Citation : 2009 Latest Caselaw 655 Del
Judgement Date : 26 February, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP 163/2005
%26.02.2009 Date of decision: 26.02.2009
M/S GENERAL ELECTRIC
INTERNATIONAL INC. ....... Petitioner
Through: Mr. Abhinav Vasisht & Ms. Harsita
Priyanka, Advocates.
Versus
M/S U.C. JAIN HUF & Ors. ....... Respondents
Through: Mr. B.B.Gupta, Advocate for the
respondents No. 1to3 & 5.
Mr. S.K. Chandwani & Mr. M.S.
Rahman, Advocates for the
respondents No.4,6&7.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may Yes
be allowed to see the judgment?
2. To be referred to the reporter or not? Yes
3. Whether the judgment should be reported Yes
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. Objections under Section 34 of the Arbitration Act, 1996 with
respect to the award dated 8th February, 2005 of Shri. H.C. Gupta,
Member (Retd.), M.R.T.P.C. are for consideration.
2. The disputes between the parties arose out of several
agreements entered into by the petitioner with different respondents
all in relation to letting out of the ground floor of House No.13,
Palam Marg, Vasant Vihar, New Delhi - 110057. The lease
agreement and the security deposit agreement are between the
petitioner and the respondent No.1 M/s U.C. Jain (HUF) of which the
respondent No.2 Mr. U.C. Jain is the Karta. The Generator Set
maintenance agreement is between the petitioner and the
respondent No.3 Smt. Rakhee Jain. The AC maintenance agreement
is between the petitioner and the respondent No.4 Mr. Ashish Jain.
The other maintenance agreement is between the petitioner and the
respondent No.5 Ms. Raj Rani Jain and the renovation agreement is
between the petitioner and the respondent No.6 M/s Ease
Consultants (P) Ltd. Each of the said agreements contained a clause
of arbitration of disputes or differences arising out of or in
connection with the agreement to be referred to two arbitrators one
each to be appointed by each party and for the arbitration to be
subject to the Arbitration and Conciliation Act, 1996 and the rules of
Arbitration of Indian Council of Arbitration.
3. However, notwithstanding the arbitration clause, disputes and
differences having arisen between the parties the petitioner
instituted suit No.1903/1998 in this court against all the respondents
for mandatory injunction directing the respondents to assume
possession of the property and claiming recovery of Rs.32,63,100/-
from the respondents. Though certain pleadings/documents of that
suit were also filed in the present proceedings but during the
hearing, with the consent of the parties, the file of the suit was also
called for. It was the case of the petitioner in that suit that as
against the promised date of delivery of possession of 1st April, 1997
it was given possession after inordinate delay only on 1st July, 1997;
that after possession it was found that the premises and the
amenities and services therein were not as assured, promised and
agreed; that the petitioner therefore terminated the lease agreement
and called upon the respondents to accept possession and refund the
security deposit placed by the petitioner with each of the
respondents under different agreements; that the respondents had
however illegally refused to do so. The respondents also upon
receipt of summons of the suit inspite of arbitration clause in the
agreements did not apply under Section 8 of the Arbitration Act,
1996 and filed their written statement. During the pendency of the
suit on 23rd September, 1998 an interim settlement was arrived at
between the parties as per which a sum of Rs.10 lacs was agreed to
be paid to the petitioner and a court commissioner was appointed for
inspecting the property, taking photographs with regard to the
condition and for assessing the quantum of damages, if any; it was
further agreed that the keys of the property shall be handed by the
petitioner to the court commissioner and the court commissioner
after looking into the question of electricity bills shall submit the
report. The commission was executed on 15th October, 1998 and the
commissioner on the same day also delivered actual possession of
the premises, amenities etc. therein to the respondents. Some of the
respondents also preferred objections to the report of the court
commissioner. On the basis of the pleadings of the parties and even
though no counter claim had been preferred by the respondents, on
31st July, 2000, the following issues were framed:-
1. Whether the plaint does not disclose any cause of action?
2. Whether the suit is bad for mis-joinder of parties and causes of action?
3. Whether the suit has not been properly valued for purposes of court fee and jurisdiction?
4. Whether the lease agreement was terminated by notice dated 12th December, 1997/9th January, 1998? If so, to what effect?
5. Whether the plaintiff is not liable to pay rent and maintenance charges from 1st December, 1997 to 15th October, 1998? If so, to what effect?
6. Whether there was any damage to the property at the time it was vacated by the plaintiff?
7. If issue No.6 is proved in the affirmative, whether the defendant is entitled to claim compensation/damages for this loss? If so, to what extent?
8. To what amount, if any, is the plaintiff entitled from the defendants?
9. Whether the plaintiff is entitled to interest? If so, at what rate and for what period?
10. Relief.
And the trial was ordered. On 20th May, 2002 it was noted in
the order sheet of that suit that the counsel for the parties on
instructions were now agreed that in view of the arbitration
agreement between the parties, the disputes/differences "subject
matter of the present suit" be referred for adjudication by a sole
arbitrator. Accordingly, Mr. H.C. Gupta aforesaid was appointed as
the sole arbitrator "to resolve the disputes/difference subject matter
of the present suit between the parties". It was also noted in the
said order that after the institution of the suit, a sum of Rs.10 lac had
already been paid to the petitioner and it was ordered that after
adjusting the said amount, the total claim of the petitioner as it so
stood reduced shall be treated as the petitioner's claim in the suit.
4. It may be noted that after the institution of the suit aforesaid
by the petitioner, the respondent No.1M/s U.C. Jain (HUF) also
instituted suit No.1923/2008 in this court for recovery of possession
of the premises from the petitioner. Along with the said suit an
application under Order2 Rule 2 of the CPC was also filed to sue
separately the petitioner for recovery of the arrears of rent and other
dues. However, after the possession of the premises was handed
over on 15th October, 1998 by the court commissioner appointed in
the other suit, this suit was on 1st February, 1999 dismissed as
infructuous. The file of this suit also was called during the hearing of
the objections with the consent of the counsel for the parties.
5. The petitioner preferred its claims before the Arbitrator of
Rs.19,50,000/-, after adjustment of Rs.10 lacs received as aforesaid
during the pendency of the suit and Rs.30,000/- towards electricity
charges. The respondents filed their statement of defence and
counter claim. The petitioner herein filed their response to the
counter claim of the respondents. The parties also filed affidavit by
way of evidence.
6. The arbitrator has vide award aforesaid awarded a sum of
Rs.3,92,760/- to the respondents No.1to3 & 5 against the petitioner
along with interest at 12% per annum from 15th October, 1998 till
the date of payment and awarded a sum of Rs.82,500/- to the
petitioner against the respondent No.4 Mr. Ashish Jain together with
interest on 12% per annum from 15th October, 1998 till the date of
payment. No objections have been preferred by the respondent No.4
Mr. Ashish Jain to the award in so far as against him. Objections
have been preferred by the petitioner only to the award against it for
sum of Rs.3,92,760/- with interest and for dismissal of its claims.
7. According to the petitioner though it had paid rent and other
charges under the various agreements w.e.f. 1st April, 1997 from
which date it was to be put on possession of the premises but the
possession was delivered to the petitioner on 1st July, 1997 only. The
petitioner had, therefore, claimed refund of the rent and other
charges paid for the said period. The arbitrator has found the claim
of the petitioner of having been put into possession on 1st July, 1997
to be fallacious. Though in the pleadings objection has been raised
to the said finding also, but the counsel for the petitioner during the
course of hearing fairly conceded that such objection was outside the
ambit of Section 34 of the Arbitration Act.
8. According to the petitioner, it had given notice of termination
of tenancy on 12th December, 1997 or in any case on 9th January,
1998 - which was acknowledged by the respondents; its liability for
rent and other charges ceased on that date even though the
possession was delivered by the court commissioner on 15th October,
1998. Alternatively it is contended that the petitioner at best is
liable for rent and other charges till 31st March, 1998 only, on which
date respondents had agreed to receive possession. The arbitrator
however found that though the petitioner had offered possession of
the premises and other amenities, such offer was conditional on
payment of various security deposits. The arbitrator further held that
the respondents were also ready to take possession and refund
security deposits, subject to deduction of rental dues, damages,
electricity charges therefrom and with respect whereto no
settlement could be arrived at between the parties. The Arbitrator,
therefore, held the petitioner liable for rent and other charges till
15th October, 1998. Axiomatically, the arbitrator after adjusting the
balance security deposit in the rent and other charges till 15th
October, 1998 found the aforesaid sum of Rs.3,92,760/- to be due
from the petitioner, inclusive of Rs. 20,000/- towards value of
damages to the premises and Rs. 32,760/- towards electricity
charges. The arbitrator also negatived the claim of the petitioner of
Rs. 9,60,000/- paid under the renovation agreement holding that it
was a one time payment and the petitioner has not led any evidence
that the renovation was not carried out.
9. The counsel for the petitioner besides challenging the
aforesaid findings of the arbitrator has also argued that only the
claims of the petitioner had been referred to arbitration. He has
urged that the arbitrator ought not to have considered the counter
claims of the respondents. He has further urged that the counter
claims of the respondents even if to be considered were on the date
of institution thereof barred by time. He has further urged that
though the issue had been framed in the suit instituted by the
petitioner of the claims of the respondents but the respondents had
neither made any counter-claim nor paid any court fee thereon. He
has argued that when refund of security deposit is sued for, the party
denying the liability for refund is required to make a counter claim
with respect to its claims and unless so makes a counter claim is not
entitled to oppose the refund of security deposit.
10. Under Section 34 of the Arbitration Act, the court is
empowered to set aside an award if the same deals with the disputes
not contemplated by and not falling within the terms of submission
to arbitration or if it contains decision on matters beyond the scope
of submission to the arbitration. Thus, if the contention of the
petitioner that the counter claims of the respondents were not
referred to arbitration is to be found true, the award in so far as
allowing the said counter claims would certainly be liable to be set
aside.
11. As noticed above, this court vide Order dated 20th May, 1992
referred the disputes/differences subject matter of that suit to
arbitration. The question which arises is as to what were the
disputes and differences subject matter of that suit.
12. I will first deal with the contention of the counsel for the
petitioner that in a suit for refund of security deposit, the defendant;
averring that the security deposit is liable to adjustment, has to
prefer a counter claim to that effect and unless does so, a decree for
refund of security deposit is to follow without adjudication of the
claims for adjustments therefrom. It is essential to understand the
nature and character of a security deposit. The security deposit is
generally meant to secure the landlord against various defaults of
the tenant at the time of final determination of the lease. Such
default may include damage to the property, arrears of rent, arrears
on account of electricity or water charges, telephone bills etc. It was
so held by this court in Parmanand Vs. Vimal Chand Jain 1995 III
AD (Delhi) 547 that the security deposit is not liable to be adjusted at
interim stages towards rent unless there is an agreement to the
contrary between the parties. Similarly in Uberoi Sons Machines
Ltd. Vs. Samtel Colour Ltd. 105 (2003) DLT 383 this court held
that security is paid to the landlord for the purpose of guaranteeing
that no damage is done by the tenant nor any fixture and fittings are
removed and the landlord is entitled to use the security for repairing
the damages done by the tenant. In the present case, the security
deposit agreement between the parties also provided of mutually
agreed reasonable deduction therefrom of damage or pending dues if
any on account of lessee's occupation of the demised premises.
Once it is found that the very purpose of security deposit is to secure
to the landlord the value of any outstandings from the tenant, it
would be inherently, contradictory to hold that though the landlord is
holding the said security deposit but in a suit by the tenant for
refund thereof the landlord is required to maintain a counter claim
(and which is same as a suit) for the adjustment of claims and that
without maintaining the said counter claims, is not entitled to the
relief of adjustments. The occasion for the tenant instituting a
suit/claim for refund of security deposit would arise only when the
tenant contends that there is nothing to be adjusted from the same
and the landlord contends otherwise. The question for adjudication
before the court in such case would be whether any adjustment is to
be done from the security deposit or the same is refundable in toto to
the tenant. For the same adjudication, the landlord cannot be asked
to file a counter claim and pay court fee thereon. The said counter
claim would also adjudicate an adjudication as to whether the
landlord is entitled to claim adjustments or not. The law provides for
court fee to be paid on adjustments, counter claim, set off, when the
claim of the opposite party is admitted and is sought to be
adjusted/set off against some claim. In such a situation, the
adjudication involved qua the set off or adjustment is different from
the claimed amount. It is for this reason that a separate set of court
fee is required to be paid thereon. However, where as in the case of
security deposit, the question of adjudication is whether adjustment
permitted to be made, is to be made or not out of the security
deposit no court fee is required to be paid thereon. The said
contention of the counsel for the petitioner does not find favour with
me.
13. Thus, even in the absence of a counter claim of the
respondents the arbitrator while adjudicating the claim of the
petitioner for refund of security deposit was entitled to go into the
question of adjustments, to which the respondents were entitled to
therefrom.
14. However, since the arbitrator besides merely allowing
adjustments from the claim for security deposit has also found claims
over and above thereto of the respondents against the petitioner and
which have been allowed to the extent of Rs. 3,92,760/- herein
above, it is also important to adjudicate whether the findings of the
arbitrator of the counter claims also having been referred calls for
any interference under Section 34 or not.
15. At the outset, it may be noted that when the respondents
preferred their counter claims no application under Section 16 of the
Act was made by the petitioner. The petitioner though filed reply to
the counter claim of the respondents did not even challenge therein
that the said counter claims had not been referred to arbitration. It
was only while addressing arguments before the arbitrator that the
said plea was taken by the petitioner.
16. It has been held by the Division Bench of this court in S.N.
Malhotra & Sons Vs. Airports Authority of India (2008) IV AD
(Delhi) 424 that without following the procedure under Section 16 of
the Arbitration Act, the plea under Section 34 (2) (a) (4) of the Act
cannot be taken for the first time. Admittedly no plea under Section
16 of the Act was taken. The said objection of the petitioner is liable
to be dismissed on this ground alone.
17. Besides aforesaid, even otherwise I am unable to find fault
with the award to the effect that the counter claims were also
referred to arbitration.
18. The contention of the counsel for the petitioner is that since no
counter claim had been preferred by the respondents in the suit in
which the reference was made, the order of this court to the effect
that the dispute subject matter of the suit were being referred to
arbitration could include only the claims of the petitioner. The
argument of the petitioner would have been correct had the issues
No. 5, 6 and 7 not been framed. The said issues clearly are to the
effect as to whether the respondents are entitled to amounts
claimed. The contention of the petitioner is that the said issues were
erroneously framed. However, the fact remains that they were
framed in the presence of the counsel for the petitioner and without
any objection whatsoever from the petitioner. The petitioner having
allowed the said issues to have been framed and to remain on record
till the date the disputes subject matter of suit were referred to
arbitration, the said disputes have to necessarily relate to the issues
framed in the suit and which issues as aforesaid include the counter
claims of the respondents also. This court made the order of
reference in relation to the issues. If according to the petitioner any
of the issues was wrongly framed, the petitioner should have got the
same clarified. The petitioner by allowing the said issues to stand till
the date of reference and in fact till the date of award has led not
only this court while making the order of reference but also the
arbitrator as well as the respondents to believe that their claims on
which issues had been framed were also being referred to arbitration
and were to be adjudicated by the arbitrator only. Had the
petitioner raised the objection at that time, the respondents would
have stood warned and would have either sought clarification from
this court or would not have agreed to arbitration or would have
sought a specific direction of reference of its counter claims also. It
may be noted, the respondents in suit filed by them had filed
application reserving right to sue for their counter claims. Had the
issues aforesaid not been framed or had objection been taken by the
petitioner, the respondents would have separately sued.
19. I had, during the course of hearing, put to the counsel for the
petitioner as to what would have been the effect had instead of being
referred to arbitration, the suit proceeded. In that case also at the
stage of final arguments, what course would have been adopted by
the court, whether to refuse to answer these issues because no
counter claim had been preferred or to allow the respondents to pay
court fee thereon. The counsel for the petitioner naturally was non-
committal. In my view, had the trial proceeded on issues, after
several years it would have been unjust to refuse to answer the
issues on counter claims of respondents without giving an
opportunity to the respondents to pay the court fees.
20. A perusal of the written statement of the respondents in the
suit would show that though the respondents made their claims but
did not formally make a counter claim and axiomatically the question
of valuing the same for purpose of court fee did not arise. However,
the manner in which the said written statement was understood by
all concerned including the petitioner was that the respondents
besides raising the pleas of adjustment of the entire security deposit,
were also claiming other amounts from the petitioner. In my opinion,
it is too late in the day for the petitioner to poke holes in the issues
framed in the suit and which were referred to arbitration and no
illegality can be found with the finding of the arbitrator of the
counter claims also having been referred to him.
21. There is yet another aspect of the matter. The respondent
raised the counter claims before the arbitrator on the premise that
the same were arbitrable. The petitioner replied to the said counter
claims also on the premises that the same were arbitrable. In my
opinion an arbitration agreement within the meaning of Section 7 (4)
(c) of the Act came into being, even if there had been no reference of
the said counter claims to arbitration.
22. That brings me to the question of limitation. It is the
contention of the counsel for the petitioner that since counter claims
were not made in the suit, the date of institution thereof should be
the date of filing counter claim before the arbitrator and which was
beyond three years from date of vacation. However, the said
question of limitation would arise only if the counter claims are
found to have been not referred to arbitration by order of this court.
Since I have held that the counter claims were referred to
arbitration, I do not find any merit in the plea of the counter claims
being barred by time. Even otherwise the respondents by raising the
said disputes and by pressing and having framed issues thereon had
raised the same within the meaning of Section 21 of the Act and for
this reason also it cannot be said that the counter claim was barred
by time or that the finding of the arbitrator thereon is contrary to the
policy of India. Moreover, no bar of limitation was pleaded. It was
argued for the first time during arguments before arbitrator.
Limitation is a mixed question of law and facts and no fault can be
found in the reasoning of the arbitrator and the court can in absence
of pleading refuse to entertain the same.
23. That brings me to the awards on merits.
24. The findings of the arbitrator of there being damage to
premises of value of Rs. 20,000/-, of there being electricity arrears of
Rs. 32,760/- and of the petitioner having led no evidence to be
entitled to refund of Rs. 9,60,000/- are pure findings of facts and
non-interfereable under Section 34. The counsel for the petitioner
has rightly raised no argument with respect thereto.
25. The arbitrator has found that though the petitioner had offered
the possession to the respondents but the said offer was conditional
and therefore the liability of the petitioner for rent and other charges
did not cease till the date of actual delivery of possession. Is such
finding such which is liable to be interfered with under Section 34?
In my opinion not. It cannot be argued that the said finding is
contrary to the policy of India which as per the dicta in ONGC Vs.
SAW Pipes Ltd. (2003) 5 SCC 705 has been held to be the law of
India.
26. I may notice that while this court in Uberoi Sons Machines
Ltd. (Supra) has held that a tenant could not have retained
possession of the premises without paying the rent on account of
non-refund of security deposit by the landlord and that the tenant in
such case has an independent remedy to recover the security deposit
and if retains possession of the premises on the ground of non-refund
of security deposit, would remain liable for payment of rent and
other charges with respect to the premises till the date of
possession, another single judge of this court in ICRA Ltd. Vs.
Associated Journals Ltd. 2007 VII AD (Delhi) 437 has held that if
the defendant/landlord does not take possession in spite of offer of
the tenant, the tenant cannot be liable for rent and other charges
thereafter. To the same effect is another judgment of a single judge
of this court in Onida Finance Ltd. Vs. Ms. Malini Khanna 2002
(III) AD (Delhi) 231. Thus, it would be seen that whether possession
has been offered unequivocally or not is a question of fact. In the
present case, the arbitrator has returned a finding that the offer of
possession of the petitioner was not unequivocal and not
unconditional and therefore the petitioner continued to be liable for
rent. Such factual findings of the arbitrator is outside the purview
of interference under Section 34 of the Act.
27. In the present case, the agreement in writing between the
parties entitled the petitioner to retain possession till the refund of
the security deposit. However, a detailed inspection of the security
deposit agreement would show that only mutually agreed
reasonable deduction due to damage or pending dues, if any, were
allowed to be deducted therefrom. It was only on the landlords
default in refunding such mutually agreed amount that the petitioner
was entitled to withhold possession without any liability for rent and
other charges. However, the present was a situation where no
mutual agreement could be arrived at between the parties as to the
deductions. The remedy provided therefor in the agreement itself
was of arbitration. The only reasonable way of interpreting such a
clause in the agreement would be that, if in spite of a mutual
agreement as to the amount of security deposit refundable, the same
is not refunded, the tenant even if withholds possession would not be
liable for any rent. If, however, the parties are not able to arrive at
any mutual settlement, the only remedy open to the tenant is to
surrender possession and to resort to the dispute resolution
mechanism agreed to between the parties. If the tenant in such a
case continues to occupy, he will do so at his own peril of being
found liable to pay rent and other charges, till the date of actual
delivery of possession.
28. A perusal of the correspondence between the parties also
shows that the petitioner had therein agreed to pay rent till 31 st
March, 1998. The respondents were however claiming more
amounts. The respondents vide letter dated 13th February, 1998
showed willingness to take possession and to pay the security
deposit after adjusting the damages, if any. The petitioner however
did not come forward to deliver the possession and ultimately the
respondents got issued the legal notice dated 10th May, 1998,
thereafter. Even in response thereto, the petitioner did not offer
possession and instead filed the suit.
29. The law as to interference in arbitral awards need not be
restated. The arbitrator being a judge chosen by parties to finally
decide the matter, the awards are not to be seen as in appeal.
Findings of arbitrator purely based on appreciation of material on
record cannot be interfered with. The award in this case is not found
contrary to the agreement or the law. No inconsistency is found in
the award.
30. The counsel for the respondent No.4 has urged that this court
should interfere with the rate on interest awarded by the arbitrator.
However, no objections have been preferred; in the absence of the
objections, this court does not have the power to interfere with the
award. Moreover, I find that the arbitrator has allowed against the
respondent No.4 interest at the same rate as allowed against the
petitioner in relation to the counter claims of other respondents. For
this reason also no ground is found to interfere with the rate of
interest.
31. Thus, I do not find any ground to interfere with the award. The
petition under Section 34 is dismissed. However, in the facts and
circumstances of the cases the parties are left to bear their own
costs.
RAJIV SAHAI ENDLAW (JUDGE) February 26, 2009 PP
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!