Citation : 2009 Latest Caselaw 563 Del
Judgement Date : 17 February, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP 340/2008 & ARB.APPL.14/2008
%17.02.2009 Date of decision: 17th February, 2009
PUNJ LIOYD LTD .... Petitioner/Appellant
Through: Mr Amit S Chadha, Sr Advocate with
Mr Kunal Sinha and Mr Manish Jha,
Advocates
Versus
NATIONAL HIGHWAYS AUTHORITY ... Respondent
OF INDIA
Through: Ms Padma Priya with Mr Sumit
Gehlawt, Advocates.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may Yes
be allowed to see the judgment?
2. To be referred to the reporter or not? Yes
3. Whether the judgment should be reported
in the Digest? Yes
RAJIV SAHAI ENDLAW, J.
1. The petition as well as the appeal have arisen out of the order
dated 5th March, 2008 of the Arbitral Tribunal constituted in terms
of the agreement between the parties. On an application of the
respondent herein and who is also the respondent before the
Arbitral Tribunal, under Section 16 of the Arbitration and
Conciliation Act, 1996, the Arbitral Tribunal has held claims No. 18
to 24 out of the claims preferred by the petitioner/Appellant against
the respondent before the Arbitral Tribunal to be not arbitrable
owing to mandatory provision of clause 67 of the agreement
between the parties having not been followed by the
petitioner/appellant.
2. Clause 67 of the agreement between the parties relates to
settlement of disputes. Sub-clause (1) thereof provides that a
dispute between the parties shall in the first place be referred to the
Disputes Review Board (DRB) to be constituted in terms thereof; it
further provides that if any party is dissatisfied of any
recommendation of the DRB or the DRB fails to issue its
recommendation within 56 days of the receipt of the request for
recommendation, then that party shall within 14 days after receipt of
recommendation or within 14 days after the expiry of the said period
of 56 days, give notice to the other party of intention to commence
arbitration as to the matter in dispute; such notice was agreed to,
to establish the entitlement of the party giving the same to
commence arbitration; it further provides that no arbitration in
respect of the dispute shall be commenced unless notice is given; the
said clause further provides that if no such notice is given within 14
days after receipt of recommendation, the recommendation shall
become final and binding upon the parties. Sub-clause (3) of clause
67 provides that the disputes in respect of recommendations which
have not become final and binding pursuant to sub-Section (1) shall
be finally settled by arbitration as provided therein.
3. The admitted position in the present case is that the claims 18
to 24 were referred to the DRB on 19th November, 2005. In terms of
the agreement, the DRB was required to give its recommendation on
the said disputes within 56 days i.e., by 15th January, 2006. The DRB
however for reasons which are not relevant for the present purposes,
did not make any recommendation within the said period of 56 days
and with the consent of the parties, the tenure of the DRB was
extended from time to time, till 31st March, 2006. A meeting of the
DRB was fixed for 16th July, 2006. However, the chairman of the
DRB cancelled the said date vide letter dated 24th June, 2006 with
the stipulation that further dates would be fixed after getting
consent letter from both the parties regarding extension of the
tenure of the DRB. The respondent vide letter dated 27th June, 2006
of its General manager and Project Director and in pursuant to the
communication with the Chairman DRB gave its consent to extend
the tenure of DRB upto 31st July, 2006 with a further request to the
DRB to confirm that decision in respect of all its disputes previously
referred will be finalized by 31st July, 2006, so as to obtain the
approval of the competent authority. The Chairman DRB vide letter
dated 5th July, 2006 fixed the next hearing before the DRB on 28th to
30th July, 2006. The respondent, however, vide its letter dated 12th
July, 2006 informed the DRB with copy to the petitioner/appellant
that the proposal for extension of the tenure of DRB upto 31 st July,
2006 had not been accepted by the competent authority of the
respondent and thus requesting for postponement of the hearing
fixed on 28th to 30th July, 2006. The DRB was also requested to
communicate the recommendations of claims No. 18 to 24 for which
hearings were already completed on the earlier dates. The
Chairman DRB accordingly vide letter dated 17th July, 2006, in view
of the letter aforesaid of the respondent conveying that extension of
DRB beyond 31st March, 2006, had not been agreed to by the
respondent, cancelled the hearing fixed on 28th to 30th July, 2006.
4. The petitioner/appellant vide letter dated 11th August, 2006
gave notice to the respondent of its intention for commencing of
arbitration for the claims No. 18 to 24 aforesaid alongwith the other
claims. The petitioner/appellant, vide the same letter, also appointed
its nominee arbitrator. The respondent vide letter dated 25th August,
2006 referred all the 24 disputes to arbitration. With respect to the
claims 18 to 24 it was mentioned that the same were pending with
the DRB and the tenure of the DRB was completed.
5. The respondent thereafter moved the application under
Section 16 of the Act before the Arbitral Tribunal contending that
the Arbitral Tribunal had no jurisdiction to decide the claims 18 to 24
for the reason of the petitioner/appellant having not issued the
notice of its intention to refer the said disputes to arbitration within
14 days of the expiry of the 56 days period.
6. The respondent has contended that the notice ought to have
been given within 14 days of 15th January, 2006 i.e., on the expiry of
the first 56 days of the constitution of DRB. Alternatively, it is
contended that in any case the notice ought to have been given
within 14 days of 12th July, 2006 on which date the respondent had
communicated that the competent authority of the respondent was
not willing to extend the term of the DRB. Conversely it is argued by
the senior counsel for the petitioner/appellant that since the
respondent had agreed to extension of time of the DRB till 31st July,
2006 and from which the respondent had subsequently retracted, the
notice given on 11th August, 2006 was within the stipulated time of
14 days.
7. The Arbitral Tribunal decided the application of the respondent
under Section 16 of the Act in favour of the respondent. It was held
that there was no unequivocal consent of the respondent to extend
the term of the DRB till 31st July, 2006. The Arbitral Tribunal held
that the notice given by the petitioner/appellant was beyond the time
provided in the arbitration clause and thus held that the tribunal had
no authority to examine and adjudicate upon the said claims 18 to
24. I am informed that arbitration proceedings qua the other claims
of the petitioner against the respondent arising out of the same
agreement are pending before the Arbitral Tribunal.
8. The petitioner/appellant after the order dated 5th March, 2008
(supra) of the Arbitral Tribunal first filed the OMP under Section
43(3) of the Act for extension of time for commencement of arbitral
proceedings and thereafter filed the appeal challenging the order of
the Arbitral Tribunal aforesaid on the application under Section 16 of
the Act. The respondent has filed a reply to the OMP as well as the
appeal.
9. The senior counsel for the petitioner/appellant has argued that
in the facts and circumstances hereinabove stated, the delay, if any,
in giving the notice of intention of arbitration not only is miniscule
but attributable to the respondent and the petitioner will suffer
undue hardship if deprived of the claim without its adjudication. The
order of the tribunal was also challenged on merits for the
contentions made therein and as recorded therein and which did not
find favour with the tribunal.
10. This court had on 16th December, 2008 itself when the hearing
commenced inquired from the senior counsel for the
petitioner/appellant as to whether clause aforesaid in the agreement
requiring notice of intention to arbitrate to be given within 14 days
and forfeiture of right of arbitration upon failure to give such notice
was not in contravention of Section 28 of the Indian Contract Act as
amended w.e.f. 1997. The senior counsel for the petitioner/appellant
fairly stated that the said plea was neither taken before the Arbitral
Tribunal nor in the memorandum of appeal nor was this ground
taken in the OMP. It was urged that the petitioner on other grounds
urged, was entitled to the relief. The counsel for the respondent had
sought adjournment on that date and has also made submissions
with respect to Section 28 of the Contract Act, which being a pure
question of law, can be taken up even though not pleaded.
11. The counsel for the petitioner/appellant has also argued that
the respondent itself had referred the claims aforesaid to arbitration
and was therefore estopped from contending that the same were not
referable. The counsel for the respondent has urged that the
provisions of Section 43(3) can be availed of only before reference to
the arbitration and not after the order on an application under
Section 16. With respect to the arguments of the petitioner/appellant
that the respondent was estopped, it was urged that the respondent
of its own could not have refused to refer the disputes to arbitration
even though not arbitrable according to the respondent and the said
plea could be decided by the Arbitral Tribunal only and for which
purposes the application under Section 16 was immediately filed. It
was further contended that the period of 14 days could not be
computed from 31st July, 2006 inasmuch as prior thereto, on 12th
July, 2006 itself notice was given by the respondent of its competent
authority having not agreed to extension of time till 31st July, 2006.
12. I do not find any merit in the contention of the petitioner that
the respondent having referred the disputes to arbitration was
disentitled / estopped from taking the plea aforesaid. The decision
whether the disputes are arbitrable or not is to be taken by the
arbitrator and not by the respondent. The respondent would have,
while referring the disputes, done the same without prejudice to its
contention that claims 18-24 were not arbitrable for the delay in
giving the notice of arbitration but having not stated so cannot
deprive the respondent of taking the said plea before the Arbitral
Tribunal.
13. The claims 18 to 24 are otherwise arbitrable as per the
agreement between the parties. The Arbitral Tribunal has however
held that they are not so arbitrable because the agreement between
the parties provides that they shall not be so arbitrable (as distinct
from that they shall be barred) unless notice of intent to commence
arbitration is given within the time fixed by the agreement. The
Arbitral Tribunal held that the petitioner/appellant had not given the
notice within the time fixed by the agreement. The tribunal noticed
Section 28 of the Contract Act but held the same not coming to the
rescue of the petitioner/appellant owing to the dicta of Apex Court in
National Insurance Co Ltd Vs. Sujir Ganesh Nayak AIR 1997 SC
2049.
14. Section 28 of the Contract Act, as amended on 8th January,
1997 deals with agreements, (a) by which any party thereto is
restricted absolutely from enforcing its rights under or in respect of
any contract by the usual legal proceedings in the ordinary tribunals,
and/or (b) which limit the time within which it may thus enforce its
rights; and/or (c) which extinguish the rights of any party thereto, or
discharge any party thereto from any liability under or in respect of
any contract on the expiry of a specified period as to restrict any
party from enforcing its rights.
and declares such contracts to be void.
15. Unfortunately the tribunal did not notice the amendment w.e.f.
8th January, 1997 of Section 28 and thus relying upon National
Insurance Co. (supra) (which itself, though pronounced on 21st
March, 1997 i.e., soon after the amendment, does not deal with the
amended Section 28) held that the parties could provide for
forfeiture or waiver of rights. Prior to the amendment, the contracts
of the category in clause (c) in para 14 hereinabove were not covered
by the ambit of Section 28. That is why the courts, as in National
Insurance Co. (supra) had held that parties could agree/provide for
forfeiture of rights. The amendment was brought about to get over
such interpretations of Section 28 as existing earlier.
16. This court in Pandit Construction Company Vs. DDA 143
(2007) DLT 270 has held that National Insurance Co. and yet
another dicta of the Apex Court in Wildlife Institute of India Vs.
Vijay Kumar Garg (1997) 10 SCC 528 also pronounced soon after
the amendment on 2nd May, 1997, do not deal with the amended
Section 28 and hence not good law. Thus the arbitration clause in a
DDA contract providing that if the contractor does not make demand
for arbitration within 90 days of receiving intimation of bill being
ready for payment, the claims of the contractor will be deemed to
have been waived and absolutely barred and DDA discharged and
released from liabilities in respect of those claims was held to be in
teeth of Section 28 as amended and not barring the claim of the
contractor.
17. Though the aforesaid is enough for interfering with reasoning
given by the Tribunal with respect to Section 28, but I find that there
is a difference in clause 67 of the NHAI contract and the DDA
contract in Pandit Construction Co. (supra). It is felt necessary to
deal with the said difference also since NHAI is involved in a large
number of arbitrations.
18. It will be seen that while the DDA clause, after requiring
demand for arbitration to be made within 90 days, provided the
consequence of claim being deemed to have been waived and for
DDA to stand discharged of liability, clause 67 of NHAI contract,
after requiring for notice of intention to commence arbitration to be
given within 14 days, while in the case of recommendation having
been made by DRB provides the consequence of such
recommendation becoming final and binding, does not provide for
any consequence as of such claim being waived or extinguished or of
other party being discharged in the case of no recommendation
having been made by DRB, but only bars commencement of
arbitration without such notice.
19. We are in this concerned with the latter category of cases,
where no recommendation has been made by DRB on claims 18 to
24. The contract bars commencement of arbitration without notice
within agreed time.
20. What is to happen in such a case. Is the party who has failed
to give the notice and which under the contract is barred from
commencing arbitration, to institute a suit for adjudication of its
claims. If that were to be so, does it not vest a discretion in the party
to the contract to, if opting for arbitration, to give the notice and if
not, to avoid giving the notice. Further, what effect does such an
interpretation have on the efficacy of the arbitration agreement or
even the validity thereof.
21. In Wellington Associates Ltd Vs. Kirit Mehta AIR 2000 SC
1379, though exercising powers under Section 11 Arbitration Act, it
was said for an arbitration clause to constitute an arbitration
agreement within the meaning of Section 7, arbitration should be
agreed to be resorted to mandatorily and as a sole remedy, without
requiring any fresh consent of the parties. In the present case, in
the eventuality with which we are concerned, if the interpretation as
flowing from the impugned order is to be adopted, the party in the
case of no recommendation from DRB will have an option of
arbitration or civil suit as aforesaid. Of course if the option of
arbitration is exercised and notice within agreed time given, the
other party will mandatorily join in arbitration.
22. The Apex Court in Jagdish Chander Vs. Ramesh Chander
(2007) 5 SCC 719 also held that consensus ad idem to refer the
disputes to arbitration is required and not a mere hope to have
disputes settled by arbitration. The Division Bench of this court in
U.O.I. Vs. Bharat Engineering Corpn. ILR (1977) 2 Delhi 57 was
faced with a question, "can there be an "arbitration agreement"
which reserves the right of reference to only one party? Or, in other
words, which only one party can invoke?" Justice T.P.S. Chawla
concluded that the provisions of the 1940 Act did not visualize an
arbitration agreement which only one party can invoke and hence
that the law, neither Indian, nor English, nor American does not
contemplate an arbitration agreement which is contingent or
conditional or confers an option. There was thus held to be no
arbitration agreement where similar clause as in this case existed.
23. Another Full Bench of this court in Ved Prakash Mithal Vs.
U.O.I. AIR 1984 Delhi 325 was faced with a clause of arbitration of
administrative head of Chief Engineer of CPWD and further provided
that if for any reason that was not possible, the matter is not to be
referred to arbitration at all. The question arose whether in the face
of such agreement, the court was empowered to appoint the
arbitrator. The judgment of Division Bench in Bharat Engineering
Corp. (supra) was not cited before the Full Bench. The Full Bench
held that the purpose of Section 20 of the 1940 Act was to effectuate
the intention of the parties of arbitration of disputes and the parties
could not have agreed to exclude the power of court under Section
20.
24. I do not find any change in the 1996 Act to make the dicta of
Division Bench or Full Bench inapplicable. Read in that light, either
clause 67 which as aforesaid, read literally leaves discretion in party
to opt for either arbitration or civil suit has to be held to be not an
arbitration agreement as held by the Division Bench or has to be
given effect to. I find the latter of the two options to be more in
consonance with amended Section 28 of the Contract Act. The
requirement of giving notice of intention to arbitrate within 14 days,
else there will be no arbitration, restricts absolutely from enforcing
right under the contract by usual legal proceedings in the ordinary
tribunal, and/or limits the time within which rights may be enforced.
The words used are "ordinary tribunal" and not "ordinary courts".
So even though failure to give notice restricts right of arbitration
only and not right of approaching the court but the parties having
agreed to arbitration, the ordinary tribunal would be the arbitral
tribunal and not the court.
25. In U.O.I. Vs. M/s D.N. Revri AIR 1976 SC 2257 it was laid
down that a contract must be interpreted in such a manner as to give
efficacy to the contract rather than invalidate it.
26. In my view the intention of parties would be best served by
upholding the arbitration clause rather than derogating the same.
27. I have also wondered that if under the amended Section 28 of
the Contract Act, any clause of the contract barring arbitration
unless some step to commence arbitral proceeding is taken within a
time fixed by the agreement, is void, why Section 43(3) in the 1996
Act. Was the legislative intent to make the benefit of Section 28 of
Contract Act available in arbitration clause only on proof of hardship
and empower the court only to relieve against such forfeiture and
not allow the Arbitral Tribunal to apply Section 28.
28. In my view that could not be the legislative intent. The
proximity of dates of amendment to Section 28 of the Contract Act
notified on 8th January, 1997 and the 1996 Arbitration Act notified on
19th August, 1996 appears to be the reason. At the time of drafting
and notification of the 1996 Act the interpretation of law as under
the un-amended Section 28 of the Contract Act was in force and
Section 43(3) was intended to be a remedy therefor. However, after
the amendment of Section 28 of the Contract Act, the same has to be
given full effect by the Arbitral Tribunal also and without proof of
any hardship.
29. I may also notice the recent judgment of the Apex Court in P
Manohar Reddy Vs. Maharashtra Krishna Valley Dev. Corp
MANU/SC/8480/2008 relied upon by the counsel for the respondent.
In the said judgment, the Apex Court upheld a contractual clause
providing for limitation for the purposes of raising a claim and
further held the said clause to be not invalid. Reliance was placed
on Wild Life Institute of India (supra) which judgment as
aforesaid has been considered by this court in Pandit Construction
Company (supra) and held to be not considering the amendment to
Section 28 of the Act.
30. The counsel for the respondent also relied on Dr E
Muralidharan Vs. Venkataraman and Company 2006 (3)
Arbitration Law Reporter 477 Madras holding that the courts under
Section 43(3) can extend the time before referring the dispute to the
arbitrators or at least before the award is passed and not thereafter.
However, the senior counsel for the petitioner/appellant, in this
regard drew attention to a judgment of this court in National
Highways Authority of India Vs. PNC Construction Co Ltd 121
(2005) DLT 511 in which case the application under Section 43 (3)
was entertained during the pendency of the arbitration proceedings.
Reliance was also placed on Sterling General Insurance Company
Ltd Vs. Planters Airways Pvt Ltd AIR 1975 SC 415 and Bank of
Baroda Vs. Uttam Singh Dugal & Co. 17 (1980) DLT 265 on
undue hardship. Even though, I have held that Section 43(3) after
the amendment to Section 28 of the Contract Act is otiose but I may
mention that even otherwise in the facts of the present case, the
jurisdiction under Section 43(3) would have been exercised. The
facts set out show that the term of the DRB was being extended from
time to time beyond the first period of 56 days also. The
petitioner/appellant acted on respondent's representations that the
DRB was in session as borne out from the record and is therefore
estopped from averring that even though it had represented that the
DRB was in session but the time of 14 days for giving notice of
intention to arbitrator has expired. The respondent NHAI is
involved in large scale of activity of construction/development of the
highways in the country and is awarding a large number of
works/contracts. Clause 67 is a standard term of its contract. It
appears to have been felt and rightly so that before commencing
arbitration attempt should be made for mediation/conciliation. The
same is through constitution of DRB. Though DRB has been given a
time of 56 days to make the recommendation but the said time is
contractual and there is nothing preventing the parties from
extending the said time. Once the parties have represented to each
other that the said time has been extended, then the parties are
expected to act on the same and any other interpretation would be
negating the settlement machinery provided for in the agreement
itself. I thus find that the time of the DRB in the present case was
represented to be extended till 31st July, 2006. However, one cannot
lose sight of the notice dated 11th July, 2006 given by the respondent
communicating its decision for not agreeing to further extension of
time. The respondent is right in contending that the period of 14
days ought to have run not from 31st July, as contended by the
petitioner but upon receipt of its notice. On such calculation, the
petitioner did not give the notice within 14 days which ought to have
been given within 14 days of 11th July, 2006 i.e., by 25th July, 2006.
The notice was, however, given on 11th August, 2007. There was
thus a delay of 17 days in giving the notice. Since the parties had
been extending the time from time to time the time limit of 14 days
could not be of essence and no prejudice is shown to have been
suffered by respondent. Other claims of the petitioner/appellant are
stated to be pending adjudication before the Arbitral Tribunal and it
is just that all claims which would necessarily involve same question
of facts are decided together.
31. I, therefore, allow both the appeal and the OMP. The claims 18
to 24 of the petitioner against the respondent are held to be
arbitrable and the petitioner/appellants are entitled to have the same
adjudicated through the Arbitral Tribunal already constituted and to
whom the said claims were referred. However, in the facts and
circumstances aforesaid, the parties are left to bear their own costs.
RAJIV SAHAI ENDLAW (JUDGE) February 17, 2009 M
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!