Citation : 2009 Latest Caselaw 849 Del
Judgement Date : 17 March, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ A.A. 389/2006
%17.03.2009 Date of decision: 17th March, 2009
SUSHIL KUMAR BHARDWAJ .......Petitioner
Through: Mr V.K. Sharma, Advocate.
Versus
UNION OF INDIA .......Respondent
Through: Mr Sushil Dutt Salwan.
And
A.A. 522/2006
M/S BINDRA ASSOCIATES .......Petitioner
Through: Ms Anusuya Salwan, Advocate
Versus
MUNICIPAL CORPORATION OF DELHI ....Respondent
Through: Ms Smita Shankar, Advocate.
And
A.A. 523/2006 & 524/2006
M/S R & T ENTERPRISES .......Petitioner
Through: Ms Anusuya Salwan, Advocate
Versus
MUNICIPAL CORPORATION OF DELHI .....Respondent
Through: Ms Smita Shankar, Advocate.
A.A. 153/08,421/08,523/06,524/06,389/06,522/06,323/08 Page 1 of 16
And
A.A. 153/2008
SHRI RAM CHANDER DAGAR .......Petitioner
Through: Ms Anusuya Salwan, Advocate
Versus
MUNICIPAL CORPORATIN OF DELHI ....... Respondent
Through: Ms Smita Shankar, Advocate.
And
A.A. 323/2008
M/S RAJORA BUILDERS .......Petitioner
Through: Mr. N.K. Kantawala, Advocate
Versus
D.S.I.D.C. ....... Respondent
Through: none.
And
A.A. 421/2008
ENGINEERING DEVELOPMENT CORP. ....Petitioner
Through: Ms Anusuya Salwan, Advocate
Versus
MUNICIPAL CORPORATION OF DELHI ....Respondent
Through: Ms Smita Shankar, Advocate.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may Yes
be allowed to see the judgment?
2. To be referred to the reporter or not? Yes
3. Whether the judgment should be reported
in the Digest? Yes
A.A. 153/08,421/08,523/06,524/06,389/06,522/06,323/08 Page 2 of 16
RAJIV SAHAI ENDLAW, J.
1. Common question as to interpretation of clause 25 in General
Conditions of contracts of MCD and Government of NCT of Delhi is
involved in all these cases. Vide order dated 29th August, 2008, the
divergence of opinion on the interpretation of the said clause was
noticed and all the matters ordered to be taken up for hearing
together.
2. The said clause 25 is as under:
"clause 25.
Except where otherwise provided in the contract, all questions and disputes relating to the meaning of the specifications, design, drawings and instructions here-in- before mentioned and as to the quality of workmanship or materials used on the work or as to any other question, claim, right, matter or thing whatsoever in any way arising out of or relating to the contract, designs, drawings, specifications, estimates, instructions, orders or these conditions or otherwise concerning the works or the execution or failure to execute the same whether arising during the progress of the work or after the cancellation, termination, completion or abandonment thereof shall be dealt with as mentioned hereinafter:
i) If the contractor considers any work demanded of him to be outside the requirements of the contract, or disputes any drawings, record or decision given in writing by the Engineer-in-Charge on any matter in connection with or arising out of the contract of carrying out of the work, to be unacceptable, he shall promptly within 15 days request the Superintending Engineer in writing for written instruction or decision. Thereupon, the Superintending Engineer shall give his written instructions or decision within a period of one month from the receipt of the contractor's letter.
If the Superintending Engineer fails to give his instructions or decision in writing within the aforesaid period or if the contractor is dissatisfied with the instructions or decision of the Superintending Engineer, the contractor may, within 15 days of the receipt of Superintending Engineer's decision, appeal to the Chief Engineer who shall afford an opportunity to the contractor to be heard, if the latter so desires, and to offer evidence
in support of his appeal. The Chief Engineer shall give his decision within 30 days of receipt of contractor's appeal. If the contractor is dissatisfied with this decision, the contractor shall within a period of 30 days from receipt of the decision, give notice to the Chief Engineer for appointment of arbitrator failing which the said decision shall be final binding and conclusive and not referable to adjudication by the arbitrator.
ii) Except where the decision has become final, binding and conclusive in terms of sub para (i) above disputes or difference shall be referred for adjudication through arbitration by a sole arbitrator appointed by the Chief Engineer, CPWD, in charge of the work of if there be no Chief Engineer, the administrative head of the said CPWD. If the arbitrator so appointed is unable or unwilling to act or resigns his appointment or vacates his office due to any reason whatsoever, another sole arbitrator shall be appointed in the manner aforesaid. Such person shall be entitled to proceed with the reference from the stage at which it was left by his predecessor.
It is a term of this contract that the party invoking arbitration shall give a list of disputes with amounts claimed in respect of each such dispute alongwith the notice for appointment of arbitrator and giving reference to the rejection by the Chief Engineer of the appeal.
It is also a terms of this contract that no person other than a person appointed by such Chief Engineer CPWD or the administrative head of the CPWD as aforesaid should act as arbitrator and if for any reason that is not possible, the matter shall not be referred to arbitration at all.
It is also a term of this contract that if the contractor does not make any demand for appointment of arbitrator in respect of any claims in writing as aforesaid within 120 days of receiving the intimation from the Engineer-in- charge that the final bill is ready for payment, the claim of the contractor shall be deemed to have been waived and absolutely barred and the Government shall be discharged and released of all liabilities under the contract in respect of these claims.
The arbitration shall be conducted in accordance with the provisions of the Arbitration and Conciliation Act, 1996 (26 of 1996) or any statutory modifications or re- enactment thereof and the rules made thereunder and for the time being in force shall apply to the arbitration proceeding under this clause.
It is also a term of this contract that the arbitrator shall adjudicate on only such disputes as are referred to him by the appointing authority and give separate award against each dispute and claim referred to him and in all cases where the total amount of the claims by any party exceeds Rs. 1,00,000/- the arbitrator shall give reasons for the award.
It is also a term of the contract that if any fees are payable to the arbitrator, these shall be paid equally by both the parties.
It is also a term of the contract that the arbitrator shall be deemed to have entered on the reference on the date he issues notice to both the parties calling them to submit their statement of claims and counter statement of claims. The venue of the arbitration shall be such place as may be fixed by the arbitrator in his sole discretion. The fees if any, of the arbitrator shall, if required to be paid before the award is made and published, be paid half and half by each of the parties. The cost of the reference and of the award (including the fees, if any, of the arbitrator) shall be in the discretion of the arbitrator who may direct to any by whom and in what manner, such costs or any part thereof shall be paid and fix or settle the amount of costs to be so paid."
In the MCD cases, the clause is identical save that authority for
appointing the Arbitrator is the Commissioner, MCD.
3. The common questions which arise for adjudication are as
under:
A. Whether the procedure prescribed in sub clause (i) of clause 25 is applicable to all disputes or to only the matters of the contractor being required to do any work considered by him to be outside the contract or where the contractor disputes any drawing, record or decision given in writing only.
B. Whether the procedure prescribed in sub clause (i) is mandatory or directory.
C. Whether the designate of the Chief Justice under Section 11(6) of the Arbitration Act, 1996 is empowered to appoint an arbitrator if the procedure prescribed in sub-clause (i) is not followed.
Re: Question A
4. The divergence of opinion noted above is with respect to this
question. While a Single Judge of this Court in Concrete India Vs
MCD Arbitration Application No.130/2005 decided on 29th
September, 2005 held that clause 25(i) is so widely worded as to
include all claims of the contractor in relation to any matter in
connection or arisen out of a contract of carrying out the work, in a
subsequently decided Gursaran Vs MCD 2006 IV AD (Delhi) 35,
another Single Judge whose attention had not been invited to
Concrete India (supra) expressed a view that the disputes
pertaining to actual working of the contract did not fall within the
scope of clause 25(i) and thus the procedure prescribed therein was
not required to be followed and the clause applicable was clause
25(ii) which dealt with any other issues not covered by clause 25(i);
it was further held that in the case of disputes falling under clause
25(ii), only a demand for appointment of an arbitrator to the
Commissioner of MCD (in that case concerning MCD) was required
to be made and upon the failure of the Commissioner to appoint the
arbitrator Section 11(6) could be invoked.
5. At the outset, I may notice that Sub-clauses (i) and (ii) are not
intended to apply to different contingencies or different kinds of
disputes. Sub-clause (ii) is in continuation of sub-clause (i). Clause
25 refers to all kinds of disputes which may arise between the
parties. Thereafter sub-clause (i) is not so widely worded as clause
25. That appears to have led to it being held in Gursaran (supra)
that sub-clause (i) applies to only some out of the various disputes
mentioned in clause 25. However, sub-clause (i) though using fewer
words while describing disputes, in comparison to clause 25, takes
within its sweep all kinds of disputes and I am unable to fathom as to
which disputes can be said to be not covered by sub-clause (i). The
words "the contractor....... disputes any....... record or decision
given in writing by Engineer-in-charge on any matter in connection
with or arising out of the contract of carrying out the work to be
unacceptable......." in sub-clause (i) are very wide, enough to cover
all kinds of disputes, described more expressly in clause 25. Of
course, there may be disputes/claims on which there may be no
decision in writing of the Engineer-in-charge. For adjudication of
such disputes, is the contractor to immediately by passing the
Engineer-in-charge, Superintending Engineer and Chief Engineer,
demand appointment of arbitrator. In my view, No. The purport
/idea/ meaning appears to be that if there are any claims/disputes,
they should first be raised before the Engineer-in-charge and he is
required to give a decision thereon in writing. Though the contract
does not so provide expressly, but in the absence of any decision in
writing of Engineer-in-charge and upon his failure to give a decision
in writing inspite of demand, the contractor is still to follow up with
superintending engineer and so on. If the contractor is not satisfied
with the said decision in writing, he is to within 15 days request the
Superintending Engineer to take a decision in the matter. The
Superintending Engineer is required under the contract to give his
decision within the period of one month from the receipt of the
contractor's letter. Upon the failure of the Superintending Engineer
to give the decision within the time aforesaid or if the contractor is
dissatisfied with the decision of the Superintending Engineer, the
contractor is required to within 15 days thereof appeal to the chief
engineer who is again required to give his decision within 30 days.
Only upon being dissatisfied with the decision of the chief engineer
and / or upon the failure of the chief engineer to give a decision
within the stipulated time, is a contractor entitled to apply to the
chief engineer for appointment of arbitrator. The contract further
provides that upon the failure of the contractor to so apply for
appointment of the arbitrator within the time of 30 days, the
decision, if any, of the chief engineer shall become binding and
conclusive on the contractor.
6. Not only is the language wide enough as aforesaid to cover all
disputes, I also do not find any rationale in providing the aforesaid
procedure for only some and not all disputes. The parties, in the
making of contract, while interpreting the same, are expected to
have been guided by reason, rather than having acted irrationally.
Yet another reason for me to hold so, is that if procedure prescribed
in sub-clause (i) is held to apply to some only and not all disputes, it
will add another tier of conflict between the parties, leading to
further delays in disposal of applications under Section 11(6) of the
Act.
7. The aforesaid procedure has been prescribed so that before
the parties resort to lengthy/costly arbitration, there is ample
opportunity to the MCD to, if finds any merit in the claims of the
contractor, to settle the same. The parties are perfectly within their
right to provide for such a procedure. A public body as the MCD, in
the discharge of its functions is dependent upon its officials and
since such bodies are the largest employers for such works, and the
value whereof may vary to a large extent, the intent seems to be that
even if the engineer-in-charge or the superintending engineer for
any reason whatsoever out of any differences with the contractor,
have not acted reasonably, there is full opportunity at all levels for
amicable settlement of the claims. The clause is also intended to
prevent a contractor from without inviting the attention of the
engineer-in-charge and/or superintending engineer approaching the
chief engineer who may otherwise not be in know of all the facts, to
appoint the arbitrator. Once the aforesaid procedure has been
followed, the Chief Engineer, before appointing the arbitrator would
have the reasons of the engineer-in-charge and the superintending
engineer before him and would also be entitled to, if he still finds
merit in the claims of the contractor, to settle the same without
resorting to arbitration.
8. Sub clause (ii) does not use the word "other disputes" so as to
apply the same to any dispute other than that defined in sub clause
(i). In fact sub clause (i) ends with a notice for appointment of
arbitrator being required to be given and sub clause (ii) is in
continuation of the said procedure by providing for appointment of
arbitrator. The purpose seems to be that there should be due
application of mind by the expert body of the public body before the
contractor is compelled to take recourse to the arbitration
proceedings. Conversely, the possibility of the contractor being
satisfied by the reasoning given by successive officials and hence not
insisting on arbitration, cannot also be ruled out. Most of such
contractors have several such projects with such public bodies and
may be convinced / satisfied with the hearing of their grievance by
higher officials. I would thus respectfully agree with Concrete India
(supra), particularly when there does not appear to be much
discussion on this aspect in the latter judgment. The question No.1
is thus answered to the effect that the procedure of inviting the
decision in writing on any claim/dispute, of approaching the
superintending engineer and thereafter the chief engineer for
decision on the dispute is to be exhausted before the chief engineer
can be approached for appointment of the arbitrator.
Re: Question No. B
9. In Saraswati Construction Co. Vs East Delhi Coop. Group
Housing Society Ltd 57 (1995) DLT 343 decided under the 1940
Act and relied upon by counsel for petitioners, a view was taken that
such procedure as in clause 25 is directory and not mandatory and a
petition to the court for appointment of arbitrator cannot be defeated
for the reason of the procedure having not been exhausted. It was
held that once an arbitration clause is found, the court necessarily
has to appoint the arbitrator. But I find that there is a marked shift
in the provision qua filing of application in the court for appointment
of the arbitrator, in the 1996 Act from the 1940 Act.
10. Under Section 20 of the 1940 Act any party to an arbitration
agreement, instead of following the procedure prescribed in Chapter
II thereof i.e., of themselves appointing an arbitrator, could apply to
the court for having the arbitrator appointed by the court. Thus,
under Section 20 of the 1940 Act, the party had a choice of either
themselves appointing an arbitrator or straightway approach the
court for appointment of the arbitrator. All that the court was
required to see in a petition under section 20 was as to whether
there was an agreement of appointment of arbitrator. The court was
not required to see whether the party had attempted constitution of
arbitral tribunal themselves as per procedure prescribed in Chapter
II and/or whether the parties were unable to do so. It was in the
aforesaid state of law that it was held that the agreed procedure for
appointment was directory and not mandatory.
11. Per contra, under Section 11 of the 1996 Act, the designate of
the Chief Justice can be approached for appointment of an arbitrator
only where a party has failed to act as required under the agreed
procedure and/or where a person or an institution has failed to
perform any function entrusted to him/it under that procedure.
Thus, the parties now under the 1996 Act do not have a choice of
either, attempt appointment of the arbitral Tribunal themselves or at
least take steps therefor or approaching the court directly but are
now before approaching the court required to first exhaust the
agreed procedure or the procedure prescribed by law. Without the
same being done, there would be no cause of action for approaching
the designate of the Chief Justice. I may in this regard also refer to
the judgments relied upon by the counsel for the Government of NCT
of Delhi.
12. In The Iron & Steel Co. Ltd Vs M/s Tiwari Road Lines AIR
2007 SC 2064 it was held that in the matter of settlement of dispute
the agreement executed by the parties has to be given great
importance and an agreed procedure for appointing the arbitrator
has been placed on high pedestal and has to be given preference to
any other mode for securing appointment of an arbitrator. Similarly
in Municipal Corp, Jabalpur Vs Rajesh Construction Co. 2007
(2) Arb. L.R. 65(SC), the agreement required furnishing security
before demanding constitution of Arbitral Tribunal, the Apex Court
held that the obligation of corporation to constitute an Arbitration
Board to resolve disputes could not arise because of failure of
applicant to furnish security and the designate of the Chief Justice of
the High was held to be in error in appointing an independent
arbitrator. The Kerala High Court also in M/s Bel House
Associates Pvt. Ltd Vs General Manager Southern Railway AIR
2001, Kerala 163 and Nirman Sindia Vs M/s Indal Electromelts
Ltd AIR 1999 Kerala 440 held that where agreement stipulated
reference to arbitration to be proceeded by a decision by the
Engineer and a challenge to that decision before the adjudicator,
without resorting to those essential or preceding steps for
arbitration or waiver thereof, the agreement prohibited either party
from enforcing the arbitration clause; the application under Section
11(6) was held to be premature.
13. The counsel for the petitioners relied upon Kailash Vs
Nankhe (2005) 4 SCC 480 in paragraphs 28 to 30 whereof it has
been emphasized "procedure are the handmade of justice". Reliance
was also placed on Hindustan Petroleum Corpn Vs Pinkcity
Midway Petroleums (2003) 6 SCC 503 to urge that in cases where
there is an arbitration clause in the agreement, it is obligatory for
the court to refer parties to arbitration. However, neither of the said
judgments is on the controversy before this court. There is a definite
purpose, as aforesaid in the agreement providing for steps to be
taken before resorting to arbitration and such agreement ought not
to be interfered with specially when Section 11(6) also provides
cause of action only after such agreement has been followed.
14. There is yet another aspect of the matter. The 1940 Act deals
with arbitration only. Per contra, the 1996 Act gives legal
recognition to conciliation and the two are not repugnant to each
other. The steps preceding arbitration are to encourage conciliation
and the designate of the Chief Justice ought to encourage such
mechanism for conciliation agreed upon by the parties.
15. The second question is also thus answered to the effect that
the procedure prescribed is mandatory and not directory.
Re: Question No. C
16. Axiomatically this question has to be answered to the effect
that following the agreed procedure being mandatory, in the absence
of an averment or a pleading to the effect that the agreed procedure
or the procedure prescribed in law has been followed, there would
be no option but to reject the application under Section 11(6) of the
Act as without cause of action and/or premature.
17. In this regard I may also notice a recent judgment of the Apex
Court in P Manohar Reddy Vs Maharashtra Krishna Valley
Development Corp. MANU/SC/8480/2008 giving supremacy to
contractual terms in arbitration. Arbitration is a feature of an
agreement and in arbitration matters the agreement is supreme and
cannot be given a go-bye by the parties, especially when it is found
to be in the interest of the parties and to have been inserted with a
view to avoid unnecessary arbitrations in matters in which the
higher authorities find a possibility of settlement.
The factual data with respect to the various petitions is as under:
Re: Arbitration Application No. 389/2006
18. Though the petition does not plead compliance of the terms of
clause 25 but the annexures to the petition show that the petitioner,
vide letters dated 8th March, 2004, 16th December, 2004 and 29th
December, 2004, approached the Executive Engineer being the
engineer-in-charge. The Executive Engineer vide letter dated 3rd
January, 2005 gave his decision. The petitioner, thereafter,
approached the Chief Engineer for appointment of arbitrator.
However, there is on record a letter addressed to the Superintending
Engineer also prior thereto. The respondents in their reply have,
inter alia, taken a stand that in pursuance to the application of the
petitioner for appointment of arbitrator, the respondent vide its
letter dated 26th August, 2005 asked the petitioner to submit the
claim alongwith supporting documents. The respondent relied upon
a letter dated 20th January, 2006 of the Superintending Engineer to
the effect that all pre-conditions necessary for making request for
appointment of arbitrator had not been complied with.
Though there is no strict compliance with clause 25 in the
instant case but since the petition has been pending since August,
2006 and further since there was a dichotomy of view of this court as
aforesaid and yet further since rejection of the application at this
stage may lead to complication qua limitation, it is deemed expedient
to direct the respondent to appoint an arbitrator within one month of
this order.
With these directions, the application is disposed of.
Re : Arbitration Application No.522/2006
19. In this Petition neither any pleading nor any document to show
any compliance with the procedure prescribed in clause 25.
However, for the same reasons as in arbitration application 389/2006
in this case also the respondent / Commissioner MCD is directed to
appoint the arbitrator within one month of the date of this order.
Re : Arbitration Application No.523/2006 & 524/2006
20. In these petitions again there is neither pleading nor proof of
compliance of the procedure. The respondent / MCD has in the short
affidavit also pleaded that the petitions are time barred, the works
having been completed on 21st July, 2003, the final bill having been
prepared on 24th May, 2006.
These petitions have also been pending since 2006. For the
reasons stated in Arbitration Application No.389/2006 these
petitions are disposed of with the direction to the Commissioner
MCD to appoint the arbitration within one month. The respondent
/MCD shall be free to take the plea of limitation before the
arbitrator.
Re : Arbitration Application No.153/2008
21. In this again there is neither pleading nor proof of compliance
of the procedure prescribed in clause 25. This fact was brought to
notice of the counsel for the petitioner on 7th November, 2008.
However, no attempt was made to satisfy that procedure had been
followed. The petition is rejected as premature/without cause of
action with liberty to the petitioner to apply afresh after complying
with the procedure.
Re : Arbitration Application No.323/2008
22. In this case also there is no pleading of compliance. The
documents also do not show any compliance. Upon the same being
brought to notice of counsel for the petitioner, the petitioner filed an
additional affidavit stating that the post of Superintending Engineer
had been removed and hence the question of filing an appeal before
the Chief Engineer did not arise. Even if the post of Superintending
Engineer was not existing, though the same is not believable the
petitioner ought to have approached the officer with corresponding
authority and thereafter the chief Engineer. The petitioner having
not done so, the petition is premature and is rejected with liberty, of
course, to the petitioner to apply afresh after complying with the
procedure.
Re : Arbitration Application No.421/2008
23. In this petition also there is neither pleading nor proof of
compliance with the procedure. In the affidavit accompanying the
petition it is generally stated that the petitioner approached the
Executive Engineer, Superintending Engineer and Chief Engineer
but no reply was received. However, no particulars are given. The
documents filed with petition comprise of copies of letters written to
Executive Engineer only and not to the Superintending Engineer or
Chief Engineer. The copy of the letter written to Commissioner MCD,
also for appointment of arbitrator also merely states that office of
Superintending Engineer was visited but he did not do anything.
This letter also refers to a letter to Chief Engineer but neither are
particulars given nor copy filed. It was brought to notice of counsel
for petitioner on very first day when petition was listed that
procedure prescribed in Clause 25 does not appear to have been
followed. However, no attempt was made to satisfy that procedure
had been followed. The petition is found to be premature and without
cause of action and is rejected with liberty as aforesaid.
RAJIV SAHAI ENDLAW (JUDGE) March 17, 2009 M
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!