Citation : 2009 Latest Caselaw 3644 Del
Judgement Date : 9 September, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP No.314/2009
% Date of decision:09.09.2009
M/S TECHMAN SHELTERS PVT. LTD. ....Petitioner
Through: Mr. Sudhir Nandrajog, Senior Advocate
with Mr. Trideep Pais Mr. Shivam
Sharma & Mr. Rakesh Mishra,
Advocates.
Versus
SH. VIJAY CHOUDHARY ... Respondent
Through: Mr. Abhay Kumar, Advocate.
AND
OMP No.318/2009
M/S TECHMAN SHELTERS PVT. LTD. ....Petitioner
Through: Mr. Sudhir Nandrajog, Senior Advocate
with Mr. Trideep Pais Mr. Shivam
Sharma & Mr. Rakesh Mishra.
Versus
SH. SANJEEV SINGH & OTHERS ... Respondents
Through: Mr. Abhay Kumar, Advocate.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? NO
2. To be referred to the reporter or not? NO
3. Whether the judgment should be reported NO
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. These petitions, both under Section 9 of the Arbitration and
Conciliation Act, 1996 are in respect of two agreements, informed to
be identical, and entail the same questions of law and fact. Vide
order dated 10.06.2009 in these petitions, after hearing the counsel
for the parties, this court was pleased to direct the parties to
maintain the status quo with respect to title and possession of the
property subject matter of the petitions in terms of the report of the
Court Commissioner appointed on that date. The Commission has
been executed and the Court Commissioner has filed the report in
this court.
2. The respondents have not filed any reply to these petitions.
The counsel for the respondent has urged that as per the agreement,
the parties prior to arbitration are required to approach the named
persons for mediation and the parties had further undertaken not to
approach the Court but to resolve the disputes through mediation as
aforesaid and only if the mediation fails, the matter was agreed to be
submitted for conciliation or arbitration under the Arbitration and
Conciliation Act, 1996.
3. Counsel for the respondent has contended that there is no
averment whatsoever in the petition of the petitioner having
approached the mediators aforesaid or of the mediation having failed
and since the arbitration agreement was to come into effect
thereafter only, even this petition is not maintainable without
process of mediation being followed.
4. It is also contended that these petitions are not maintainable
for the reason of the petitioner having filed the application under
Section 9 of the Act for the same reliefs as claimed in these petitions
before the Court of the Civil Judge, Delhi.
5. The petitioners had prior to the institution of this petition
instituted a suit in the Court of the Civil Judge, Delhi for declaration
and permanent injunction inter alia with respect to their rights in the
same properties. The respondents on being served with the notice of
the said suit filed an application under Section 8 of the Act in the
suit. Thereafter, the petitioner herein filed an application under
Section 9 of the Act in the same suit.
6. During the pendency of the aforesaid proceedings, these
petitions came to be filed and the disclosure of the previous
proceedings was made in the petition and in fact, the counsel for the
respondent also has made a submissions on the basis of the copies of
the pleadings in the suit aforesaid filed along with the petition.
Senior Counsel for the petitioner has pointed out that in fact prior to
approaching this Court, the petitioner had already applied to the
Court of the Civil Judge, Delhi for withdrawal of the application
preferred under Section 9 in the suit. It is fairly stated that the said
application in the suit was misguided and the remedy of the
petitioner was by way of an independent OMP as has now been
preferred. Counsel for the respondent has contended that the
application for withdrawal of application under Section 9 in the suit
was also pending as on the date of the institution of these petitions.
7. In my view, the petitioner would not be disentitled from
maintaining these petitions for the reason of having filed Section 9
application in the suit before the Civil Judge. In view of the
arbitration agreement between the parties, the suit in any case was
barred and not maintainable and thus the question of preferring the
Section 9 application therein did not arise. Therefore, the earlier
proceedings do not come in the way of the petitioner.
8. As far as other contention of the respondent is concerned,
though there is some ambiguity in the arbitration agreement i.e
whether the same constitutes an agreement for arbitration or not but
in view of the pleadings of the respondents in the previous
proceedings aforesaid and on which reliance is placed in this Court
also, the respondents have within the meaning of Section 7 (4) (c) of
the Act admitted the existence of the arbitration agreement. Senior
counsel for the petitioner also drawn attention to the application
under Section 8 preferred by the respondents, wherein, the
respondents have stated that a serious dispute had arisen between
the parties, they ought to be referred for arbitration as per the
agreement and the petitioner herein had abused the process of the
Court by instituting the suit.
9. The clause aforesaid on which reliance is placed by the
respondent in my view does not bar a petition under Section 9 of the
Act. Even if the arbitration is agreed to be preceeded by mediation,
the fact remains that the parties had agreed to arbitration. Once
such an agreement exists, the Court would be empowered under
Section 9 and any party entitled to a relief under Section 9 would be
entitled to approach the Court. Merely because the parties had
agreed to preceed arbitration with mediation cannot prohibit the
remedies available to them in law and the clause in the agreement
prohibiting the parties from approaching the Court till mediation, is
found to be against public policy. The interim measures to which a
party may be entitled to, may become infructuous if the filing of the
petition under Section 9 has to be deferred during mediation. The
parties had not agreed to any time schedule also for mediation.
10. The senior counsel for the petitioner has in this regard also
cited M.K. Shah Engineers & Contractors Vs. State of Madhya
Pradesh (1999) 2 SCC 594. The Supreme Court held that the steps
preceeding the coming into operation of the arbitration clause,
though essential are capable of being waived.
11. The counsel for the respondent has also urged that till now the
petitioner has not approached the agreed mediators and if the
petitioner still approaches the mediators, the need for arbitration
may not arise. On enquiry, it is informed that the respondents have
also not approached the mediators till date. The dispute between the
parties are pending since long. From the conduct of the respondents
of having not taken any steps for mediation and of applying under
Section 8 of the Act, the respondents are deemed to have waived
mediation as a precursor to arbitration. In any case, if the parties
feel the need for approaching the mediators, the parties would still
be entitled to do so.
12. The Senior Counsel for the petitioner has also urged that para
16 of the order dated 10.06.2009 is ambiguous and may lead to
further disputes. The petitioner had agreed to at its own cost raise
construction on the land/property of the respondents; in lieu thereof
the built up area was agreed to be shared by the parties; the
petitioner had also advanced some monies to the respondents which
were agreed to be refunded by respondents on completion of
construction. Attention is invited to Clauses 10 & 11 of the
agreement between the parties, wherein, the respondents have
agreed not to sell, use, mortgage, lease or convey their entitlement
of the built up area in the property until the refund of the monies to
the petitioner. Counsel for the respondent has controverted the
same by drawing attention to Clause 19 of the agreement,
whereunder, the respondents are entitled to compensation from the
petitioner for delay in construction. It is contended that the
petitioner delayed the construction and hence, the respondents are
entitled to compensation and thus, no monies are refundable by the
respondents to the petitioner. However, all that is to be the subject
matter of the arbitration and the respondents cannot decide for
themselves that the delays were occasioned owing to the petitioner
or the amount of compensation due to them or for no refund being
due to the petitioner for this reason.
13. The parties having contracted that the respondents shall not
sell their entitlement of the built up area also till settlement of the
dues of the petitioner, till the same is done and which can be done
only in arbitration, the respondents are not entitled to sell any
portion of their entitlement also of the built up area of the property.
14. Accordingly, these petitions are disposed of directing both the
parties to maintain status quo qua title, possession and use for the
properties subject matter of these petitions, in terms of the report of
the Local Commissioner. No order as to costs.
15. Senior Counsel for the petitioner has expressed apprehension
of breach of the said order. Considering the locality and nature of
disputes the SHO concerned is directed to ensure compliance of the
order.
RAJIV SAHAI ENDLAW (JUDGE)
September 9th, 2009 rs
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!