
M/s. Guru Mehar Construction
204, Avalon Apartments
New Mangla Puri
8, M.G. Road
New Delhi - 110 030.
ARB. P.No. 53/2009 Page 4
Kind Attn: Mr. N.S. Atwal
Subject: Excavation works at Jindal Opencast Coal Mine
Dear Sir,
Please refer to the various correspondences regarding the rates for excavation in various types of soil at the Coal Mine of Jindal Steel & Power Limited. The Management is pleased to renew your contract at the following rates:-
1) Excavation in Soil - Rs.30.25 / BCM - Diesel Capping - 0.6 Ltr/ BCM
2) Excavation in Coal -Rs.31.25 / BCM - Diesel Capping - 0.6 Ltr / BCM
3) Excavation in Hard Store / Shale - Rs. 38.63 / BCM - Diesel Capping
- 0.8 Ltr / BCM
The Excavation quantity for the contract period will be 8.5 Million BCM + 10%.
The above rate will be in force from 15th Feb 2006 to 31st March 2007. Based on your satisfactory performance the terms and contract will be decided further. You may approach ED, JSPL, Raigarh, who will issue formal work order to you.
Thanking you,
Yours faithfully, For JINDAL STEEL & POWER LIMITED
(VIKRANT GUJRAL) VICE CHAIRMAN & CEO"
5. The expression used in the very first para of this letter namely "renew" is
important. Renewal is an extension of an existing contract which is renewed i.e.
an old contract given a new life for a new period. It means that all the terms and
conditions of the original contract stand adopted subject to any variation
contained in the letter dated 17.07.2006. The only variation contained in the
ARB. P.No. 53/2009 Page 5 letter dated 17.07.2006 is the change in the rates with respect to excavation.
Thus, even if there is no work order dated 04.08.2006, the work order dated
02.03.2001 will hold the field and, admittedly, this work order contains an
Arbitration Clause.
6. In fact, the respondent itself understood the issue in this very manner
because in their letters dated 22.11. 2006 and 05.01.2007, the respondent itself
sought reference of the disputes to arbitration in terms of Clause 18 of the work
order dated 02.03.2001. These paragraphs of the letters of the respondent to the
petitioner dated 22.11.2006 and 05.01.2007 respectively read as under :-
"We hereby request you to refer the matter to Arbitration in terms of Clause 18 of the Work Order dated 02 March 2001, flowing out of which the entire episode has come off. We would be submitting our claims separately. The payments due to you or to us can only be finalized after the Arbitration award."
"In view of the above, we would once again request that an Arbitrator should be appointed in terms of Clause 18 of the Work Order dt. 02.03.2001"
7. In my opinion, therefore, clearly there is an Arbitration Agreement. This
Arbitration Agreement is Clause 18 in the work order dated 02.03.2001 and
which has simply been renewed by the letter dated 17.07.2006. Once there is a
renewal, and as already stated by me above, the original terms and conditions
continued and which original terms and conditions do contain an Arbitration
ARB. P.No. 53/2009 Page 6 Clause. Also as already stated by me above, the respondent itself has understood
this accordingly as per its letters dated 22.11.2006 and 05.01.2007.
8. The counsel for the respondent raised an additional point that no review
application is permissible once a petition under Section 11 of the Arbitration and
Conciliation Act, 1996 is disposed of. I have in fact wholly failed to understand
this argument of the learned counsel for the respondent. Surely, provisions of
review are available when a petition under Section 11 of Arbitration and
Conciliation Act is disposed of if the conditions contained in Order 47 CPC are
satisfied. A petition under Section 11 is dealt with by this Court as a delegatee of
the Chief Justice under Section 11 and this Court functions as a civil Court
exercising ordinary original civil jurisdiction vide Section 2(e) of the Arbitration
and Conciliation Act, 1996. To a Civil Court, the provisions of Code of Civil
Procedure, 1908 surely apply. I, therefore, fail to understand the argument raised
by the learned counsel for the respondent on the basis of Section 11 (and more
particularly sub-Section 7 thereof) that a review application is not maintainable
once a petition under Section 11 is disposed of.
9. No other issue/argument/point was urged by either of the parties.
10. Accordingly, I hold that there is an error or mistake apparent on the face of
the record being the order dated 03.12. 2009 and which has arisen on account of
ARB. P.No. 53/2009 Page 7 the bona fide mistake of the petitioner in not arguing for seeking reference of
disputes to arbitration in terms of the work order dated 02.03.2001 and continued
vide letter dated 17.07.2006, although, such a case was in fact laid down in the
petition under Section 11. In my opinion, this in fact also amounts to "any other
sufficient reason" as found under Order 47 Rule 1 of the Code of Civil Procedure,
1908. The disputes pertaining to the principal contract dated 2.3.2001 and as
renewed vide letter dated 17.7.2006 are therefore liable to be referred to
arbitration as there is an Arbitration Clause, the disputes fall within the scope of
the Arbitration Clause and there is no other objection to the maintainability of the
petition.
11. Accordingly, I hereby allow the review application and review the order
dated 03.12.2009 whereby, the petition under Section 11 will stand partly
dismissed in terms of the said order with respect to the Soft Loan transaction
between the parties, however, the disputes/differences/claims/counter-claims
pertaining to excavation activities and which are the subject matter of the work
order dated 02.03.2001 and as renewed by the letter dated 17.07.2006 are referred
to the arbitration of Hon'ble Mr. Justice R.C. Chopra (Retd.) N-7, Greater
Kailash-I, New Delhi-110048 (Mob: 9818097777). I am informed by the counsel
for the petitioner that the claim of the petitioner will be approximately in the
region of one and a half crores at least. This figure I am only stating in order to
ARB. P.No. 53/2009 Page 8 fix the fee of the Arbitrator and it will not prevent the petitioner from raising all
its claims whatsoever it deems fit before the learned Arbitrator. The fees of the
learned Arbitrator is fixed at Rs.2,20,000/- to be equally shared by the parties and
which will be payable in three equal portions. The first portion will be payable
when the Arbitrator enters upon the reference. The second tranche will be
payable when the evidence commences and the third part would be payable at the
time of commencement of the final arguments. The Arbitrator will in addition be
entitled to all actual out of pocket miscellaneous expenses including secretarial
charges. The petitioner should file his claim petition before the Arbitrator within
a period of three weeks from today. The respondent shall file the written
statement and counter claim, if any, within a period of three weeks thereafter.
Replication-cum-written statement to the counter claim be filed within a period of
three weeks thereafter.
12. Parties to appear for preliminary directions before the learned Arbitrator on
23rd April, 2010 at 5.00 PM. The Arbitrator shall endeavour to dispose of the
matter within a period of approximately one year from the date he enters
appearance. None of the parties will seek unnecessary adjournments in the
arbitration proceedings and Arbitrator will be entitled to impose costs with
respect to the unnecessary adjournments which are sought by either of the parties.
I may state that I originally intended to refer the matter to the Delhi High Court
ARB. P.No. 53/2009 Page 9 Mediation and Conciliation Centre, however, the counsel for the parties were not
agreeable in this regard.
13. The review application is accordingly disposed of in terms of the above,
leaving the parties to bear their own costs. Arbitration petition 53/2009 and the
review application both are now disposed of in terms of the present order. I may
clarify that since the Section 11 petition is partly allowed, no costs shall be
payable as imposed upon the petitioner vide order dated 03.12.2009.
VALMIKI J. MEHTA,
April 08, 2010
dkg/J
ARB. P.No. 53/2009 Page 10
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!