Citation : 2009 Latest Caselaw 3760 Del
Judgement Date : 15 September, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP No.537/2009 (U/s.34 of the Arbitration Act, 1996)
% Date of decision: September, 15th, 2009
M/S. HINDUSTAN TRADING COMPANY ....Petitioner
Through: Mr. . Parvinder Chauhan, Advocate
Versus
DELHI DEVELOPMENT AUTHORITY ... Respondent
Through: None.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? No
2. To be referred to the reporter or not? No
3. Whether the judgment should be reported
in the Digest? No
RAJIV SAHAI ENDLAW, J.
1 This petition under Section 34 of the Arbitration Act, 1996 is
preferred with respect to the arbitral award dated 16th June, 2009 of
Mr. Ashok Kumar, Vice Chairman of the DDA dismissing the claims
of the petitioner against the respondent DDA.
2 The petitioner was the highest bidder in an auction held by the
DDA for allotment of Idle Truck parking site at Timarpur. Pursuant
to acceptance of the bid, the petitioner was put into possession of the
said parking site and it is the admitted position that the petitioner
remained in possession of the same for the term of the license i.e. for
three years. It is also the admitted position that the petitioner has
paid license fee to the respondent / DDA for the said period of three
years as per its bid. The license deed executed between the parties
provided for arbitration.
3 It was the case of the petitioner that the aforesaid parking site
had encroachment to the extent of 40% and thus the area available
to the petitioner for parking was 40 % less and thus the petitioner
became entitled to remission of the license fee. The petitioner from
time to time made several representations to the respondent / DDA
claiming the said remission or calling upon the DDA to remove the
encroachment. Ultimately claim for approximately Rs.40 lacs on
account of remission of license fee for a period of three years on the
basis of 40% encroachment together with interest on the excess
license fee paid, was made. It is the said claim of the petitioner
which has been rejected by the arbitrator.
4 The arbitrator has in the award upheld the contention of
petitioner that there was an encroachment leading to reduction in
parking area available of 37% and which was subsequently on
removal of some encroachment reduced to 26.52%. As far as the
said finding (i.e. of encroachment of less than 40%) is concerned, the
same being a matter of fact is not interfereable in proceedings under
Section 34 of the Act. The petitioner also has not seriously
challenged the same.
5 The arbitrator has notwithstanding the encroachment declined
the claim of the petitioner for the reason, inter alia that the
petitioner as per the notice inviting tenders was required to, before
making the bid, inspect the site; it was held that the petitioner must
have made the bid with knowledge of the encroachment and it was
not the case of the petitioner that the encroachment was made after
he had made the bid; the arbitrator further held that even if the
encroachment had been made between the date of inviting the bids
and date of delivery of possession, the petitioner ought not to have
taken possession if had found his bid unviable for the reason of such
encroachment. The arbitrator has further held that the petitioner
thus must have made the bid as per which the payments have been
made, knowing the viability thereof and cannot seek remission of the
same. The arbitrator has next held that the petitioner could not be
allowed the remission inasmuch as that would amount to subverting
the whole process of inviting the bids and the auction. It has been
held that if the bid amount was allowed to be reduced as contended
by the petitioner, it would tantamount to bestowing an unfair
advantage to the petitioner over the other bidders. The arbitrator
has lastly held that inspite of the encroachments continuing, after
expiry of the term of three years of the petitioner, the license fee bid
for subsequent period for the same parking site was nearly double of
that being paid by the petitioner. The same was also held to be a
ground not entitling the petitioner to any remission.
6 The grievance of the petitioner is as follows. Firstly, it is
contended that the arbitrator has not followed the due procedure. It
is contended that only one hearing was held and that the response of
the respondent / DDA to the claims of the petitioner was not even
placed before the arbitrator on the date of the said hearing or
supplied to the petitioner; that the petitioner had no opportunity of
meeting the said response of the respondent; that in fact the
petitioner obtained copy of the same only after the award. It is also
contended that the award is exactly the same as the
response/comments of the respondent/DDA and which showed non-
application of mind on the part of the arbitrator.
7 Secondly, it is contended that the practise of giving remission
with respect to such parking sites owing to encroachment is a well
established pratise; the counsel for the petitioner contends that such
remissions have been given in a large number of cases regularly and
there are over a hundred orders of the courts granting such
remission. Reference is also made in the OMP itself to at least two
orders of this court made in writ petitions, though the copies of the
said orders have not been supplied. The counsel thus contends that
the award is contrary to substantive law.
8 Lastly, it is contended that the award ought to shock the
judicial conscience of this court inasmuch as the petitioner has been
treated unfairly qua others who have been granted a remission.
Reliance in this regard is placed on Paragraph 12 of DDA Vs. R.S.
Sharma & Co. 2008 X AD (SC) 393.
9 As far as the plea of the arbitrator not following the procedure
is concerned, Section 19 of the Act permits the arbitrator to
determine his own procedure. It is not the case that the parties in
the present case had agreed to any procedure which has not been
followed by the parties. Though on the basis of the averments made,
principles of natural justice appear to have been violated but in the
OMP nothing has been stated as to what prejudice has been suffered
by the petitioner owing to being not furnished copy of the response
of the DDA or no hearing thereon being given to the petitioner. The
counsel for the petitioner has during the hearing also not disclosed
as what would have been the rejoinder or contention of the
petitioner to the reply/response of the DDA or as to how it could have
altered the reasoning given in the award without it being pleaded
and established that had opportunity been given, the arbitrator could
not have arrived at the findings reached, no ground of deprivation of
opportunity or irregularity in procedure can be agitated.
10. The petitioner has not even controverted the finding of the
arbitrator of the site remaining encroached and fetching nearly
double the license fee after the expiry of the term of the petitioner.
Without any prejudice having been shown to have been caused to the
petitioner owing to the irregularity in procedure alleged, no case on
that ground under Section 34 of the Act is made out. The reasoning
given in the award is based on the admitted documents and cannot
be faulted with.
11 I have also inquired from the counsel for the petitioner as to
whether the area in sq. yds./sq. mts. of the parking site was
disclosed in the notice inviting tender. The counsel for the petitioner
has fairly stated that though the area was not disclosed but the DDA
maintains a register in which the area in square yards/square metres
of each parking site is mentioned and since it is the same set of
people who usually participate in the bids for the parking sites, they
are in the know of the said area and make their bids accordingly. It
is also admitted that the encroachment was existing on the date of
the making of the bid by the petitioner. The counsel however
contends that the respondent being a state, the petitioner expected
that the encroachment would be removed at the time of possession
else the remission as per practise shall be given. It is further
contended that the arbitrator being the Vice Chairman of the DDA
itself was aware of the practise and ought not to have made the
award in contravention thereof.
12 The arbitrator has made the award in accordance with the
contract between the parties and as per which contract the
petitioner had agreed to make the payments at the rates made and I
find nothing contrary to substantive law of the land, in the award
holding the petitioner not entitled to wriggle out of the said contract.
The reasoning given by the arbitrator that if the petitioner is
permitted to do so it would subvert the auction is also found to be
cogent. Even if the petitioner had any expectation that the
encroachment shall be removed before the delivery of possession,
there is nothing to show that the bid of the petitioner was subject to
any such condition or the petitioner prior to taking possession made
any such demand on the respondent. The petitioner after entering
into possession of the parking site on the basis of the bid, cannot be
permitted to wriggle out of the same. Had the petitioner made the
said intention known, the respondent could have re-auctioned the
site and given equal opportunity to the other bidders also to make a
bid with the existing encroachment. Similarly the logic adopted by
the arbitrator that as per the terms of the notice inviting tender the
petitioner was required to inspect the site is found to be sound.
13 There is yet another aspect of the matter. The petitioner, upon
the respondent/DDA not agreeing to reduce the license fee had the
option to terminate the contract and walk out of the parking site.
The petitioner did not do so. It appears that the bid made by the
petitioner was viable and that is why the petitioner allowed the
contract to run for its entire length and subsequently wanted refund
of nearly half of the license fee paid also.
14 The counsel for the petitioner has lastly urged that the
petitioner has been very fair to the respondent in the matter of
paying the license fee as per contract. It is urged that most of the
contractors stop paying the license fee on such grounds. However
this court in the exercise of jurisdiction under Section 34 cannot
enter into such aspects. There is nothing to shock the judicial
conscience of this court also. The petitioner with its eyes open had
made the bid and carried on business on the terms agreed. It is the
petitioner which was by making claims for remission seeking to put
the respondent in a disadvantageous position.
14 No ground under Section 34 of the Act for issuance of the
notice is made out. Petition is dismissed. No order as to costs.
RAJIV SAHAI ENDLAW (JUDGE) September 15, 2009 J
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!