Friday, 24, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Globe Construction Co. vs Union Of India
2009 Latest Caselaw 1975 Del

Citation : 2009 Latest Caselaw 1975 Del
Judgement Date : 11 May, 2009

Delhi High Court
M/S Globe Construction Co. vs Union Of India on 11 May, 2009
Author: Shiv Narayan Dhingra
             * IN THE HIGH COURT OF DELHI AT NEW DELHI

                                                                  Date of Reserve: 24.3.2009
                                                                 Date of Order: 11th May 2009

OMP No. 50/2009
%
     M/s Globe Construction Co.                 ... Petitioner
                    Through: Mr. G.D.Chopra, Advocate

                  Versus

        Union of India                                       ... Respondent
                                Through: Mr. Vineet Malhotra, Advocate with
                                Mr. Sanjay Kumar, Advocate

JUSTICE SHIV NARAYAN DHINGRA

1.      Whether reporters of local papers may be allowed to see the
        judgment?

2.      To be referred to the reporter or not?

3.      Whether judgment should be reported in Digest?



JUDGMENT

1. By this petition under Section 34 of the Arbitration & Conciliation

Act, 1996, the petitioner has raised objections against the award dated

21.10.2008 of the learned Arbitrator.

2. Brief facts relevant for the purpose of deciding this petition are that

the petitioner had executed civil work for the respondent and thereafter raised a

dispute about non-payment of certain claims. This dispute was referred to the

Arbitrator and learned Arbitrator after considering the pleadings and evidence of

both the parties passed the award. The claim raised by the petitioner and the

amount awarded by the learned Arbitrator are as under:

Claim                                                       Amount Claimed          Amount Awarded



Claim No.1 - In respect of amount withheld in Rs.24,000/-                           Rs.24,000/-

final bill



Claim No.2 - Amount wrongly recovered at Rs.2,43,000/-                              Rs.2,42,979/-

penal rate recovery



Claim No.3 - Lesser rate paid for agreement Rs.39,250/-                             Rs.39,246/-

items.



Claim        No.4   -   Recovery     on    account     of Rs.33,040/-               Nil

overweight Torsteel



Claim No.5 - Seeking refund of amount Rs.3,47,293                                   Rs.1,59,528/-

recovered on account of rebates by the claimant

Claim No.6 - For refund of amount recovered Rs.82,500/- Rs.41,493/-

under garb of RIS/MEI/DIS

Claim No.7 - Work done but not paid Rs.3,60,000/- Rs.74,756/-

Claim No.8 - Interest for delay in payment Rs.4,72,052/- Rs.3,19,323/-

Claim No.9 - Balance payment under Clause Rs.6,50,000/- Rs.4,34,116/-

10CC

Claim No.10 - Damage and Loss of Profit Rs.21,00,000/- Rs.2,00,000/-

Claim No.11 - Interest                                  @      18%       w.e.f @10%               of

                                                        1.12.1995               awarded amount

                                                                                w.e.f. 1.1.2004




3. Apart from allowing claims of the claimant to the above tune, the

learned Arbitrator also awarded amount of Rs. 30,000/- to the petitioner towards

cost of arbitration. Thus, the total sum awarded to the petitioner was

Rs.12,46,118/-

4. The claimant/petitioner has assailed the award against each of the

claims except claim no.4. The various grounds as stated by the claimant in its

challenge are on the merits of each claim. It is settled law that while considering

challenge to the award under Section 34 of the Arbitration & Conciliation Act,

1996, this Court does not act as a Court of appeal against the order of the

learned Arbitrator. The Arbitrator is the final judge chosen by the parties in

respect of facts and law. The Arbitrator in this case is a retired Additional

Director General of CPWD, who was well versed with the civil engineering works

and he has given reasons for allowing the claims either partly or in full. In

respect of claim no.7 he has given table specifying the measurements of different

items which were claimed by the petitioner not having been paid and he has

taken into account the amount paid and the amount as claimed by the petitioner,

the rates and what was required to be paid further. Against each of the claims,

the learned Arbitrator has considered all material which was placed by the

petitioner and the respondent and given reasons why the particular amount was

being allowed.

5. In view of the award being a speaking and reasoned award and

given by an expert of its field, I consider that the award does not warrant any

interference on the grounds as stated by the petitioner for challenging the award.

The grounds taken by the petitioner for challenging the award do not fall within

the purview of Section 34. I find no reason to entertain this petition. The petition

is hereby dismissed having no force.

May 11, 2009                                   SHIV NARAYAN DHINGRA, J.
vn





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter