Saturday, 25, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Lal Builder vs Union Of India & Ors.
2009 Latest Caselaw 2117 Del

Citation : 2009 Latest Caselaw 2117 Del
Judgement Date : 18 May, 2009

Delhi High Court
M/S Lal Builder vs Union Of India & Ors. on 18 May, 2009
Author: Shiv Narayan Dhingra
*             IN THE HIGH COURT OF DELHI AT NEW DELHI



                                                       Date of Reserve: 12.5.2009
                                                        Date of Order: May 18, 2009

+ OMP No. 356/2005
%
                                                               18.05.2009
        M/s Lal Builder                                  ...Petitioner
                             Through : Mr. Sukesh Kumar, Advocates

        Versus

        Union of India and others                ...Respondent
                             Through:Ms. Geetanjali Mohan, Advocate
                             and Ms. Vaishnavi, Advocate


        JUSTICE SHIV NARAYAN DHINGRA

1.      Whether reporters of local papers may be allowed to see the
        judgment?

2.      To be referred to the reporter or not?

3.      Whether judgment should be reported in Digest?


        JUDGMENT

1. By this petition under Section 34 of Arbitration and

Conciliation Act, the Petitioner has assailed an award dated 5th July,

2005 passed by the Arbitral Tribunal whereby the Tribunal had partly

allowed the claims of the petitioner and partly disallowed the claims of

the petitioner.

2. The award has been challenged on the ground that Learned

Arbitral Tribunal failed to give reasons for denial of the claims. It is

submitted that claim No.1 was denied by the Arbitral Tribunal on the

OMP No. 356/2005 M/s Lal Builder v.Union of India and others Page 1 Of 4 ground of improper planning and assumption, which shows lack of

application of mind by the Arbitral Tribunal. None of the parties had

claimed that there was improper planning and assumption. The total

work awarded was for Rs.60,46,651/-. There was no evidence that the

work was reduced due to improper planning. It is also submitted that

the Arbitrators were not experts who could have arrived at a conclusion

about the planning in the matter of civil contracts.

3. The other ground of challenging the award is that the

Arbitral Tribunal rejected some of the claims of the petitioner on the

basis of measurement recorded in the measurement book (MB), while

in fact the petitioner had done much more work than all the work

shown in the MB. It is submitted that the original work awarded was

more than of Rs.60,00,000/- . After the petitioner had left the work

remaining work was awarded for a sum of Rs.14,00,000/- only to the

subsequent contractor. If the petitioner had not done the work to the

extent of Rs.46,00,000/- the remaining work would not have been of

Rs.14,00,000/-. Thus, the Arbitral Tribunal should have taken this into

consideration and should have reached the conclusion that the MB had

not correctly recorded the work done. The petitioner also challenged

awarding of Rs.89,449/- by the Arbitral Tribunal to the respondent on

the ground that the Arbitral Tribunal lost sight of the fact that the

applicant could not have removed any material from the site without

prior permission of the authorities concerned.

4. The petitioner assailed the award also on the ground that

claim No.3 of the petitioner was rejected without any basis. The

OMP No. 356/2005 M/s Lal Builder v.Union of India and others Page 2 Of 4 Arbitral Tribunal failed to appreciate the evidence produced by the

petitioner. Regarding claim No.4, it is stated by the petitioner that the

Arbitral Tribunal did not consider Clause 21.5 in proper prospective.

The Arbitral Tribunal should have decided this claim on the basis of

work done as claimed by the petitioner. Similarly, regarding claim No.5

it is stated that the Arbitrators did not even pronounce upon the claim

of Rs.5,00,000/- made by the petitioner for mental agony and hardship

caused to the claimant due to unilateral recession of the contract.

5. A perusal of the award would show that the Learned

Arbitral Tribunal had considered the claims of the petitioner and

counter-claim of the respondent on the basis of measurement book

which records the measurement of the work done. The contention of

the petitioner that the measurement book did not reflect the true

quantity of work done by the petitioner could not have been considered

by the Arbitrators. In any civil contract where measurement book is

maintained and the work done is recorded in the measurement book,

the contractor cannot lay claim for a work which is not recorded in the

measurement book unless during the continuation of work, the

contractor had protested to the authorities that a particular work done

by him was not recorded in the measurement book. It is not the case

of the petitioner that he had protested against non recording of work

done by him in the measurement book by the concerned Engineer.

Measurement book is the authentic record of the work done. No

contractor can claim for a work allegedly done which is not recorded in

the measurement book. I, therefore consider that the Learned Arbitral

OMP No. 356/2005 M/s Lal Builder v.Union of India and others Page 3 Of 4 Tribunal rightly based the award on the measurement book.

6. It is a settled law that under Section 34 of the Arbitration

and Conciliation Act, the Court does not act as an Appellate Court and

cannot re-appreciate the evidence to arrive at a conclusion different

from that of the Arbitrator. An award can be challenged under Section

34 only on one of the grounds as mentioned in Section 34 of the Act.

Petitioner in the present case has made challenge to the award on the

basis of non-appreciation of evidence and misinterpretation of contract,

challenge on such grounds cannot be considered.

7. It is also settled law that an Arbitrator is prisoner of the

contract. The Arbitrator cannot travel beyond the contract. The

tortuous liabilities or claims for mental agony etc. cannot be raised

before the Arbitrator. Only the claims which flow from the contract and

which are not tortuous liabilities can be considered by the Arbitrator.

The Arbitrator therefore rightly did not touch the claim for mental

agony.

8. I find that the present petition under Section 34 of the

Arbitration and Conciliation Act, 1996 is not maintainable and is hereby

dismissed.

May 18, 2009                                              SHIV NARAYAN DHINGRA J.
'neeraj'




OMP No. 356/2005             M/s Lal Builder v.Union of India and others   Page 4 Of 4
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter