Citation : 2009 Latest Caselaw 148 Del
Judgement Date : 19 January, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP No. 133/2002 and Arb. P. No. 31/2003
% Date of Decision: January 19, 2009
# Sanjeev Khokha ..... Petitioner
! Through: Mr. Rajeev Mehra, Advocate
Versus
$ Ircon Internation Ltd.
.....Respondents
^ Through: Mr. K.R. Gupta and Ms. Kiran
None for respondent No. 2.
CORAM:
HON'BLE MR. JUSTICE S.N. AGGARWAL
1. Whether reporters of Local paper may be allowed to see the judgment?
2. To be referred to the reporter or not?
3. Whether the judgment should be reported in the Digest?
S.N.AGGARWAL, J (ORAL) Both these petitions are taken up for disposal by this common
order with the consent of counsel for both the parties.
2 The petition being OMP No. 133/2002 is a petition filed by the
petitioner (hereinafter to be referred as the 'Contractor') under
Section 9 of the Arbitration and Conciliation Act, 1996. The case
being Arb. P. No. 31/2003 is an application filed by the Contractor
for appointment of an Arbitrator under Section 11(6) of the
Arbitration and Conciliation Act for adjudication of disputes that
have arisen between the parties under the contract in question
dated 12.04.1997.
3 Respondent No. 1 vide letter of indent dated 12.04.1997 had
awarded a contract to the Contractor for constructing 'guest house
and office block' at the National Agricultural Science Centre
Complex, Pusa Complex, New Delhi. At the time contract was
awarded, the firm to whom the contract in question was awarded
was a partnership firm duly registered under the Partnership Act,
1932. The petitioner/ contractor Mr. Sanjeev Khokha along with Mr.
Suresh Khokha and Mr. R.K. Kapoor was the partner of the
contractor firm. While the contract work was in progress, two of the
partners of the contractor firm namely Mr. Suresh Khokha and Mr.
R.K. Kapoor resigned from the firm and in terms of agreement
between them, the business under the same name of contractor
firm was succeeded by Mr. Sanjeev Khokha who has filed these
petitions in his capacity as sole proprietor of the contractor firm. Mr.
Suresh Khokha and Mr. R.K. Kapoor, erstwhile partners of the
contractor firm, were present before the Court when the matter was
taken for hearing by me on 07.01.2009, 14.01.2009 & 15.01.2009.
Both erstwhile partners of the contractor firm who attended the
hearing along with Mr. Sanjeev Khokha confirmed to the Court
about their having resigned from the contractor firm and also about
Mr. Sanjeev Khokha succeeding to the business of the contractor
firm after their resignation from the firm. There was dispute
between the parties regarding the date on which Mr. Sanjeev
Khokha succeeded to the business of the contractor firm. The
liability of the partners of a registered partnership firm is joint and
several in view of provisions contained in Section 25 read with
Section 32 of the Partnership Act, 1932. Since there was a dispute
about the date of dissolution of the contractor firm and also as
there was a dispute about the date on which Mr. Sanjeev Khokha
succeeded to the business of contractor firm, both the erstwhile
partners Mr. Suresh Khokha and Mr. R.K. Kapoor who attended the
hearing gave a statement to the Court that in case any award is
passed by the Arbitrator against the contractor firm, respondent No.
1 may enforce the said award not only against Mr. Sanjeev Khokha
who has filed these petitions but also against them (namely Mr.
Suresh Khokha and Mr R.K. Kapoor) as well being the erstwhile
partners of the contractor firm. On this statement being made by
erstwhile partners of the contractor firm, counsel for both the
parties have agreed for passing of a consent order in both these
petitions.
4 In terms of consent given by the counsel for the parties on
instructions from their clients, the petitioner/ contractor has agreed
to deposit the FDRs to the tune of Rs.2,41,35,092/- in the name
Registrar General of this Court so as to secure the payment of
amount of the bank guarantees furnished by the contractor firm to
respondent No. 1 in the event of an award being passed by the
Arbitrator in favour of respondent No. 1. It is submitted by Mr.
Mehra, learned counsel appearing on behalf of the petitioner/
contractor that his client shall furnish a fresh FDR in the sum of
Rs.64 lacs in favour of Registrar General of this Court within four
weeks from today and on instructions from his client, he further
submits that the FDRs for the balance amount out of total amount
of Rs.2,45,35,092/- are lying with respondent No. 2 i.e Punjab
National Bank, Sansad Marg Branch, New Delhi and a request is
made that this Court may direct the concerned Branch Manager to
endorse these FDRs for the balance amount (Rs.2,45,35,092 minus
Rs.64,00,000/- = Rs.1,81,35,092) in favour of Registrar General of
this Court forthwith. This suggestion given by Mr. Mehra is
acceptable to Mr. K.R. Gupta, learned counsel appearing on behalf
of respondent No. 1. Accordingly, the petitioner/ contractor is
directed to furnish a fresh FDR of Rs.64 lacs in the name of
Registrar General of this Court within four weeks from today and
the Branch Manager, Punjab National Bank, Sansad Marg Branch,
New Delhi is directed to endorse the FDRs for the balance amount
((Rs.2,45,35,092 minus Rs.64,00,000/- = Rs.1,81,35,092)) lying
with him in the name of the contractor firm. On these FDRs being
endorsed by Punjab National Bank in favour of Registrar General of
this Court, the lien of respondent No. 1 with regard to bank
guarantees to the tune of Rs.2,45,35,092/- furnished to it by the
contractor firm shall stands discharged automatically. The amount
in the form of FDR to be deposited with the Registrar General of this
Court in the present case shall be dealt with in terms of the award
that may be given by the learned arbitrator.
5 Clause 67 of the contract between the parties contains
mechanism for settlement of dispute between the parties under the
contract in question. It is admitted by both the parties that the
disputes in fact have arisen between them under the contract in
question and they have agreed for getting these disputes decided
through the process of arbitration. Since the contractor firm had not
exhausted the mechanism for settlement of disputes provided in
Clause 67 of the contract, counsel for both the parties have agreed
that Mr. A.K. Sarin, Engineer Member (retd.), DDA, R/o 14/1, Tilak
Marg, New Delhi-110001 (Mobile No. 9810032292) be appointed as
the sole arbitrator for deciding the disputes between the parties
under the contract in question. The name of Mr. A.K. Sarin has been
selected by the counsel for the petitioner Mr. Sanjeev Khokha out of
list of 29 names of arbitrators furnished by respondent No. 1.
Needless to say that both the parties to the contract will be entitled
to make their claims and counter claims against each other and
they have to be decided by the sole arbitrator Mr. A.K. Sarin. The
arbitrator shall decide the disputes between the parties under the
contract in question in accordance with law after giving opportunity
of hearing to both of them. Learned arbitrator shall fix his own fee
as per rules and any fee to be fixed by the learned arbitrator has to
be shared equally by both the parties.
A copy of this order be sent to the learned arbitrator for
information and necessary compliance. The parties are directed to
appear before the learned arbitrator for necessary directions at
5:00 PM on 25.02.2009.
In view of the above, both these petitions stand disposed of
leaving the parties to bear their own costs.
Order dasti to both the parties through their counsel under the
signatures of the Court Master.
January 19, 2009 S.N.AGGARWAL
a [JUDGE]
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ Arb. P. No. 31/2003
% Date of Decision: January 19, 2009
# Sanjeev Khokha ..... Petitioner
! Through: Mr. Rajeev Mehra, Advocate
Versus
$ Ircon Internation Ltd.
.....Respondents
^ Through: Mr. K.R. Gupta and Ms. Kiran
None for respondent No. 2.
CORAM:
HON'BLE MR. JUSTICE S.N. AGGARWAL
1. Whether reporters of Local paper may be allowed to see the judgment?
2. To be referred to the reporter or not?
3. Whether the judgment should be reported in the Digest?
S.N.AGGARWAL, J (ORAL) For orders, see file of OMP No. 133/2002.
January 19, 2009 S.N.AGGARWAL a [JUDGE]
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!