Citation : 2009 Latest Caselaw 1925 Del
Judgement Date : 8 May, 2009
* HIGH COURT OF DELHI : NEW DELHI
OMP No.115/2007
% Judgment reserved on : 16th April, 2009
Judgment pronounced on : 8th May, 2009
Delhi Development Authority ..... Petitioner
Through : Mr. D.S. Mahendru, Adv. with
Ms. Alpana Pandey, Adv.
versus
M/s. Amita Nand Aggarwal Associates .... Respondent
Through : Mr. Vivekanand, Adv.
Coram:
HON'BLE MR. JUSTICE MANMOHAN SINGH
1. Whether the Reporters of local papers may
be allowed to see the judgment? Yes
2. To be referred to Reporter or not? Yes
3. Whether the judgment should be reported Yes
in the Digest?
MANMOHAN SINGH, J.
1. This petition has been filed by the petitioner under Section
34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to
as the 'Act') challenging the Award dated 16th October, 2006.
2. The undisputed facts between the parties are that the tenders
for the subject work were submitted on 21.12.1989 and the work was
awarded to the respondent by the petitioner vide letter dated 16.03.1990
with the awarded value of the work of Rs.85,79,315/-, which was
64.64% gross without deduction of rebates for timely payments and
64.34% net above after adjustment of rebates on the estimated cost of
Rs.52,20,467/-. The estimated cost was based on Delhi Schedule of
Rates, 1985. The stipulated period of completion was six months to be
reckoned after 10th day from the date of acceptance of the tender as per
award letter. Thus, the stipulated date of start of the work was
26.03.1990. Undisputedly, the work was not completed within the
stipulated period of six months upto 25.09.1990 and work prolonged
beyond about six months upto 30.06.1993 for further period of about 33
months. The recorded date of completion is 30.06.1993.
3. The extension of time without levy of compensation under
Clause 2 was granted by the respondent to the petitioner upto actual date
of completion. In between, in 1994 part security deposit was released by
the petitioner and labour escalation payment only as per statutory Govt.
notifications on the work done upto 30.06.1993 was also paid to the
claimant.
4. However, final bill on measurement books of the petitioner,
as prepared and proposed by the petitioner was accepted and signed
under protest by the respondent on 03.12.1996 and 09.12.1996 before
receiving the cheque. After signing the measurements and bill under
protest on 03.12.1996, the respondent vide letter dated 04.12.1996
informed the petitioner about the balance payments not included in the
final bill of the petitioner. The respondent again vide letter dated
18.12.1996 requested the petitioner to make the balance payment within
30 days.
5. The respondent vide letter dated 05.02.1997 invoked
arbitration clause 25. Ultimately, the petitioner having failed to appoint
Arbitrator within time despite requests, respondent no.2, was appointed
by this Court vide order dated 09.08.2002 in OMP No. 228/1998.
6. The learned Arbitrator made and published the award after
affording full opportunities to the parties to file pleadings, documents,
to lead evidences, to file written submissions and make oral submissions
and ultimately made and published the award on 16.10.2006.
7. The learned Arbitrator awarded a sum of Rs.29,31,068/- in
favour of the respondent with interest @12% on all the claims except
Claim no.2 on which a specified amount has been awarded from
09.12.1996 i.e. the date of payment of final bill to the date of award. It
has been further directed that if the petitioner pays the awarded amount
with interest as aforesaid within three months from the date of the
award, there will be no interest from the date of the award till payment
and if no payment is made within three months as aforesaid, the awarded
amount of Rs.29,31,068/- will carry further interest @ 12% p.a. from the
date of the award till the date of actual payment. The learned Arbitrator
also directed the petitioner to pay Rs.1,00,000/- on account of cost of
the arbitration proceedings.
8. On account of part payment, a sum of Rs.2,35,912/- vide
cheque dated 16.01.2007 was received on 20.01.2007 with letter dated
16.01.2007, without any details or facts and figures by the Petitioner. As
per respondents, after adjusting the amount of part payment, the balance
amount as on 16.01.2007 is Rs.60,87,125/-which the petitioner is to pay
with interest @12% from 16.01.2007 till the date of the payment and
which was clarified to the petitioner by the respondents vide letter dated
20.01.2007. The said fact, according to respondent remained unrebutted
from the act of the petitioner.
9. The petitioner challenged the award in respect of claim No.1
(e), (f), (l), 7, 8, 10 to 13. The payment in respect of the rest of the
claim as mentioned above has been made by the petitioner within the
stipulated time.
10. The petitioner contended that the award published by the
Ld. Arbitrator is clearly based on surmises and conjectures and is
against the public policy of India.
11. Regarding Claim No.1(e), it is urged that the Ld. Arbitrator
grossly erred in allowing the sum of Rs.1,20,000/- in favour of the
respondent towards shifting of existing cables. It is submitted that the
removal of electricity cables etc. could only be done by the respective
department of the Govt., the petitioner has no responsibility under the
agreement to execute this work. The learned counsel for the petitioner
relied upon Exhibit R-41 and R-34 to contend that the cables were
never shifted by the respondents but were merely pushed away.
Therefore, the findings of the Ld. Arbitrator is contrary to the evidence
on record and is not sustainable in law.
12. Similarly regarding claim No.1(f), it is urged that the Ld.
Arbitrator grossly erred in awarding the sum of Rs.20,000/- in favour of
the respondent for shifting, relaying and rectification of damaged PVC
pipes (125 mm outer diameter) water line belonging to MCD. The
subject matter of the claim is the policy matter of the government as the
same involves the network of essential services which cannot be
hampered unless or until some alternate arrangement is made.
13. It is further submitted that the learned arbitrator wrongly
awarded a sum of Rs.11,940.22/- towards straightening and cutting of
steel under Claim No. 1(e) without appreciating that item No. 13 of the
agreement includes all operations including the work of straightening
and cutting of steel bars which are received in bundles. The objection
under claim No.1 raised by the petitioner is given up during the course
of hearing.
14. As regards Claim No.7 and 8, it is submitted that the Ld.
Arbitrator grossly erred in awarding a sum of Rs.20,00,000/- under
claim No. 7 and Rs. 5 lacs in claim no. 8 while dealing with both the
claims together. The list of delays recorded by the Arbitrator is only a
hype created by the arbitrator as these are normal delays and having
regard to the work involved in the case, whenever extension of time was
sought by the petitioner, the same was allowed without levy of
compensation by the respondent in view of the understanding between
the parties. It is alleged that the ld. Arbitrator has grossly erred in
holding that for assessing the damage, the provision under clause 10 CC
will not apply and he will have to assess the damages under the
provisions of section 73 of Indian Contract Act. In cases where the
stipulated date of completion of work is more than six months, the 10
CC formula is applicable. The Arbitrator wrongly applied the Hudson
formula to calculate the loss of overheads by holding that the same is
widely recognized and applied in Construction Industry. Hudson
formula is not prescribed in the agreement between the parties and thus
cannot be applied.
15. On account of watch and ward expenses in claim No.10, the
Arbitrator has wrongly awarded a sum of Rs.30,000/- for 36 months
and 18 days. It should have been 33 months and not 36 months as
claimed by the respondents from 30.6.1993 to 18.3.1996.
16. As regards claim no. 11, it is submitted that the Ld.
Arbitrator grossly erred in awarding the sum of Rs.7800/- on account of
expenses incurred in transporting including loading and unloading of
balance quantity of the steel. He relied upon clause 42 of the agreement
in this regard.
17. As regards claim no. 12 and 13, it is submitted that the Ld.
Arbitrator wrongly awarded interest @12% w.e.f. 9.12.96 i.e. from date
of award till the date of payment except on claim no. 2 where the
interest has been given for specified periods. The award of interest is on
a very higher side. The Ld. Arbitrator also grossly erred in awarding
a sum of Rs. 1 lac as cost to the respondent as the Arbitrator himself
made the observation that both the parties were at fault at one or the
other time and it could not be said that only the petitioner was
responsible for the gross delay in the execution of the work, therefore,
by awarding the cost in favour of the respondent, the arbitrator seems to
have awarded the respondent for its inactions and mismanagement.
18. The learned counsel for the respondent vehemently argued
that none of the objections filed by the petitioner are maintainable and
sustainable within the provisions of the Section 34 (2) of the Act. All
the objections are beyond the ambit and scope of the provisions of
Section 34 of the Act. The Award is not in any manner in violation of
or against public policy of India nor there is any such objection taken by
the petitioner.
19. The Arbitrator has made and published award after
considering entire record and submissions before him and have given
detailed reasons for his award in respect of the claims challenged by the
petitioner. The Arbitrator is not supposed to give detailed reasons and
write judgment like that of the Court. The reasons and finding of the
Arbitrator in respect of the claims challenged by the petitioner is as per
record available before the Arbitrator and in view of the contract,
documents and evidence/ record available before him. The view taken
by the Arbitrator is a plausible view if not the only possible view and
the findings of the arbitrator based on record and interpretation of
contract/ documents is a finding of fact and cannot be disturbed even if
the Court by a process of reasoning come to a different view, because
the Court is not sitting in appeal over the award of the arbitrator.
20. He relied upon various case laws to contend that where
after taking into consideration the arbitration agreement, statements
filed by the parties and documents produced, the arbitrator proceeds to
give his award in writing as to all disputes referred to him, the Court
will assume that the Arbitrator has considered and disposed of every
claim made or defence raised.
21. It is further contended that reasonableness of reasons cannot
be challenged and appraisement of evidence by the Arbitrator is never a
matter which the court questions and considers.
22. Interpretation of contract is a matter for the Arbitrator to
determine, even if it gives rise to determination of a question of law.
Further as per provisions of Section 19 (4) of the Act, the appreciation
of evidence and documents is within the sole jurisdiction and power of
the Arbitrator.
23. The claimant herein respondent had made in all 13 claims
before the arbitrator. Claim no. 1 for works done but not paid consisted
of about 17 sub claims from (a) to (q). Out of 13 claims, the learned
arbitrator has allowed partly only claims 1(e), (f), (g), (k), (l), claim no.
2 for interest on delayed payment of final bill and security, claim no. 4
release of withheld amount of final bill, claim no. 5 refund of penal rate
recovery of stipulated materials, claim no. 7 damages by way of
increased rates on the work done beyond stipulated period, claim no. 9
staff and overheads expenses for the prolonged period by way of losses,
claim no. 10 watch and ward expenses of departmental materials from
30.6.1993 and 18.6.1990, claim no. 11 cartage of balance departmental
materials at places other than departmental stores from where materials
were issued, claim no. 12 interest @ 12% p.a. from 9.12.1996 on all
awarded claims, except claim no. 2 till payment, claim no. 13 Rs. 1 lakh
towards the fees of arbitrator.
24. Countering the argument of the learned counsel of the
petitioner in clause 1 (e), it is submitted by the learned counsel for the
respondent that the shifting of underground services was not contractual
obligation of the respondent and was not within the scope of the work of
the respondent. The petitioner instead of shifting the cable itself or
getting it done by DDA electrical department or through DESU asked
the respondent to shift the cable by shifting. The execution of this extra
item and additional expenses incurred were intimated by the respondent
to the petitioner from time to time during the course of execution of the
work. The letters R-34 and R-41 were clear instructions/authority to the
respondent to shift cables. The appreciation of evidence and
construction of the document was within the jurisdiction of the
arbitrator and after considering the document/evidence taken by the
arbitrator, his view is final and binding.
25. Similarly, the arbitrator on claim No.1 (f) considered the
evidence on record and the statement made by Sh. S.C. Jain, SE DJB
and noted his observations and is, therefore, final.
26. With regard to claim no. 1(l), the arbitrator made reference
to the relevant DSR 1985 and DSR 1993 rates. The view/interpretation
of the arbitrator is neither an impossible nor perverse but a plausible
view and cannot be set aside even if erroneous. The learned counsel for
the petitioner has given up his objection pertaining to the said claim
during the course of his submission.
27. The arbitrator also considered and gave his categorical
finding on claims No. 7 & 8 on account of increased rates i.e. Rs.20 lac
in claim No.7 and Rs. 5 lakhs in claim no. 8. The finding of delay on
behalf of the petitioner being a finding of fact based on record/evidence
is final and binding. Further the plea of the petitioner with reference to
clause 10C or clause 10CC have been dealt by the ld. Arbitrator. The
Ld. Arbitrator has also considered and appreciated the provision of
clause 1 of general conditions and specifications as alleged and referred
to by the petitioner during arguments though not pleaded in reply to
these claims.
28. With regard to claim no. 10 the learned Arbitrator rightly
awarded Rs.30,000/- towards watch and ward expenses of departmental
materials from the date of completion on 30.06.1993 till it was taken
over by the petitioner i.e. from 30.06.1993 to 18.06.1996 which works
out to 36 months and not 33 months as alleged in objection petition. The
claim no. 8 was for the period beyond stipulated period of completion
till actual date of completion i.e. 26.09.1990 to 30.06.1993 whereas the
claim under claim No. 10 was for the period after completion of the
work beyond 30.06.1993 till the date of taking over departmental
materials i.e. 18.06.1996.
29. In respect of claim no. 11 the learned Arbitrator while
awarding Rs.7,800/- on account of expenses incurred in transporting
materials on loading/unloading, stacking and hire charges of the truck,
the arbitrator has considered and appreciated and interpreted clause 42
and not ignored it as alleged by the petitioner.
30. Regarding the rate of interest awarded in claim No.12, it is
stated that the amounts were due since 1993-1994 when the bank rate of
interest on loans was minimum 18% compounded quarterly, the ld.
Arbitrator has allowed only 12% simple interest and that too after about
two and half years form due date i.e. completion of work in 30.06.1993.
31. With regard to award of costs of proceedings under claim no.
13 at Rs. 1 lakh, it is urged that the claimant/respondent has paid
arbitrator fee and incurred other expenses of about more than Rs. 2
lakhs. However, the arbitrator has allowed only Rs. 1 lakh which does
not cover even the 50% of the fee paid by the claimant/respondent. The
ld. Arbitrator is empowered and authorised to apportion and award the
cost under Section 31 (8) of Act.
32. It is well settled that the jurisdiction of the court when called
upon to decide the objection raised by a party against an arbitral award
is limited as expressly indicated in the Arbitration and Conciliation Act,
1996. The court has no jurisdiction to sit in appeal and examine the
correctness of the award on merits with reference to the materials
produced before the arbitrator. It cannot sit in appeal over views of the
arbitrator by re-examining and re-assessing the materials. (See Puri
Construction (P) Ltd. vs. Union of India (1989) 1 SCC 411)
33. In the case of Food Corp. of India Vs. Arosan Enterprises
Ltd. ILR (1996) 1 Del. 185, it is laid down that the approach of the
court has to support the award if it is reasonably possible, rather than to
declare it illegal. It is not permissible to reappraise the evidence or to
go into the questions of quality and quantity of evidence. If two views
are possible, the court even if inclined to take a view different from that
taken by the arbitrators is not entitled to substitute its view over that of
the arbitrators. But at the same time, it being an award which sets out
reasons, though it is not permissible to go into the reasonableness of the
reasons yet this court can set aside the award on finding errors apparent
on the face of the award or if there is an error of law on the face of the
award.
34. The Apex Court in the case of D. D. Sharma vs. Union of
India, 2004 (5) SCC 325 held that the jurisdiction of the Court to set
aside an award is well settled. An arbitrator being a judge chosen by the
parties, his decision would ordinarily be final unless one or the other
condition contained in Section 30 of the Arbitration Act, 1940 is
satisfied for the purpose of setting aside his award. Interpretation of a
contract is a matter for the arbitrator to determine, even if it gives rise to
determination of a question of law. It is also trite that correspondences
exchanges by the parties are required to be taken into consideration for
the purpose of construction of a contract. Once it is held that the
construction of an agreement fell for consideration of the arbitrator, the
determination thereupon shall not ordinarily be interfered with. The
court's jurisdiction in this behalf is merely to see whether the arbitrator
has exceeded his jurisdiction or not.
35. In BOC India Ltd. vs. Bhagwati Oxygen Ltd., 2007 (9)
SCC 503, the arbitrator refused to set aside the award of the arbitrator
and held that when the arbitrator had considered all the aspects of the
matter including the terms of the contract and all the materials on
record and the statement of claim and has come to a conclusion of fact,
it cannot but be held that the award was not based upon a proposition of
law which is unsound or an error of law must have appeared from the
award itself or from any document or note incorporated in the award or
appended to it. When the arbitrator had taken a plausible view on
interpretation of contract, it is not open to the court to set aside the
award on the ground that the arbitrator had misconducted himself in
the proceedings.
36. Recently in the case of Sethi Engineering Corp. vs. Delhi
Development Authority, 158 (2009) DLT 19 similar question arose
before this Court and the damages on account of prolongation of work
beyond stipulated date of completion was awarded by the arbitrator and
the observations were made in this regard by the Arbitrator. This court
refused to interfere with the findings given by the arbitrator.
37. In the impugned award, the learned Arbitrator with regard to
claim No.1(e) has referred to the letters dated 25.4.1990 and 2.2.1993,
he has also referred other documents namely the letter R-34 dated
21.12.1991 and another letter R-41 dated 7.10.1992 and held that the
claim, was justified and allowed the same to the extent of Rs
1,20,000/-. In claim No.1(f) also, the learned Arbitrator after
considering the evidence of Mr. S.C. Jain and interpreting that the work
was beyond the scope of the agreement awarded the amount of
Rs.20,000/- in favour of the respondent. In claim No.1(l) after perusing
Item No.13 in the agreement, the learned arbitrator allowed the claim of
Rs.11,940.22.
38. On account of escalation/increased rate of material for the
work done beyond stipulated period in claim No.7 and on account of
overheads, establishment and staff expenses beyond stipulated period
because of prolongation of the work in claim No.8, the learned
Arbitrator gave detailed finding after interpreting clause 10 C and
clause 10CC of the agreement, several letters, price indices and DSR
on 1985, 1991, 1993.
39. As regards claim No.10 and claim No.11 also, the learned
arbitrator gave his detailed reasoning and awarded the amount of
Rs.30,000/- and Rs.7,800/- respectively.
40. Claim No.12 and 13 pertains to the interest @ 12% p.a. and
cost of Rs.1 lac towards arbitration proceeding which in my view, is in
the discretion of the arbitrator and I find no reason to modify these
claims.
41. I have perused the award carefully and have also gone
through the pleadings of both the parties. the learned Arbitrator has
considered all the documents relied upon by both the parties and
evidence on record. The learned Arbitrator has also interpreted the
terms of the contracts. In view of well settled law and my above
discussion, I find no ground to interfere with the impugned award. The
petition being devoid of merits, is hereby, dismissed. No costs.
MANMOHAN SINGH, J MAY 08, 2009 SD
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!