Citation : 2009 Latest Caselaw 1861 Del
Judgement Date : 5 May, 2009
* HIGH COURT OF DELHI : NEW DELHI
+ O.M.P. No. 25/2002
% Judgment reserved on : 17th February, 2009
Judgment pronounced on : 5th May, 2009
Swadeshi Cables (I) Ltd. ....Petitioner
Through : Mr. Pramod B. Agarwala with Ms. Praveena
Gautam, Mr. Manmohan Sharma and Mr.
Abhishek Baid, Advs.
Versus
National Aluminium Co. of India Ltd. ....Respondents
Through : Mr. V.P. Singh with Mr. Anuj Berry, Advs.
CORAM:
HON'BLE MR. JUSTICE MANMOHAN SINGH
1. Whether the Reporters of local papers may
be allowed to see the judgment? Yes
2. To be referred to Reporter or not? Yes
3. Whether the judgment should be reported Yes
in the Digest?
MANMOHAN SINGH, J.
1. This petition has been filed by the petitioner for setting aside
the award dated 1st October, 2001 whereby the learned Arbitrator
awarded an amount of US$ 12698 with interest at 6% per annum from
4th September, 1998 till payment to the respondent. The respondent was
also awarded cost at US$ 1000.
2. The petitioner, Swadeshi Cables Industries (in short SCI) is a
company incorporated in Nepal. The respondent, NALCO is a Public
Sector Enterprise. NALCO released the sale order to buy aluminium
wire rod of about 300 MT at a fixed price of US $ 2070 per MT with a
delivery schedule from July to December 1995, dated 17th June, 1995 to
SCI containing all terms, conditions of sale, delivery, price etc. and the
arbitration clause.
3. SCI issued the necessary bank guarantees, three Letters of
Credit and lifted 142.057 M.T. of goods and the deliveries were
scheduled to be made in the month of July, August and September, 1995
to the respondent. However, by letter dated 13th September, 1995 SCI
informed NALCO that due to political disturbances in Nepal, the
deliveries scheduled for October, November and December could not be
lifted and to postpone them to January, February and March, 1996.
NALCO refused to reschedule the deliveries.
4. It is alleged by SCI that NALCO did not inform them that the
manufactured goods were lying ready with it for delivery in January,
February and March, 1996 or that they could lift them in the above said
months on payment of delayed charges or damages. There were price
fluctuations during the months from November to March and the price
of aluminium was continuously falling. NALCO did not offer to deliver
the goods during January to March, 1996. By letter dated 4th May,
1996, NALCO requested SCI to lift the goods in May to July, 1996 but
SCI refused to accept the demands to take the deliveries in May to July,
1996. It is averred that neither party cancelled the contract till March,
1996.
5. Thereafter, NALCO filed an Arbitration Petition against the
SCI before the learned Arbitrator which was decided in his favour
holding that SCI committed the breach of the agreement by refusing to
accept the supply for the months of October to December, 1995.
6. The petitioner has raised objections to the impugned award
mainly contending that the award is contrary to Section 28 of the
Arbitration and Conciliation At, 1996 (hereinafter referred to as 'the
Act'). The award is contrary to the evidence on record as it was the case
of NALCO that it had already planned, produced and kept ready for
delivery the said contracted goods and that they were available for
delivery even on 4th May, 1996. The Arbitrator has ignored the letter
dated 4th May, 1996 which expressly states that the contract was not
ended till December, 1995. The damages occurred not naturally in the
usual course of things but it was caused due to political disturbances in
Nepal which was going on that time.
7. It is submitted in the petition in para 24 that the copy of
award was given to the petitioner on 12 th October, 2001 and they have
filed the objection petition within 90 days of the said service of the
award. The petition was filed on 15th January, 2002.
8. The respondent refuting the allegations of the petitioner, has
submitted that under Section 34 of the Act, the petition is not
maintainable as the scope of interference is very restricted in objection
petition. He relied upon Section 5 of the Act to emphasize that under
the Act of 1996, minimal judicial intervention of the Court is provided.
Learned counsel for the respondent has relied upon the case of
Olympus Superstructures Pvt. Ltd. V. Meena Vijay Khetan, AIR
1999 SC 2102 at para 17 and has argued that the scope of Section 34 of
the Act to set aside the award is far less than under Section 30 and 33 of
the Arbitration Act, 1940.
9. He has also argued that the Court should not reappraise the
evidence intrinsically or embark on a close scrutiny of the same for
arriving at the conclusion that the findings given by the learned
Arbitrator are erroneous. It is only where the error of law or finding of
fact, if any, is patent or is easily demonstrable without the necessity of
carefully weighing the various possible views for it, that the Courts can
interfere with the award. The award made by an Arbitrator is conclusive
as a judgment between the parties and the Court would be set aside only
when Arbitrator has misconducted himself or the award has been made
contrary to the provisions of the Contract.
10. The respondent also relied upon the case of Indu
Engineering and Textiles Ltd. v. DDA (2001) 5 SCC 691, para 6 & 7,
wherein it is held that Courts endeavour should be to preserve the award
as far as possible and a close scrutiny of the findings of the Arbitrator is
not possible. The Hon'ble Supreme Court in this case has further held
that even in the case of misconstruction or misappreciation of the
material on record, if any, the award may not be interfered with, even if
this Court may have come to different conclusion.
11. It is submitted by the learned counsel for the respondent that
as a measure of goodwill, NALCO despite having suffered losses gave
an opportunity to SCI to mitigate their losses by lifting the goods at a
later date by letter dated 4th May, 1996 which SCI refused but it cannot
be pleaded as a waiver or abandonment by NALCO. The learned
counsel relied upon the case of Mangal Sen vs. Kanchid Mal 1981 (4)
SCC 117 to contend that issue of plea of waiver cannot be allowed to be
raised when not pleaded.
12. It is also argued that under Section 34(3) of the Act,
limitation period of three months is prescribed for filing the objection
application from the date the party received the award. The petitioner
was admittedly served a copy of the award on 12 th October, 2001,
however, the objections to the award were filed on 15th January, 2002.
In the objection petition, the petitioner submitted that the petition has
been filed within 90 days of the service of the award. No application for
extension of time of 30 days as prescribed under Section 34 has been
filed, hence the court has no power to condone the delay even for a
single day without any application having the ground of sufficient
cause/reasons and thus the petition is liable to be dismissed.
13. In the rejoinder filed by the petitioner, it is stated that three
months of filing the petition expired only on 15th January, 2002, 12th
January, 2002 being second Saturday and 13 th January, 2002 being
Sunday, the court was closed. 14th January, 2002 being Makar Sankranti
was also declared a local holiday and the court was closed.
Consequently, the petition could be filed only on 15 th January, 2002.
The same is, therefore, within time. It is further submitted in the
rejoinder that without prejudice to the aforesaid, even if there is a delay
of a few days as alleged, in the said event this Court has
ample power to condone the delay. In the present case, the petitioner is
located at Kathmandu - Nepal. It takes time to communicate and to
receive papers. Even though the affidavit was affirmed as early as on
29th December, 2001, it took time for papers to reach to Delhi for filing
in court. Consequently, the delay, if any, was due to unforeseen reason
being postal delays, for papers and documents to reach Delhi from
Kathmandu. It is submitted that the postal delay being beyond the
control of the petitioner, the same be considered as sufficient cause for
delay, if any, in filing the captioned petition.
14. The learned Arbitrator has considered the contentions and
pleadings on record of both the parties including the letter of respondent
dated 4th May, 1996 and the letter of the petitioner dated 13 th September,
1995. The learned Arbitrator after considering detailed arguments and
evidence held that the petitioner was guilty of breaching the contract by
failing to lift the goods from the respondent.
15. The petitioner relied upon various decision in support of his
submission but facts and circumstances in each case are different. None
of the decisions is applicable to the facts of the present case.
16. The Apex Court in the case of Oil & Natural Gas Corpn.
Ltd. v. Saw Pipes Ltd.,(2003) 5 SCC 705 clearly laid down the scope of
interference by the court in the award of the arbitrator under Section 34
of the Act. The relevant para is reproduced as under :
"Conclusions
74. In the result, it is held that:
(A) (1) The court can set aside the arbitral award under Section 34(2) of the Act if the party making the application furnishes proof that:
(i) a party was under some incapacity, or
(ii) the arbitration agreement is not valid under the law to which the parties have subjected it or, failing any indication thereon, under the law for the time being in force; or
(iii) the party making the application was not given proper notice of the appointment of an arbitrator or of the arbitral proceedings or was otherwise unable to present his case; or
(iv) the arbitral award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration.
(2) The court may set aside the award:
(i)(a) if the composition of the Arbitral Tribunal was not in accordance with the agreement of the parties,
(b) failing such agreement, the composition of the Arbitral Tribunal was not in accordance with Part I of the Act.
(ii) if the arbitral procedure was not in accordance with:
(a) the agreement of the parties, or
(b) failing such agreement, the arbitral procedure was not in accordance with Part I of the Act.
However, exception for setting aside the award on the ground of composition of Arbitral Tribunal or illegality of arbitral procedure is that the agreement should not be in conflict with the provisions of Part I of the Act from which parties cannot derogate.
(c) If the award passed by the Arbitral Tribunal is in contravention of the provisions of the Act or any other substantive law governing the parties or is against the terms of the contract.
(3) The award could be set aside if it is against the public policy of India, that is to say, if it is contrary to:
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality; or
(d) if it is patently illegal.
(4) It could be challenged:
(a) as provided under Section 13(5); and
(b) Section 16(6) of the Act."
17. The learned arbitrator considered the documents on record
and objections and arguments raised by both the parties. The learned
arbitrator in fact has framed an issue regarding the effect of writing
letter dated 4th May, 1996 and gave his findings in that regard. The plea
of the petitioner that the arbitrator ignored this letter is clearly
untenable. I find no ground to interfere with the findings and reasoning
given by the arbitrator on repudiation of contract by the petitioner.
18. With regard to the contention raised by the respondent that
the petition is not maintainable under Section 34 (3) as not filed within
time, considering overall circumstances of the matter, I will not go into
the question of delay as the petitioner has failed to make any case on the
basis of which the Award of the Arbitrator can be set aside.
19. I find no merit in the objections, the same are dismissed. No
costs.
MANMOHAN SINGH, J MAY 05, 2009 SD
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!