Citation : 2009 Latest Caselaw 1994 Del
Judgement Date : 12 May, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ LPA 214/2009 & C.M. No.6790/2009
M/s Naryanan Consultancy ..... Appellant
Through: Mr. R.P. Bhatt, Sr. Advocate with
Mr. S. Udaya Kumar Sagar, Ms. Bina
Madhavan, Mr. Shwetank Sailkwal and
Ms. Reeta Chandaranna, Advocates.
versus
Indian Oil Corporation Ltd. & Ors. ..... Respondents
Through: None.
CORAM:
HON'BLE THE CHIEF JUSTICE
HON'BLE MR. JUSTICE NEERAJ KISHAN KAUL
ORDER
% 12.05.2009
1. The present appeal is preferred against the order of the
learned Single Judge dated 23.03.2009. Briefly stated, the facts of
the present case are that there were disputes between the Indian Oil
Corporation Ltd.(IOC) and the Western Railways as regards the
question of refund of excess freight charges by the Railways to the
IOC. The appellant (original petitioner in the writ petition) claims
that IOC entered into a contract with it for consultancy services to
secure settlement of such outstanding claims. The appellant as
consultant was responsible for pursuing the matter with the Railways
and getting IOC's claims settled. The appellant was entitled to
charges for the services rendered in accordance with Schedule-A to
the contract. The appellant claims to have followed up a large
number of claims and was able to successfully secure settlements of
over 14,000 claims. As per the appellant due to its effort IOC was the
beneficiary of large amounts but despite this the refunds as due to
him were not paid by IOC. It was contended that having availed of
the services and obtained refund of substantial amounts IOC cannot
refuse to honour the appellant's bills. The IOC in its turn contended
before the learned Single Judge that it had made payments to the
petitioner towards consultancy charges for amounts that it had
actually received from the Railways. Since no amount was disbursed
towards substantial part of the claims the IOC had filed claims before
the Railway Claims Tribunal for the same. It was the case of the IOC
that it did not pay consultancy charges to the appellant for the
amounts that had not been realized. It was further submitted on
behalf of the IOC that for the amounts realized after the consultancy
contract ended the appellant could not claim credit as the same were
realized through independent efforts of IOC. As per the IOC the
appellant was not entitled to any consultancy charges for the
amounts realized after the contract had ended. The Western
Railways also filed its counter affidavit in the writ petition and stated
that disputes between the IOC and itself towards refund of alleged
excess claims were sub-judice and pending before the Railway Claims
Tribunal, Ahmedabad and that the said tribunal is the most
appropriate forum to adjudicate the disputes.
2. The learned Single Judge has rightly held that the facts of the
present case disclosed that the question of what is payable to the
appellants is not admitted by the respondents. The Railways did not
admit the claims and even the IOC's case was that the Railways had
not settled its claims. However, the disputes between the IOC and
Western Railways were pending adjudication. The learned Single
Judge, thus, rightly came to the conclusion that in such
circumstances it would be imprudent and inexpedient to examine
the feasibility and soundness of the appellant's claim. Further, as
correctly held by the learned Single Judge that as regards the claim
of the IOC that the appellant was not entitled to consultancy charges
for the amounts received after the contract ended and that such
amounts were received by independent initiative of IOC were all
disputed questions of fact and they would necessarily involve
recording of evidence and consideration of arguably voluminous
documents and materials, for which Article 226 proceedings would be
inappropriate. The learned Single Judge also took note of the fact
that there was considerable delay as well in the appellant
approaching this Hon'ble Court.
3. The appellant in the writ petition has also made allegations
against the Railways and has stated that the Railways were not
justified in charging wrong freight charges from the IOC and that the
Railways were illegally holding on to the amounts that it was required
to refund/disburse to the IOC. Accordingly, relief was also sought
against the Railway to notify the correct charge of freight and a
direction to the Railways to make payments of 14.7 crores with
interest to the IOC. We fail to see as to how the appellant could claim
these reliefs in the present petition against the Railways with whom it
had no privity of contract if there was arbitrariness in the actions of
the Railways it was for the IOC to take necessary action in
accordance with the law. In any case the disputes between the IOC
and the Railways are pending before the Railway Claims Tribunal.
The appellant can not pursue the matter on behalf of the IOC
against the Railways by way of the present writ petition out of which
the appeal arises.
4. For the reasons stated hereinabove, the present appeal must
fail. The appeal is accordingly dismissed. Pending application also
stands disposed of.
CHIEF JUSTICE
NEERAJ KISHAN KAUL, J.
MAY 12, 2009 RS
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!