Citation : 2009 Latest Caselaw 4474 Del
Judgement Date : 5 November, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP No.601/2009
5th November, 2009
M/S.ANUKAMPA SOLUTIONS PRIVATE LIMITED ...Petitioner
Through: Mr. Akhil Sibal, Advocate with
Mr. Rohan Dheman, Advocate.
VERSUS
UTTAR PRADESH STATE ROAD TRANSPORT CORPORATION & ORS.
.....Respondents
Through: Mr. Neeraj Kishan Kaul, Senior
Advocate with Ms. Garima
Parshad, Advocate and Ms.
Neha Goyal, Advocate.
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see
the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
% JUDGMENT (ORAL)
VALMIKI J. MEHTA, J.
1. This is a petition under Section 9 of the Arbitration and
Conciliation Act, 1996 whereby the petitioner has in effect prayed for the relief
that the respondents be restrained from in any manner interfering with its
operations of running a food plaza (single storeyd medium size structure as the
photographs shop) at Ajmeri Gate Inter State Bus Terminal, New Delhi. The
O.M.P. No.601/2009 Page 1 land on which the food plaza now exists belongs to the Uttar Pradesh State
Road Transport Corporation-the respondent No.1. The other respondents are
designated authorities of the respondent No.1.
2. The facts of the case are that an agreement dated 23.11.2006 was
entered into between the respondents and the petitioner whereby the petitioner
within a period of four months from the date of the agreement had to construct a
food plaza and run the same subject to various terms and conditions as set out in
the subject agreement. I may, at this stage, note certain important clauses of
this agreement and which are:
(i) Clause 2, which requires construction within a period of four
months subject to any extension which may be granted by the respondents if the
delay is found to be unavoidable.
(ii) Clause 6, pertaining to payment of licence fee @ Rs.17,500/- per
month after the expiry of the period of four months or completion of the facility
for operation, whichever is earlier. I may note that a conjoint reading of clauses
2 and 6 show that just because the extension is granted, will not mean that the
payment of licence fee will not commence after the original stipulated period of
four months.
(iii) Clause 16, as per which the title, interest and ownership with
respect to the food plaza and the land allotted shall always remain vested with
O.M.P. No.601/2009 Page 2 the respondents herein and the petitioner herein shall not be the owner of either
the land or the superstructure or the fixtures and fitting therein.
(iv) Clause 19, as per which power is vested with the respondents to
cancel/revoke/terminate the agreement on account of the breach of stipulated
terms and conditions by the petitioner herein,
(v) Clause 32, which requires that on completion of the licence period,
the petitioner shall hand over vacant possession of the food plaza so constructed
along with the fixtures and fitting as per the inventory within 24 hours.
(vi) Clauses 9, 10,11,15,23,28,29 are various clauses which show that
overall supervision and control with respect to the food plaza shall remain
vested with the respondents because by virtue of these clauses, the respondents
were entitled not only to fix the rate list with respect to certain food items, it
was also entitled to also see that the food plaza is not used for any undesirable
purpose, hygiene standards and so on are maintained, the waiters are in uniform
and are courteous, maintenance of general cleanliness and so on. These clauses
seem to have been incorporated as the food plaza was to cater to the general
public coming at the Inter State Bus Terminal and which required
reasonableness in running of the food plaza as the respondents are an arm of the
State Government and its actions were also to be guided by public interest
besides the profit motive.
O.M.P. No.601/2009 Page 3
3. A reading of the aforesaid clauses of the subject agreement makes
it more than amply clear that the relationship between the parties is one of the
petitioner as a licensee of the respondent- licensor. The petitioner had no right,
title and interest in the land or the constructed superstructure or the fixtures and
fittings therein, all of which always vested with the respondents. The agreement
was specifically terminable though of course on happening of contingencies of
breach of the stipulation provided under the contract. As already stated there is
no provision for any extension of time from payment of licence fee after the
initial period of four months. The intention as reflected by the relevant clauses
of the contract was that respondents would earn revenue by receiving licence
fee after about four months of entering into the subject contract.
4. Admittedly the petitioner could not complete the construction
within either the original period of four months which expired on 23.3.2007 and
even thereafter within the extended period of three months which expired on
23.6.2007. I may note that extension was requested by the petitioner because of
its own default in proceeding with construction activities without obtaining
approval of the plans. It has become clear from the record that since the
construction activities which were being undertaken by the petitioner were
without any sanction of the Municipal Authorities the same were therefore
objected to by the respondent who issued a notice dated 14.6.2007 for stopping
of the construction unless the necessary sanctioned plans are obtained from the
O.M.P. No.601/2009 Page 4 Municipal Authorities. The sanction is obtained in this case admittedly only on
26.12.2008 i.e. more than one and half year after the extension expired on
23.6.2007. Considering that the original period of completion was four months,
taking one and a half years for obtaining sanction is indeed a long delay. Thus,
the delays in construction well beyond the four months was for reasons solely
attributable to the petitioner.
5. At this stage, I may note two letters dated 15.6.2009 and 2.7.2009,
which have been written by the respondents to the petitioner whereby in terms
of the first letter temporary permission was granted to the petitioner to run the
food plaza and by the second letter a continued permission (not temporary) was
given to run the food plaza. The last line of the letter dated 2.7.2009 addressed
by the respondent to the petitioner makes it clear that the extension was not a
conditional one and the permission is a general permission.
6. Relying on the aforesaid two letters dated 15.6.2009 and
2.07.2009, the counsel for the petitioner Mr. Akhil Sibbal has very strenuously
and emphatically contended that, that by virtue of issue of these two letters, all
breaches of the petitioner prior thereto, whether they be with regard to the
period of construction or non-payment of license fee, or any other breaches in
terms of the agreement stood condoned by the respondents.
7. Mr. Sibbal has also canvassed that both in equity and in law, the
petitioner having constructed the food plaza and since the same is presently
O.M.P. No.601/2009 Page 5 running, even if may be only from last two months or so instead of from
23.6.2007, the reliefs which have been prayed in this petition may be granted to
the petitioner inasmuch as at this stage the court should not undertake a mini
trial by deciding whether or not the termination is justified. He further
contended that whether or not breaches have been committed and whether or
not termination is justified, would be issues which would be taken up in the
substantive arbitration proceedings which would be initiated between the
parties.
8. In response, Mr. Neeraj Kishan Kaul, Senior Advocate on behalf of
the respondents has urged the following contentions:-
(i) the letters dated 15.6.2009 and 2.7.2009 cannot be and should not
be interpreted to mean that each and every breach whether it is of payment of
license fee or submission of the rate list of the food items for approval or
submission of the list of fixture and fittings which ultimately were to fall to the
ownership of the respondents can be said to have been waived.
(ii) It was further contented on behalf of the respondents that the
contract in this case is determinable by virtue of Clause 19 on account of the
breaches committed by the petitioner. In this regard, Mr. Neeraj Kishan Kaul
has referred to Section 14(1) (c) of the Specific Relief Act, 1963 which says that
a contract which in its nature is determinable cannot be specifically enforced
and since such a contract cannot be specifically enforced then by virtue of
O.M.P. No.601/2009 Page 6 Section 41(e) of the Specific Relief Act, no injunction can be granted the effect
of which is to enforce specific performance. Reliance has been placed on
Rajasthan Brewaries Ltd vs. The Stroh Brewary Co. AIR 2000 Del 450 (DB)
and Indian Oil Corporation Ltd vs. Amritsar Gas Services, (1991) 1 SCC 533
to canvass that the determinable nature of the contract disentitles the relief of
specific performance or injunction even when the contract is determinable not
at all will but it encompasses determination on the contingencies of the breaches
having been committed.
(iii) Mr. Neeraj Kishan Kaul has further contended that, the fact that
overall control and supervision on day to day issues, in view of the public
interest element of the contract, being whether of hygiene or cleanliness,
whether or not carrying on undesirable activities or certain standards being
maintained or courteous behaviour to customers having to be maintained and all
other such clauses in the agreement would show that if injunction is granted and
specific performance is allowed, the contract would run into such numerous and
minute details which the Court will not be able to supervise on a day to day
basis and consequently in terms of Section 14(1)(b) of the Specific Relief Act
even assuming the respondents are guilty of breach of contract even then no
specific performance is allowable and consequently no injunction can be
granted and at best the entitlement of the petitioner is to claim damages. To
buttress this argument, Mr. Neeraj Kishan Kaul, relied upon Section 14(1)(a)
O.M.P. No.601/2009 Page 7 which says that where the breach can be compensated by damages, specific
performance and injunction ought not to be granted by the Courts.
(iv) Mr. Neeraj Kishan Kaul has finally relied upon the termination
letter dated 24.9.2009 issued by the respondents against the petitioner in which
three specific breaches have been stated viz of non-payment of licence fee, non
submission of the rate list of the food items for approval and not giving the
details of the fixtures and fittings in the food plaza. Mr. Neeraj KishanKaul has
very emphatically stated that the respondents have not received the two letters
dated 16.9.2009 and 19.9.2009 which the petitioner claims to have written to the
respondents. Mr. Akhil Sibbal on the contrary has stated that one letter dated
19.9.2009 was sent by speed post AD.
9. An application under Section 9 of the Arbitration and Conciliation
Act has to be disposed of on the principles of Order 39 Rules 1 and 2 of the
Code of Civil Procedure, 1908 (CPC). It is trite that for disposal of such an
application, the court has to see the existence of a prima facie case, balance of
convenience and irreparable injury which will be caused to either of the parties.
Keeping these principles in view and the law as applicable, I am of the opinion
that this petition is clearly liable to fail and cannot succeed. The reasons for the
same are :-
(i) A person who is himself guilty of breach of contract cannot approach
the court for any relief, much less for an equitable relief of injunction.
O.M.P. No.601/2009 Page 8 As per clause-6 of the agreement the licence fee became payable after
four months of execution of agreement on 23.11.2006 and admittedly
licence fee (that too just Rs.7000/-) was allegedly offered for the first
time as late as two and a half years later in September, 2009. Even
taking a benign interpretation of clause 6 in favour of the petitioner,
the payment of licence fee in any case became due from 23.06.2007
when the only extension granted expired. As stated above admittedly
no licence fee was paid till at least September, 2009 when Rs.7000/- is
offered by the letter dated 19.9.2009. There is thus a clear breach of
contract on the part of the petitioner and that too of a fundamental
term of the contract. Further I may add that assuming for the sake of
arguments if every breach committed earlier was condoned by the
letter dated 2.7.2009 of the respondents it cannot have condoned
future breaches. The licence fee therefore, became payable at least
from July, 2009 and which again was not offered till 19.9.2009 and
when a piffling figure of Rs.7000/- is alleged to be sent. In fact, the
petitioner ought to have sent the entire arrears with contractual interest
thereon. There can be thus no doubt that the petitioner was in breach.
(ii) In the present case, not only the contract runs into minute details
which the court cannot supervise on a day to day basis, the fact of the
matter is that in such commercial contracts at the very best, the
petitioner would have earned profits and which can surely can be
O.M.P. No.601/2009 Page 9 quantified in terms of money for which claims can be filed before the
Arbitrators assuming that the respondent is guilty of breach of contract
and not the petitioner. The petitioner can also quantify in money terms
the cost of construction of the single storeyed structure made by it.
(iii) The judgment of the Division Bench of this court in the case of
Rajasthan Brewaries Ltd. ( supra) is binding on me and clearly
provides that even if, the contract is determinable on account of breach
and the contract is not one which is determinable at will, even then,
the provision of Section 41(e) of the Specific Relief Act would apply
and injunction cannot be granted where a contract has been terminated
on account of breaches committed by the defaulting party. To the
same effect is the judgment in the case of Amritsar Gas Services
(supra).
(iv) I am of the opinion that once a licensee, always a licensee. This
principle has been clearly laid down in a Full Bench decision of this
court reported as Chandu Lal vs. MCD AIR 1978 Del 174 . In fact,
the Full Bench of this Court in this judgment has laid down that a
licensee after his licence is terminated is not entitled to any interim
injunction and in fact the licensor is entitled to use reasonable force to
throw out the licensee from the licenced premises. I may also note at
this stage that a Division Bench Judgement of this court in the
judgment reported as DTTDC Vs. D.R.Mehra & sons 62(1996) DLT
O.M.P. No.601/2009 Page 10 234 declined an injunction which was prayed for by a licensee by
stating that a licencee after termination of the licence is not entitled to
injunction and even if he is in possession such a relief cannot be
granted to him and the Division Bench clearly stated that a licencee
should not be allowed to urge the argument of due process of law
because such issue will not arise if the licencee himself acts fairly and
vacates the premises.
10. The issue of balance of convenience and irreparable injury in a
case like this has necessarily to be seen from the perspective of the legal bar
with respect to the grant of injunction because of Sections 14 (1),(a),(b) &
(c) read with Section 41(e) of the Specific Relief Act. If the law itself
disentitles any injunction, then equities cannot have any say. That being the
position and in view especially of the law with relation to termination of
license, the balance of convenience is not in favour of the petitioner but in
favour of the respondents as the petitioner will be compensated suitably by
damages in case the respondent is found guilty of committing breach of
contract. I may finally note that by looking at facts to arrive at a decision on
an application for injunction under Section 9, it cannot be said that a Court
conducts a mini trial. This Court is mandated to see the strength of the cases
of the respective parties to arrive at a decision by virtue of Colgate
Palmolive vs. Hindustan Liver Ltd. (1999) 7 SCC 1. Mini trial would only
O.M.P. No.601/2009 Page 11 be when highly disputed questions of facts are decided while deciding an
application under Order XXXIX CPC, and which is not so in the present
case in view of the basic facts as stated above being admitted or become
apparent from the record. The contention of the petitioner of "mini trial" is
thus not well founded.
11. In view of the aforesaid the present petition under Section 9 is
dismissed with costs which are quantified at Rs.1 lac and which shall be payable
within two weeks from today failing which the same will carry interest @ 18%
per annum. With the aforesaid observations, this petition is disposed of. The
imposition of costs is in terms of the judgment of the Supreme Court reported as
Salem Advocate Bar Association Vs. Union of India (2005) 6SCC 344, para 37
thereof, whereby the Supreme Court has said that it is high time that instead of
nominal costs, actual costs should be imposed. For awarding of costs, I have
noted the financial capacity of the parties in this case and the claims and issues
involved. AS per Section 35 and Order 20 A of the CPC costs have to
necessarily follow the event.
At this stage, Mr. Neeraj Kishan Kaul, very fairly waives the costs
subject to the condition that if the petitioner prefers an appeal such concession
would stand withdrawn.
NOVEMBER 5, 2009 VALMIKI J. MEHTA, J Ne/ib O.M.P. No.601/2009 Page 12
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!