Citation : 2009 Latest Caselaw 2467 Del
Judgement Date : 3 July, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: July 01, 2009
Date of Order: July 03, 2009
+ OMP 338/2009
% 03.07.2009
SAMHO GUNYOUNG CO. LTD. .... Petitioner
Through : Mr. Debo K. Deori, Adv.
Versus
FLAKT (INDIA) LTD. & ORS. .... Respondent
Through:
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see
the judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?
JUDGMENT
1. By this petition under Section 34 of the Arbitration
and Conciliation Act, the petitioner has assailed an award of
the Tribunal dated 15th January, 2009 whereby the Tribunal
allowed the claim of the respondent in respect of balance
amount of milestone payment to the tune of USD72,730/- and
INR39,04,510.03 and also allowed a claim of USD18,045/- and
INR2,66,460/- against vat and service tax not refunded.
Tribunal awarded 12% interest on these amounts from the
date they became due and payable, in case the amounts were
not paid within 15 days of the passing of award, till realization.
The Tribunal also directed the petitioner to pay balance 25% of
the retention money of the claim and costs of arbitration
proceedings.
2. The respondent/claimant had entered into a sub-
contract with the petitioner, called as 'TVS sub-contract' and
the petitioner had deducted an amount of USD72,730/- and
INR39,04,510.03 out of the payments due towards the
respondent and had also not refunded vat and service tax in
terms of contract and had not paid remaining retention money
to the tune of 25% which resulted into invocation of the
Arbitration agreement by the respondent and passing of the
award by the Tribunal in favour of the respondent. The
contention of the counsel for the petitioner is that the sub-
contract entered into between the petitioner and the
respondent though was a lumpsum contract inclusive of all
taxes, royalty, custom duties (other than custom duties, i.e.,
basic custom duty, CVD and SAD of specified imported items
which were not payable under the special exemption
notification under the Customs Act, 1962 as described in terms
of payment, Annexure-4), excise duty and other duties, still the
petitioner was entitled to make deductions in case of an
eventuality of deviation in the custom duty rates. The
petitioner contended that it was entitled to deduct the amount
on account of exemption of custom duty enjoyed by
respondent under different notifications. The contracted
lumpsum price entitled the petitioner to make recoveries of the
amounts recovered from the petitioner by Samsung, on back-
to-back basis.
3. The learned Arbitral Tribunal considered the
contract between the parties and the specific clauses
regarding custom duty and came to conclusion that the
petitioner's assumption that the fixed lumpsum price under the
sub-contract was variable as per custom duty, was factually
not correct. It was observed that there was no component of
custom duty in the fixed lumpsum price agreed under the
contract nor there was any incidence of custom duty charged
and paid to the Government thereafter in respect of any of the
imports into the country under the contract. The Tribunal also
observed that the petitioner neither pleaded nor proved if any
amount towards the exemption of custom duty was adjusted
by the principal contractor (Samsung) from amount payable to
the petitioner. It was also observed that the petitioner had
failed to produce on record the invoices raised by Samsung on
them having a component of custom duty, unlike the invoices
raised by the respondent on the petitioner. The Arbitral
Tribunal thus came to conclusion that the petitioner was not
entitled to deduct the amount from the bills of respondent and
allowed the claim of the respondent regarding these
deductions. There is no dispute that the claimant/respondent
was entitled for vat and service tax refund and during the
arbitration proceedings, the petitioner had admitted a part of
the claim and undertaken to release the said amount to the
respondent/claimant at the earliest and as and when the same
was received by the petitioner from the principal director.
4. It is not disputed that the retention money to the
tune of 25% was not paid to the claimant/respondent because
of the alleged adjustments made by the petitioner and the
Tribunal allowed the claim to that extent as well.
5. The petitioner has assailed the award on the ground
that the Tribunal had not treated the parties with equality and
acted against the elementary principle of natural justice and
fair play. It is also submitted that the Tribunal had not given
reasons or justification for the conclusions arrived at and there
was no link between the material placed on record before the
Tribunal by the petitioner and the conclusions arrived at. It is
also submitted that the Tribunal failed to appreciate that 'TVS
sub-contract' agreement was entered on 6th June, 2003, i.e.
after Samsung (principal employer) had negotiated the price
with the respondent. The respondent did not disclose to the
Tribunal as to when the price was negotiated by Samsung and
when Samsung asked the respondent no. 1 to enter into firm
sub-contract with the petitioner. Thus, the award given by the
Tribunal was unfair.
6. The petitioner and the respondent had entered into
a written contract between them. Samsung was not a party to
the contract. It was for the petitioner to consider the contract
carefully at the time of entering into it. If the petitioner had
entered into a contract at the instance of Samsung (principal
employer), that cannot be a ground to hold that the contract
between the petitioner and the respondent was a back-to-back
contract and whatever deductions were made by Samsung
from the petitioner's bills are liable to be borne by the
respondent. The contract between the petitioner and the
respondent is an independent contract and is governed by its
own terms and conditions. Unless and until the contract
provided that it was a back-to-back contract and all deductions
made by Samsung from the petitioner would be the
responsibility of the respondent, the petitioner could not make
those deductions from the respondent. The learned Arbitral
Tribunal considered the terms of the contract between the
parties and taking into account the terms of the contract
passed the award.
7. It is settled law that under Section 34 of Arbitration
and Conciliation Act, this Court does not sit as an appellate
court over the decision of the Arbitral Tribunal and cannot re-
appreciate the evidence and arrive at a different conclusion.
The Arbitral Tribunal is a judge of the facts and of law and has
right to interpret the contract between the parties. This Court
cannot substitute its own opinion against the opinion of the
Arbitral Tribunal regarding quality, quantity and appreciation of
the evidence, import of the documents and interpretation of
the contract between the parties. The Court can interfere only
under the circumstances as enumerated under Section 34 of
the Arbitration and Conciliation Act 1996. The petitioner in this
case had challenged the award only on vague and unspecified
grounds. Though the award analysed the contract between
the parties and gave detailed reasoning, still it is alleged that
the award is an unreasoned award. The award has considered
what were the relevant documents effective between the
parties and required to be considered, still the allegation is
made that the Arbitral Tribunal had not considered the
documents. The proceedings before the Arbitral Tribunal as
filed by the petitioner show that both the parties were given
equal and adequate opportunity to present their case before
the Tribunal, still the allegations are made by the petitioner
that the Tribunal did not treat the parties equally.
8. I find that none of the grounds made by the
petitioner in the petition is tenable. I also find that the
challenge to the award made by the petitioner is not
sustainable under Section 34 of the Arbitration and Conciliation
Act. The petition is hereby dismissed.
July 03, 2009 SHIV NARAYAN DHINGRA J. ak
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!