Thursday, 23, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Aadhar Stumbh Township Pvt. ... vs Delhi Development Authority & Ors
2009 Latest Caselaw 2876 Del

Citation : 2009 Latest Caselaw 2876 Del
Judgement Date : 28 July, 2009

Delhi High Court
M/S Aadhar Stumbh Township Pvt. ... vs Delhi Development Authority & Ors on 28 July, 2009
Author: Badar Durrez Ahmed
        THE HIGH COURT OF DELHI AT NEW DELHI
%                                      Judgment reserved on 15.07.2009
                                       Judgment delivered on: 28.07.2009

+      WP (C) 7826/2009 & CM No. 4117/2009

M/S AADHAR STUMBH TOWNSHIP PVT. LTD. ...                       Petitioner


                                   - Versus -


DELHI DEVELOPMENT AUTHORITY & ORS.                       ...   Respondents

Advocates who appeared in this case:-

For the Petitioner : Mr Vivekanand For the Respondent Nos. 1 to 3 : Mr Ajay Verma For the Respondent No. 4 : Ms Kamlesh Mahajan

CORAM:-

HON'BLE MR JUSTICE BADAR DURREZ AHMED HON'BLE MS JUSTICE VEENA BIRBAL

1. Whether Reporters of local papers may be allowed to see the judgment ? YES

2. To be referred to the Reporter or not ? YES

3. Whether the judgment should be reported in Digest ? YES

BADAR DURREZ AHMED, J

1. The grievance of the petitioner is that although its price bid was the

lowest, the tender has been awarded to the respondent No.4, whose bid,

according to the petitioner, was higher than that of the petitioner. The

central point involved in this writ petition is the determination of whether,

upon a consideration of the tender conditions, the petitioner is the lowest

bidder or the respondent No.4 is the lowest bidder.

2. Sealed tenders were invited on a turnkey basis in two parts, that is, a

technical bid and a financial bid. The work was for the construction of LIG

houses as a turnkey project at Sector-14, Dwarka, Phase-II, New Delhi.

Tenders were invited in respect of the balance work which had been left

unfinished by the previous contractor. As per the invitation for tenders, the

estimated cost of the project was Rs 12,18,15,106/- and the period of

completion was stipulated to be 20 months. The petitioner and the

respondent No.4 responded to the said Notice Inviting Tender. The

technical bids were opened on 17.11.2008. Both the petitioner and the

respondent No.4 were found to be qualified and eligible for the next stage of

consideration. The financial bids were opened on 09.01.2009. The work

was awarded to respondent No.4 by the respondent No.1 [Delhi

Development Authority (DDA)]. According to the petitioner, the said work

has been wrongly awarded to respondent No. 4 inasmuch as it was the

petitioner who was L-1 (lowest bidder) and not the respondent No.4.

3. The learned counsel for the petitioner submitted that the form of the

financial bid required a lumpsum figure to be quoted for the entire work.

The relevant portion of the form of the financial bid reads as under:-

―I/We hereby tender to the Vice-Chairman, DDA for the execution of the work specified in the tender written memorandum. We undertake to execute the work within the specified time for the total sum of Rs. _________ (Rupees____________) and we further undertake that the work shall be executed entirely and in all respects in accordance with the specifications, drawings to be approved at later stage and instructions in writing, which may be issued by the Engineer-in-

Charge from time to time for the proper and timely execution / completion of the work.‖

The learned counsel for the petitioner submitted that the figure entered by

the petitioner in the said financial bid form was Rs 22,85,11,376/-, whereas

the figure given by the respondent No.4 in the financial bid form submitted

by it, was Rs 22,86,00,000/-. Consequently, it was submitted that the

petitioner's financial bid was lower than that of the Respondent No.4 and the

work ought to have been awarded to the petitioner.

4. The learned counsel for the petitioner further submitted that the

purported reason why the respondent No.4's bid was being considered as

lower than that of the petitioner was on account of a wrong interpretation

being placed by the respondent/DDA on the Additional Tender Conditions

which form part of the tender documents. The learned counsel submitted

that Section-I of the bid documents, which gave the brief facts of the work,

contained clause 8, which clearly stipulated that the work would be awarded

on lumpsum cost basis and payment would be made at various stages of

construction as specified in the tender papers. He also drew our attention to

the additional conditions of the said tender. Clause 3 of the additional

conditions was as under:-

―3. The agency should examine the various items in Schedule ‗B' at page 158 (Annexure-―D‖) & quote the rates accordingly.‖

Our attention was also invited to clause 4.1 of the said additional conditions

which, inter alia, provided:-

―4.1 ..... This scope of work given in the NIT is only indicative and not exhaustive. The agency shall be responsible for execution of all items required for completing these houses in all respects to make these units habitable and ready for occupation as well as functioning of all services, making environment fit for habitation without any additional cost, complete as per direction of Engineer-in-Charge.‖

5. At this juncture, we may also make a reference to Schedule-B which

is referred to in clause 3 of the Additional Conditions mentioned above. The

said Schedule-B reads as under:-

SCHEDULE-―B‖ Name of work: Construction of LIG Houses on Turnkey Basis at Sector-14, Dwarka Phase-II (2.40 Hect.) (Rate to be filled in by the Agency).

S. Description of Item Qty. Unit Rate Amount No.

     1.                         2.                            3.         4.     5.             6.
  1.      Deduct for not casting RCC roofs slabs at       8 Nos.       Each
          third floor including reinforcement, centring                LIG
          and shuttering, conduits etc. complete as per                Unit
          approved drawing & design.

2. Deduct for not providing and fixing steel glazed Windows at all floors & height as per approved drawing.

                                                          2320.99      Sqm.
            a) For over all portion treated as fixed.
                                                          Sqm.

            b) Extra   for       side-hung      portion
                                                          1557.92
               (Windows)                                               Sqm.
                                                          Sqm.
  3.      Add for demolishing RCC work including          55.00 Cum.   Cum.
          stacking of steel bars and disposal of

serviceable / unserviceable material within 50 metres lead.

4. Add for dismantling doors, windows and clerestory windows (steel or wood) shutter including chowkhats, architrave, holdfasts etc. complete and stacking within 50 metres lead.

                                                          2460 Nos.    Each
              a)   Of area 3 sqm. and below
 NOTE: Col. No.5 & 6 not to be Published.


6. The learned counsel for the petitioner referred to the general

specifications and conditions. In particular, he referred to clause 4 thereof,

which stipulated that the amount quoted by the tenderer shall be deemed to

include any minor details / items of work and / or construction, which were

obviously and fairly intended and which may not have been included in the

documents, but were essential for the execution and completion of the work.

A further condition had been imposed and added in the Notice Inviting

Tender for the balance work alongwith the original conditions. The same

required the successful tenderer to inspect the site before quoting the rates.

It was also indicated that it would be the responsibility of the successful

tenderer to complete the work in continuation of the work left by the other

agency. It was specifically provided in the said additional condition that in

case any deficiency / discrepancy was observed, the same would have to be

made good within the quoted rates.

7. The sum and substance of the arguments of the learned counsel for the

petitioner was that upon a reading of the tender documents and the terms and

conditions stipulated therein, the parties were to quote a lumpsum figure and

it was that figure alone which was to be considered for the purposes of

awarding the work, nothing more, nothing less. The learned counsel

submitted that, although this was the clear intention that could be discerned

from the tender documents, the DDA computed the financial bids after

considering the figures provided by the bidders in the said Schedule ―B‖,

which was required to be filled in terms of clause 3 of the Additional Tender

Conditions mentioned above.

8. The Schedule ―B‖ submitted by the petitioner was as under:-

SCHEDULE-―B‖ Name of work: Construction of LIG Houses on Turnkey Basis at Sector-14, Dwarka Phase-II (2.40 Hect.) (Rate to be filled in by the Agency).

S. Description of Item Qty. Unit Rate Amount No.

     1.                        2.                                3.          4.                 5.               6.
  1.      Deduct for not casting RCC roofs slabs at        8 Nos.        Each         41,250/-
          third floor including reinforcement, centring                  LIG          (Rs. Forty one
          and shuttering, conduits etc. complete as per                  Unit         thousand two
          approved drawing & design.                                                  hundred fifty only)

2. Deduct for not providing and fixing steel glazed Windows at all floors & height as per approved drawing.

500/-

                                                           2320.99       Sqm.
          a)   For over all portion treated as fixed.                                 (Rs. Five hundred
                                                           Sqm.                       only)

                                                                         Sqm.         100/- (Rs. One
          b) Extra   for           side-hung    portion 1557.92
                                                                                      hundred only)
             (Windows)                                  Sqm.
  3.      Add for demolishing RCC work including           55.00         Cum.         6000/-
          stacking of steel bars and disposal of           Cum.                       (Rs. Six thousand
          serviceable / unserviceable material within                                 only)
          50 metres lead.
  4.      Add for dismantling doors, windows and

clerestory windows (steel or wood) shutter including chowkhats, architrave, holdfasts etc. complete and stacking within 50 metres 535/-

          lead.                                                                       (Rs. Five hundred
                                                           2460          Each
               a) Of area 3 sqm. and below                 Nos.                       thirty five only)

 NOTE: Col. No.5 & 6 not to be published


The Schedule ―B‖ completed and submitted by the respondent No.4 was as

under:-

SCHEDULE-―B‖ Name of work: Construction of LIG Houses on Turnkey Basis at Sector-14, Dwarka Phase-II (2.40 Hect.) (Rate to be filled in by the Agency).

S. Description of Item Qty. Unit Rate Amount No.

     1.                       2.                           3.          4.                  5.                   6.
  1.      Deduct for not casting RCC roofs slabs        8 Nos.        Each        57000/-                   Rs.4,56,000/-
          at third floor including reinforcement,                     LIG         (Rs. Fifty Seven
          centring and shuttering, conduits etc.                      Unit        Thousand only)
          complete as per approved drawing &
          design.

2. Deduct for not providing and fixing steel glazed Windows at all floors & height as per approved drawing.

                                                        2320.99       Sqm. 550/-                        Rs.12,76,544.50
               a) For over all portion treated as
                                                        Sqm.                      (Rs. Five hundred
                   fixed.                                                         Fifty only)

                                                        1557.92                   275/- (Rs. Two
               b) Extra for side-hung portion                         Sqm. hundred seventy five           Rs.4,28,428/-
                                                        Sqm.
                                                                                  only)


                  (Windows)
  3.    Add for demolishing RCC work               55.00          2000/-                 Rs.1,10,000/-
        including stacking of steel bars and       Cum.           (Rs.Two thousand
        disposal of serviceable / unserviceable                   only)
        material within 50 metres lead.
  4.    Add for dismantling doors, windows and
        clerestory windows (steel or wood)

shutter including chowkhats, architrave, holdfasts etc. complete and stacking 330/-

        within 50 metres lead.                                    (Rs. Three hundred
                                                   2460    Each                          Rs.8,11,800/-
             c) Of area 3 sqm. and below           Nos.           thirty only)

 NOTE: Col. No.5 & 6 not to be published.




9. According to the learned counsel for the petitioner, what the DDA has

done by adding and deducting the figures given in the schedule ‗B' form

submitted by the petitioner is contrary to the tender conditions, which

required a lumpsum bid amount. According to the petitioner, the figures

mentioned in Schedule ‗B' referred to above were not to be considered at all

for the purposes of determining the lowest bidder and those figures were to

be subsumed in the lumpsum price quoted by each bidder. The learned

counsel for the petitioner also placed reliance on the Supreme Court decision

in the case of West Bengal Electricity Board v. Patel Engineering Co.

Limited and Others: AIR 2001 SC 682 for the proposition that it is essential

to maintain the sanctity and integrity of the process of tender / bids and also

for the award of a contract. In the said Supreme Court decision, which, of

course, related to international competitive bidding, which is not the case

here, the Supreme Court observed that the degree of care required in such

bidding is greater than in ordinary local bids for small works. At this stage

itself, we may point out that the said Supreme Court decision would not

strictly apply to the case at hand. However, there is no shying away from

the general proposition that the sanctity and integrity of the process of

tenders / bids must be maintained. It cannot also be denied that the tender

conditions are to be followed and relaxing any condition or altering any

condition to the detriment of one or more parties is not permissible and

would impair the rule of transparency and fairness.

10. The learned counsel for the DDA submitted that the work has been

correctly awarded to the respondent No.4 inasmuch as the respondent No.4,

in view of the tender conditions, was the lowest bidder. According to the

said counsel, clause 3 of the additional conditions, referred to above, clearly

required the tenderer to examine the items in Schedule ―B‖ and to quote the

rates accordingly. Schedule ―B‖ comprised of four items. The first two

items required deductions and the next two items, namely, item Nos. 3 and 4

required additions. The bidders were to quote their rates and amounts

against each of these items. The question that clearly arises is - From what

were the deductions in respect of items 1 and 2 to be made and to what were

the amounts in items 3 and 4 to be added? It is obvious that the deductions

and the additions had to be with respect to the figures quoted by the bidders

in the lumpsum financial bids submitted by them. Thus, according to the

learned counsel for the DDA, the lumpsum figure quoted by the bidders had

to be adjusted by the figures quoted in the Schedule ―B‖ forms and it is only

after they were considered together that the lowest bidder could be found

out. In the counter-affidavit, the respondent DDA has stated that the

contract was for the balance work as left incomplete by the earlier

contractor. As part of the work already executed by the previous contractor,

there were two specific items:-

-- 8 nos. roofs / slabs already laid;

-- steel glazed doors / windows already fixed.

The scope of work in the present tender included these items also. However,

Schedule-B clarified that there could be a possibility of the roofs / slabs

being retained as also the doors / windows being retained. It was submitted

that the main schedule for the balance work under the tender included the

construction of 8 roofs / slabs and doors / window frames which had been

executed by the earlier contractor. The cost of construction of such roofs /

slabs and doors / window frames had been taken in the scope of work of the

present tender under the main schedule. Thus, based on the report of a

testing agency appointed for the purpose, the DDA was to take a decision as

to whether those items were to be retained or dismantled. If the said roofs /

slabs and doors / windows were to be retained, it is obvious that the cost of

such works quoted by the bidder would be deducted from the lumpsum rates

quoted in the main schedule / scope of work. It was further explained by the

DDA that on the other hand if the concerned items were to be dismantled,

then the cost of dismantling would have to be added to the rates quoted in

the main schedule / scope of work.

11. It is on this basis that the lowest tenderer, according to the DDA, was

to be determined after examining the lumpsum amount and the amounts

quoted in Schedule-B.

12. It was further stated in the counter-affidavit that the comparative

statement of the bids of the petitioner and the respondent No.1, after

considering the lumpsum amount quoted by each as also the amounts quoted

by them under Schedule-B, was as under:-

"STATEMENT SHOWING THE POSITION OF BIDS IN FOUR (4Nos.) OF SITUATIONS. I. IF BOTH 8 NOS. OF ROOFS / SLABS AND THE WINDOWS ETC. ARE TO BE RETAINED.

                                                M/s Aadhar Stumbh     M/s. N.D.R. Israni &
                                                Township (P) Ltd.     Co. Pvt. Ltd.
      Lump-sum Quoted rates:-Page 43 of             22,85,11,376.00     22,86,00,000.00
      tender
      Deduct for not casting 8 Nos. of roofs       (-) 16,46,287.00     (-) 21,60,972.50
      slabs & not providing windows etc.
      NET AMOUNT OF BID.                            22,68,65,089.00     22,64,39,027.50

II. IF BOTH 8 NOS. OF ROOFS / SLABS & WINDOWS ARE TO BE DISMENTALLED.

                                                M/s Aadhar Stumbh     M/s. N.D.R. Israni &
                                                Township (P) Ltd.     Co. Pvt. Ltd.
      Lump-sum Quoted rates:-Page 43 of            22,85,11,376.00        22,86,00,000.00
      tender
      Add for dismentalling 8 Nos. of slabs       (+) 16,46,100.00       (+) 9,21,800.00
      and windows etc.(Item No.3 & 4)
      NET AMOUNT OF BID.                           23,01,57,476.00       22,95,21,800.00

III. IF 8 ROOFS RETAINED & WINDOWS ARE TO BE DISMENTALLED.

                                                M/s Aadhar Stumbh     M/s. N.D.R. Israni &
                                                Township (P) Ltd.     Co. Pvt. Ltd.
      Lump-sum Quoted rates:-Page 43 of            22,85,11,376.00        22,86,00,000.00
      tender
      Add for dismentalling windows &             (+) 13,16,100.00       (+) 8,11,800.00
      doors (Item No. 4)
      Deduct for not casting RCC roofs 8            (-) 3,30,000.00       (-) 4,56,000.00
      Nos. (Item No.1)
      NET AMOUNT OF BID.                           22,94,97,476.00       22,89,55,800.00


IV. IF 8 Nos. ROOFS / SLABS GOT DISMENTALLED AND WINDOWS RETAINED.

                                                M/s Aadhar Stumbh     M/s. N.D.R. Israni &
                                                Township (P) Ltd.     Co. Pvt. Ltd.
      Lump-sum Quoted rates:-Page 43 of            22,85,11,376.00        22,86,00,000.00
      tender
      Add for dismentalling 8 Nos. of slabs        (+) 3,30,000.00       (+) 1,10,000.00
      (Item No. 3)
      Deduct for not providing & fixing steel     (-) 13,16,287.00       (-) 17,04,972.50
      glazed windows .. 2(a) & (b)
      NET AMOUNT OF BID.                           22,75,25,089.00       22,70,05,027.50





Thus, according to the learned counsel for the DDA, whichever eventuality

is considered, the respondent No.4 was the lowest bidder and, therefore, the

work has been correctly awarded to the respondent No.4 and the petitioner

cannot have any grievance whatsoever.

13. The learned counsel for the respondent No.4 supported the

contentions of the learned counsel for the DDA. In addition, he submitted

that it must be noted that the rates and amounts in Schedule-B had to be

filled in by the tenderers. If those rates and amounts were not to be

considered, then what was the need for requiring the tenderers / bidders to

quote the same? It was pointed out that the tender conditions were clear and

had been understood by each of the parties and that is the reason why,

although the respondent No.4 was the lowest bidder, the bids of both the

parties are closely matched.

14. The issue that has to be determined is whether the approach adopted

by the respondent No.1/DDA or the arguments advanced by the petitioner

with regard to who is the lowest bidder, is to be accepted. From the

arguments noted above, it is clear that both the petitioner and the respondent

No.4 cleared the hurdle of technical qualification. It is also clear that both

the petitioner and the respondent No.4 filled in their respective Schedule-B

forms and submitted the same alongwith their lumpsum financial bids.

Thus, both the petitioner and the respondent No.4 were clearly aware that

they were required to fill in and give their quotations in respect of the items

mentioned in Schedule-B. Both, the petitioner and the respondent No.4

were also aware that the work entailed the balance work left by an earlier

contractor. The roofs / slabs and doors / windows constituted part of the

scope of the work of the present tender. But, that part had already been done

by the earlier contractor. The DDA was unsure at the time when the notice

inviting tender was floated as to whether they were going to retain the said

roofs / slabs and doors / windows. That would depend upon a consideration

of the report of an expert. It is for this reason that the tenderers were

required to submit their quotations for the said items also.

15. It is also clear that the items mentioned in Schedule-B could not all

stand at the same time. This is so because items 1 and 2 of Schedule-B

would come into play only if there was a decision to retain those items,

namely, roofs/ slabs and doors / windows respectively. If these items were

not to be retained, then they would require to be demolished and it is then

that a consideration of items Nos. 3 and 4, which pertain to the cost of

demolishing / dismantling would come into the picture. It is, therefore, clear

that Item Nos. 1 and 3 were mutually exclusive and so were items 2 and 4 of

Schedule-B. That leaves us with four eventualities:-

a) Items 1 and 2;

b) Items 3 and 4;

c) Items 1 and 4; and

d) Items 2 and 3.

16. A comparative summary of the bids by the petitioner and the

respondent No.4, after taking into account these eventualities and the rates

quoted by them in Schedule-B, is as follows:-

 S.    Item                 Eventuality                Petitioner's     Respondent
 No.   No.                                              Bid (Rs.)     No.4's Bid (Rs.)
 (a)   1+2         If both the roofs / slabs and the 22,68,65,089/-   22,64,39,027.50
                   doors / windows are to be
                   retained
 (b)   3+4         If both the roofs / slabs and the 23,01,57,476/-   22,95,21,800.00
                   doors / windows are to be
                   dismantled
 (c)   1+4         If the roofs / slabs are to be 22,94,97,476/-      22,89,55,800/-
                   retained and the doors /
                   windows are to be dismantled
 (d)   2+3         If the roofs / slabs are to be 22,75,25,089/-      22,70,05,027.50
                   dismantled and the doors /
                   windows are to be retained



If we were to consider any of the eventualities, the respondent No.4's bid is

clearly lower than that of the petitioner. In other words, whatever the

eventuality, the outgo on the part of the DDA would be the least if the work

was awarded to the respondent No.4.

17. It is also clear that since the roofs / slabs and the doors / windows had

already been put in place by the earlier contractor, at least one of the

aforesaid eventualities, referred to in the preceding paragraph, would have to

be undertaken by the respondent / DDA. In other words, from the lumpsum

figure mentioned by each party, the lowest price would have to be

determined by either ‗adding or deducting' or ‗adding and deducting',

depending on the particular eventuality chosen, the rates quoted for such

eventuality in Schedule-B by each of the parties. A complication could have

arisen where there was a cross-over of rates and consequently a cross-over

of the ultimate price determined in each of the eventualities. Fortunately,

that has not happened in the present case. This is so because in every

eventuality, the respondent No.4's bid has worked out to be lower than that

of the petitioner.

18. We are, therefore, of the view that the respondent No.4 was clearly the

lowest bidder and the work has been correctly awarded to the respondent

No.4 on the basis of the tender conditions. The reference by the petitioner to

clause 4 of the General Specifications and Conditions as also to the

additional conditions with regard to inspection relates to minor details and

discrepancies and is not connected with the specific items mentioned in

Schedule-B. The end result is that no fault can be found with the award of

the work in favour of the respondent No.4. The respondent Nos. 1 to 3 can

go ahead and finalise the award of the work in favour of the respondent

No.4. The writ petition is dismissed with costs which we quantify at

Rs 20,000/-.

BADAR DURREZ AHMED, J

VEENA BIRBAL, J July 28, 2009 dutt

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter