Friday, 24, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sineximco Pte. Ltd. vs M.M.T.C. Limited
2009 Latest Caselaw 1978 Del

Citation : 2009 Latest Caselaw 1978 Del
Judgement Date : 12 May, 2009

Delhi High Court
Sineximco Pte. Ltd. vs M.M.T.C. Limited on 12 May, 2009
Author: Valmiki J. Mehta
      *     IN THE HIGH COURT OF DELHI AT NEW DELHI

+                           FAO(OS) 525/2006

                                      Reserved on : April 30, 2009
                                      Pronounced on : May 12, 2009

      SINEXIMCO PTE. LTD.                                ..... Appellant
                    Through:          Mr. A.K. Singla, Sr. Advocate with Mr.
                                      Pankaj Gupta, Advocate.
                   versus


      M.M.T.C. LIMITED                   ..... Respondent
                     Through:         Mr. J.P. Sengh, Sr. Advocate with Ms.
                                      Padma Priya, Mr. Sumit Gehlot, Ms. Garima
                                      Kapoor, Mr. Sumit Batra, Advocates.
      CORAM:
      HON'BLE MR. JUSTICE MUKUL MUDGAL
      HON'BLE MR. JUSTICE VALMIKI J. MEHTA


1.    Whether the Reporters of local papers may be allowed
      to see the judgment?                                          yes
2.    To be referred to the Reporter or not?                        yes
3.    Whether the judgment should be reported in the Digest?        yes


%                           JUDGMENT

VALMIKI J. MEHTA, J

1. This appeal has been filed challenging the judgment dated 3.7.2006 of the

learned Single Judge passed in OMP No.204/2002, which OMP was the

FAO(OS) 525/2006 Page 1 objections/petition filed by the respondent herein to the award dated 8.3.2002 of

the arbitrators. By allowing the objections, the learned Single Judge has allowed

the respondent to forfeit, on account of losses caused to it by breach of two

contracts by the appellant in failing to lift/purchase the material being Friable

Chrome ore, an amount of USD 3,75,000 out of the total advance of USD 5,47,470

(total 15% value of each of the two contracts) lying with the respondent as

advances received under the two contracts. The arbitrators by the award had only

allowed forfeiture of 3% out of the 15% advance received, on the ground that the

respondent had failed to prove the loss suffered, but the learned Single Judge has

held that respondent has proved that it suffered loss of USD 3,75,000.

2. The facts of the case are that the appellant as the buyer and the respondent as

the seller entered into two contracts dated 5.9.1995 for the supply of Friable

Chrome Ore of 5000 tonnes each of two particular grades. The first grade was

50/48% at USD 205 per metric tonne and 46/44% grade at USD 155 per metric

tonne. The materials under the contracts were to be lifted by the appellant by

November-December 2005. After various extensions which were granted to the

appellant, finally the last date for lifting of the material by the appellant was fixed

as 31.5.1996 and by which date the appellant failed to lift the material. The

appellant had also to open a Letter of Credit (hereafter "L.C.") in favour of the

respondent by 6.5.1996.

FAO(OS) 525/2006 Page 2

3. On account of the breaches of the appellant, including inter-alia the breach

of non-opening of the L.C. by the appellant till 6.5.1996, the respondent, more

particularly considering the repeated extensions already granted, terminated the

contract vide its fax dated 12.6.1996 and forfeited the advance of USD 5,47,470.

By the fax dated 12.6.1996 the respondents rejected the request fax dated

30.5.1996 of the appellant for accepting the contract to have come to an end on

account of force majeure. Arbitration was initiated by the appellant seeking refund

of its advances of USD 5,47,470 and to which the respondent filed its counter-

claim claiming an amount of USD 3,75,000 for the losses suffered by the

respondent.

4. Before the Arbitrators on the pleading of the parties, which included the

counter claim of the respondent, the following points for determination were

framed:-

A. "Whether the force majeure conditions prescribed by Art. 17 of the contract agreement in question are not attracted in the present case, so as to relieve Claimant of its obligations and responsibility under the contract?

B. Whether action of respondent in refusing to adjust advance under Contract Nos. 37 and 39 has been arbitrary, discriminatory and against the spirit and substance of commercial transaction between the parties?

FAO(OS) 525/2006 Page 3 C. Whether Claimant can be alleged to be in breach of its obligation by not lifting the consignment under the subject contract, in the facts and circumstances of the case?

D. In the event of answer to Issues A to C being against the Claimant and in favour of the Respondent, whether the Respondent's action of claiming forfeiture of entire amount of advance paid by Claimant against the above contract is legal, valid and justified on facts and in law?

E. Subject to the decision on above questions, what part of deposit/advance can be retained by the Respondent as a reasonable compensation in view of statutorily recognized principles laid down in Section 74 of the contract Act?

F. To what amounts and the amount of interest thereon is the Respondent liable to reimburse to the Claimant by way of adjustment against future supplies or otherwise?

G. Liability of the respondent as to costs of litigation?"

5. The Arbitrators answered points A to C in favour of the respondent herein

and held that the appellant was guilty of breach of contract. The Arbitrators noted

that the prices of the contracted material, being Friable Chrome Ore had fallen

drastically over a period of time and consequently that was found to be the main

reason for non-lifting of the contracted material by the appellant. The Arbitrators

found the appellant guilty of breach of contract in not opening the L.C. by the

stipulated date. However, on the points D & E as to whether the respondent was

entitled to forfeit the advance payment lying with it, and if so, to what extent, the

Arbitrators held the respondent was only entitled to retain 3% out of the 15% of the

FAO(OS) 525/2006 Page 4 advance moneys. This was done because the Arbitrators arrived at the finding that

the respondent had failed to prove its loss, but, having found that certain

administrative expenditure would have been incurred by the respondent, the

Arbitrators awarded 3% out of the 15% of the advance money lying with the

respondent. The arbitrators held that the respondent had failed to prove its losses

because according to the arbitrators: the respondent had a back to back contract

with its supplier the Orissa Mining Corporation (hereinafter OMC); that the

respondent only used to receive 15% commission on sales from OMC; that

respondent had failed to prove that OMC claimed losses from the respondent; that

respondent failed to prove that the material sold to M/s Glencor was not the

material which was mined for the appellant, and that the respondent's pleading did

not show that any loss was caused to the respondent. It is relevant to note that the

respondent had filed and proved before the Arbitrators its contract with M/s.

Glencor International A.G.Baar, Switzerland dated 14.5.1996 (hereinafter M/s

Glencor) and in its counter claim had given a chart showing the difference in the

prices under the subject contract with the appellant (higher prices) and the contract

with M/s. Glencor (lower prices) and had thereafter on account of the losses caused

to it/respondent, made a counter claim of USD 3,75,000.

FAO(OS) 525/2006 Page 5

6. As already stated above the respondent being aggrieved by the award of the

Arbitrators in disentitling them to the amount of counter claim of USD 3,75,000

and restricting the forfeiture amount to only 3% of the 15%, filed its objections to

the award as OMP 204/02 before the learned Single Judge, which have been

decided by the impugned judgment of the learned Single Judge allowing the

respondent to retain USD 3,75,000.

7. In setting aside the award the learned Single Judge has primarily relied on

firstly, the fact that the Arbitrators have ignored the only and relevant material

piece of evidence being the contract of the respondent with M/s. Glencor dated

14.5.1996 which contract was reasonably proximate to the date of breach/date of

lifting of the material by the appellant being 6.5.1996 and 31.5.1996 respectively

and secondly, the material pleadings being the counter claim of the respondent

herein did in fact make averments of the loss suffered. The learned Single Judge

held that the Arbitrators ignored the material document/evidence and pleadings on

irrelevant grounds such as the contract of the respondent with M/s. Glencor was

not for the material mined for the subject contract, and was for a larger contract

which included one additional type of Friable Chrome Ore (though it did include

also the grades of Friable Chrome Ore, the contracted material) and that no loss

was caused to respondent on account of the grounds detailed in para 5 above. The

FAO(OS) 525/2006 Page 6 learned single judge also held that no doubt it is settled law that a Court which

hears an objection to an award has limited jurisdiction while hearing a challenge to

the same, but, if the Arbitrators ignored a material document (K.P. Poulose vs.

State of Kerala and Anr., (1975) 2 SCC 236) or rely on the legal proposition

which legally erroneous (Oil and Natural Gas Corporation Ltd. vs. Saw Pipes

Ltd., 2003 (5) SCC 705) the Court can definitely set aside the award of the

Arbitrator.

8. The issue which arises for determination in the present appeal are:

(i) Whether this Court sitting as an appellate court should

interfere with the findings of the learned Single Judge, when the

learned Single Judge by giving detailed reasons has upset the

findings of the Arbitrators by holding that the Arbitrator ignored the

material piece of evidence and the relevant pleadings of the

respondent?

(ii) Whether even if independently the award has to be looked at,

is not the same liable to be set aside?

9. Before us the counsel for the appellant has urged the same issues as urged

before the arbitrators that the respondent has not suffered any loss inasmuch as it

FAO(OS) 525/2006 Page 7 has not paid compensation to OMC for loss suffered by OMC or commission of

15% to Orissa Mining Corporation as the respondent had a back to back contract

with OMC and the witnesses of the respondent have failed to prove the loss and

also the fact that the respondent in spite of an application to file the documents

with respect to its loss suffered qua OMC failed to file the same. The counsel for

the appellant further contended that it was not as if the Arbitrators have ignored a

material piece of evidence because reference is found to the contract with M/s.

Glencor in the award and consequently it cannot be said that Arbitrators have mis-

conducted themselves by ignoring material document/evidence. The counsel for

the appellant has placed reliance upon the Saw Pipes case (supra) to contend that

the learned Single Judge ought not to have interfered with the findings arrived at

by the Arbitrators. The learned counsel for the appellant also referred to the

written statement of the respondent before the Arbitrators, and more particularly its

paragraph 24 at internal pages 8 and 9, as also the statement of the witnesses (Mr.

C. Govindan Kutty and Mr. Samar Das) to support his arguments. The learned

counsel for the appellant further elaborated that the respondent was only a

commission agent and it was bound to prove that OMC had recovered from the

respondent the amount which the respondent is claiming from the appellant.

FAO(OS) 525/2006 Page 8

10. We would like to deal first with the second issue stated in para 8 whether the

award can be sustained as per the arguments raised by the appellant and whether

the Arbitrators were justified in looking at the contract of the respondent with a

third party M/s. Orissa Mining Corporation in order to arrive at a decision as to

whether the respondent had suffered a loss or was it not enough for the respondent

to have relied upon its contract with M/s. Glencor to show that the prices of the

subject materials were much lower than the contracted prices on or around the

breach of the contract/performance of the contract.

We clearly feel that the arbitrators have in the award relied upon legal

propositions which are wholly unsustainable and which did in fact call for setting

aside of the award, and which the single judge rightly did.

10(i) Admittedly the respondent was a trader and did not source goods from

OMC for its own consumption. The goods were sourced from OMC to sell ahead

to purchasers such as the appellant. We think there was clearly a legal

misconception of the arbitrators with regard to the losses to be caused to the

respondent. The issue with regard to the requirement of losses in the facts of this

case was actually the loss of profits to the respondent, and not losses in the sense of

actual loss of moneys which were caused to it by moneys going out of its pocket.

The issue of losses on account of moneys going out of its pocket would have only

FAO(OS) 525/2006 Page 9 arisen if the respondent was not a trader but a consumer of goods, which

admittedly is not the position in the present case. The contracts are only between

the appellant as buyer and respondent as seller. It is a bilateral contract between

the appellant and respondent and not a tripartite contract to which OMC is a party.

It is wrong and indeed strange for the appellant to contend that respondent is only a

commission agent when the contract between the appellant and respondent does

not refer to the respondent as so and nor are the clauses as if the respondent is a

commission agent. On account of the appellant buyer refusing to purchase due to

fall in the prices, the respondent suffers a loss in the sense that, if the contract had

been performed at the contracted higher rates then respondent would have got

higher profits as the contracted material was available at much lower rates on the

date of performance/breach, i.e., the loss is loss of higher profit margin. Also, the

respondent had a long term supply contract with OMC for a year and which is for

more than the quantity which was to be purchased by the appellant as stated by the

witness C.Govindan Kutty. Thus, it was not required that only that ore which was

to be specifically sourced to appellant could only have been the specific material

which was necessary to be sold to Glencor before the respondent could maintain its

counter-claim.

FAO(OS) 525/2006                                                          Page 10
 10(ii)         In fact in law causing of actual loss by necessarily going through a

new contract at lower price with third party like Glencor is also not required as per

the law under Section 73 of the Contract Act. The proposition of law which the

arbitrators have wrongly relied upon is that actual loss must be caused and it is not

enough to show only fall in the prices to claim damages on account of breach of

contract. As per Section 73 of the Contract Act, 1872 once there is breach of

contract it is not necessary for the aggrieved party in order to claim damages to

first incur an actual loss or actual loss of profits before the aggrieved party can

successfully institute a claim for damages.

10(iii) We would at this stage seek to refer to a judgment of the Division

Bench of this Court in M/s Saraya Distillery, Sardarbaggar vs. Union of India,

AIR 1984 Delhi 360 which holds that actual carrying out of the contract and actual

incurring of losses is not a sine qua non to claim damages from the guilty party.

The following paragraphs of the said judgment are relevant which are

reproduced below:

"7. Learned counsel for the contractor contended that before a party could claim damages he must go to the market, purchase the goods not supplied or short supplied and suffer actual loss. Only

FAO(OS) 525/2006 Page 11 then, argued the learned counsel, he would be entitled to damages. We do not agree.

9. What the buyer is deprived of in the usual course of things by non-delivery is the value of the goods at the time and place of the delivery, less price payable by him under the contract. This loss of value is the only natural result of the breach, the only kind of damage that ensues in the usual course of things. The quantum of damages on account of the breach of such contract would be the difference between the contract price and the market price of the goods in question at the time when the contract is broken. The provisions contained in S.73 do not envisage that the buyer must resort to actual purchase and suffer loss before claiming damages. It was so held in Ismail Sait & Sons. v. Wilson & Co., AIR 1919 Mad 1053. Similar view was taken in Vishwanath v. Amarlal AIR 1957 Madh Bha 190.

10. The Supreme Court in the case of M/s. Murlidhar Chiranjilal v. M/s. Harish-chandra Dwarkadas AIR 1962 SC 366 observed at page 369:

"The two principles on which damages in such cases are calculated are well settled. The first is that, as far as possible, he who has proved a breach of a bargain to supply what he contracted to get is to be placed, as far as money can do it, in as good a situation as if the contract had been performed; but this principle is qualified by a second, which imposes on a plaintiff the duty of taking all reasonable steps to mitigate the loss consequent on the breach, and debars him from claiming any part of the damage which is due to his neglect to take such steps : (British Westinghouse Electric and Manufacturing Co. Ltd. V. Underground Electric Rly. Co. of London (1912 AC 673 at p. 689). These two principles also follow from the law as laid down in S.73 read with the Explanation thereof. If, therefore, the contract was to be performed at Kanpur it was the respondent's duty to buy the goods in Kanpur and rail them to Calcutta on the date of the breach and if it suffered any damage thereby because of the rise in price on the date of the breach as compared to the contract price, it would be entitled to be reimbursed for the loss. Even if the respondent did not actually buy them in the market at Kanpur on the date of breach FAO(OS) 525/2006 Page 12 it would be entitled to damages on proof of the rate for similar canvas prevalent in Kanpur on the date of breach, if that rate was above the contracted rate resulting in loss to it. But the respondent did not make any attempt to prove the rate for similar canvas prevalent in Kanpur on the date of breach. Therefore, it would obviously be not entitled to any damages at all, for on this state of the evidence it could not be said that any damage naturally arose in the usual course of things."

(emphasis supplied) Learned counsel for the Contractor relied on a judgment of a learned single Judge of this court in Union of India v. Tribhuwan Dass, Lalji Patel, AIR 1971 Delhi 120. In this case it was observed that the Government can recover the loss only sustained by it and could not claim damages, if no loss was sustained. With respect we do not agree with this view. This is contrary to the observations made by the Supreme Court in M/s. Murlidhar Chiranjilal (supra). A Division Bench of this court in All India Institute of Medical Sciences v. American Refrigeration Co. Ltd. AIR 1982 Delhi 275 came to the conclusion that the case Union of India v. Tribhuwan Dass (supra) was wrongly decided. We hereby overrule the decision in Union of India v. Tribhuwan Dass."

11. It is, therefore, clear that the only relevant evidence which was to be looked

into in order to arrive at the loss caused to the respondent on account of admitted

breach of contract by the appellant was not as to whether it suffered loss in its

contract with M/s. Orissa Mining Corporation from which it had sourced the

goods, but, whether there was fall in the market prices from those stated in the

contract to those as found at the time of the performance/breach of the contract.

The learned Single Judge has therefore rightly relied upon the contract of the

respondent with M/s. Glencor and on the basis of the following chart (given by the

FAO(OS) 525/2006 Page 13 respondent in its counter claim and also reproduced in the judgment of the learned

Single Judge) and held that the respondent had suffered a loss of USD 3,75,000:

      "                        50/48% grade                 46/44% grade

   a) Contract price

      with the claimant        205 PMT                         155 PMT



   b) Price at which

      the cargo was sold       150 PMT                         135 PMT



   c) Difference                55 PMT                         20 PMT



   d) Amount of loss
      Suffered for 5,000 MT     2,75,000                       1,00,000


   e) Total                       USD                          3,75,000



   f) Interest @ 20% from
       May 31,95 to
      October 31,1997          USD                             1,65,000

                                      Grand Total USD          5,40,000"




FAO(OS) 525/2006                                                     Page 14

12(i) The learned Single Judge in our opinion rightly held that the material piece

of evidence being the contract with the respondent with M/s. Glencor had not been

adverted to by the Arbitrators inasmuch as mere reference to the document without

reference to the relevant portion of the document is as good as ignoring the

document/evidence inasmuch as the material portion of the same is not adverted to.

It is undisputed that the material portion of the document showing the difference in

the prices in the contract under the contract with M/s. Glencor and the subject

contract has not been adverted to by the Arbitrators. The Arbitrators had simply

referred to the contract of the respondent with M/s. Glencor for the reasons which

are wholly irrelevant reasons. The contract with M/s Glencor is dated 14.5.1996

and which is very much proximate to the dates of breaches/performances of the

appellant under the contract. The contract with M/s Glencor is for three qualities,

two of which are those of the subject matter of the contracts.

12 (ii) We may note that the respondent had relied before the Arbitrators on

the judgment of the Supreme Court reiterated as Dwarka Das vs. State of M.P. &

Anr., (1999)3 SCC 500. The said judgment is an authority for the proposition that

some amount of estimation is always required in proof of damages and once there

is material available which has nexus to the estimation of damages, then, it cannot

be said that losses and damages should not be awarded. The Supreme Court

FAO(OS) 525/2006 Page 15 referred to its earlier judgments in the cases of M/s. A.T. Brij Paul Singh & Ors.

vs. State of Gujarat, (1984) 4 SCC 59 and Mohd. Salamatullah vs. Govt. of A.P.,

(1977) 3 SCC 590 to hold that evidence which is not of the same place but of a

nearby place/vicinity can be used to determine the award of damages. Also it was

held that in many cases there would be some amount of honest guesswork in

quantification of damages and there was nothing illegal about the same. The spirit

of the judgments and the law is that a party who is guilty of breach of contract is

bound to compensate the person who is aggrieved and exaction in the proof of

damages is an utopia which is not the object of law. The arbitrators acted on a

wrong proposition of law in holding the judgment as not applicable on the

reasoning that the judgment was under Section 73 of the Contract Act, 1872 and

not under Section 74 of the said Act. Once damages have to be proved under

Section 74 as the contract is such that damages have to be proved, then, the

principle for determination of loss on damages has necessarily to be on the

principles laid down under Section 73. Therefore, once we have in the facts of the

present case the contract of the respondent with Ms/ Glencor which is around the

same period as that of the breach/performance of the contract, the same is a

relevant piece of evidence on the basis of which damages can be awarded. The

Arbitrators were, therefore, wholly unjustified in ignoring this binding precedent of

FAO(OS) 525/2006 Page 16 the Supreme Court once the contract of M/s. Glencor was filed and proved before

it.

13. The contention of the learned counsel for the appellant is that paragraph 24

of the written statement of the respondent shows that it suffered no loss, ignores

the facts that the counter claim has been filed as a separate pleading than the

written statement filed by the respondent, and therefore, both the written statement

and the separate counter claim had to be read together. On reading so, it is clear

that the respondent had made averments with respect to loss suffered on account of

the lesser prices of the material sold to M/s. Glencor as compared to the prices

under the subject contract. No doubt, the pleadings seems to be inartistically

drafted with reference to the para 24 of the written statement, but, since there was a

counter claim simultaneously filed by the respondent before the Arbitrators, one

would have to then see both the written statement and counter claim together and

on so doing it cannot be said that there is no pleading with respect to the losses

suffered by the respondent inasmuch as the counter claim specifically mentions of

the contract of the respondent with M/s. Glencor and in fact in paragraph 5 of the

counter claim there is set out the chart showing the loss caused and as reproduced

in para 13 above.

FAO(OS) 525/2006 Page 17

14. As regards the other contentions of the learned counsel for the appellant that

the witnesses have admitted that no loss has been caused inasmuch as they do not

have documents to prove the same and the respondent failed to file its

correspondence and accounts with Orissa Mining Corporation, we feel that such

documents are irrelevant in view of the respondent having already filed its contract

with M/s. Glencor which as per the deposition of the witness the respondent had in

fact performed and the witness has further also stated that he does not immediately

have the details of the performance of the contract with M/s. Glencor since he has

not brought the original record. The statement of witnesses have to be read as a

whole and one part of it has to be read with the other parts. One part of a statement

cannot be torn out of context from the whole statement. The so called admission in

one part has to be necessarily read in the context of the entire deposition. When

the statements of the witnesses are contrary to the documents which are on record

as proved or admitted, then it is permissible to rely instead on the oral testimony to

the documents on record. Also merely because there is a back to back contract

does not lead to presumption that rates/prices in it will fall along with fall in the

prices in the market and which the arbitrators have presumed by the existence of a

back to back contract.

FAO(OS) 525/2006 Page 18

15. As regards the first issue stated in para 9 above which in this appeal we have

been called to consider, in view of our decision in the second issue already given

above, it is clear that there was only one view the Arbitrators could have taken in

terms of the law as applicable and the facts which were found before them, but the

Arbitrators wrongly choose to ignore the same and consequently the learned Single

Judge was right in upsetting the award. In appeal, therefore, we would not like to

take a different view once the learned Single Judge has clearly found that the

learned Arbitrator has wrongly ignored the material piece of evidence and the

learned Single Judge has further given valid reasons for holding that the contract

with M/s. Glencor being proximate in time with respect to the date of

breach/performance of the appellant, the Arbitrators were bound to consider the

same and not ignore the same on irrelevant considerations. Sitting as an appellate

court, therefore, we would not like to interfere with such valid reasons as recorded

by the learned Single Judge and in fact to which we agree and which is also the

position in law as held by a Division Bench judgment of this Court in M/s. Saraya

Distillery, Sardarbaggar's case (supra).

16. We, therefore, find no merit in the appeal and the same is dismissed. In view

of the fact that the appellant is found to have backed out of a contract upon

discovering that the market rates of the contracted item had fallen we feel that the

FAO(OS) 525/2006 Page 19 appellant must pay costs of Rs. 30,000/- to the respondent not later than four weeks

from today failing which interest at 9% per annum shall be payable on the said

costs.


                                                       VALMIKI J. MEHTA, J



                                                       MUKUL MUDGAL, J
MAY 12, 2009
dkg




FAO(OS) 525/2006                                                       Page 20
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter