Friday, 24, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Mcd vs Prabhat Construction
2009 Latest Caselaw 535 Del

Citation : 2009 Latest Caselaw 535 Del
Judgement Date : 13 February, 2009

Delhi High Court
Mcd vs Prabhat Construction on 13 February, 2009
Author: Shiv Narayan Dhingra
     *            IN THE HIGH COURT OF DELHI AT NEW DELHI

                                                     Date of Reserve: February 04, 2009
                                                        Date of Order: February 13, 2009

+ IA No. 8359/2007 in CS(OS) 228/2003
%                                                                  13.02.2009
      MCD                                                   ...Plaintiff
      Through: Mr. Uttam Dutt, Mr. Gaurang Kanth, Advocates

         Versus

         Prabhat Construction                                    ...Defendant
         Through: Mr. Raman Kapoor, Advocate

         JUSTICE SHIV NARAYAN DHINGRA

1.       Whether reporters of local papers may be allowed to see the judgment?

2.       To be referred to the reporter or not?

3.       Whether judgment should be reported in Digest?


         ORDER

IA No. 8359/2007

1. This application has been filed by the applicant for condonation of delay in

filing the award in the Court for making the same Rule of law.

2. The dispute between the parties was referred to the Arbitrator under old

Arbitration Act, 1940. The arbitration proceedings were started sometime in 1993 and

the Arbitrator gave its award in October 2002. After giving award, he wrote a letter to

the applicant/petitioner for publication of the award which was received by the

petitioner on 30th October 2004. Thereafter, the petitioner filed this award in the

Court on 24th January 2003 along with an application for condonation of delay as the

stipulated period for filing the award in the Court under Section 14 of the said Act is

30 days. This Court vide order dated 10th July 2007 observed that the only

submissions made in the application in paragraph 2 is a one line statement that

because of the departmental constraints, the application under Section 14 of the said

Act was filed with delay. The Court considered that this was no explanation and

dismissed the application. However, the counsel for the applicant/plaintiff sought

some time to examine the matter and to move an appropriate application within 15

CS (OS) 228/2003 MCD vs.Prabhat Construction Page 1 Of 3 days. This Court observed that in case no such application is made within 15 days,

the suit shall be dismissed and the objections filed by the respondent shall also stand

dismissed. The applicant filed fresh application for condonation of delay within 15

days giving detailed reasons as to why the delay occurred.

3. The non-applicant/respondent has taken the objection that the second

application under Section 5 of the Limitation Act would not lie as the first application

has already been dismissed and only an appeal would lie against the order of

dismissal of the first application. The order of this Court dated 10th July 2007 makes it

abundantly clear that the plaintiff/applicant was given a liberty to move a fresh

application within 15 days. If this liberty had not been given to the plaintiff/applicant

to move a fresh application within 15 days, the Court would have dismissed the suit

filed by the plaintiff under Section 14 and 17 of the said Act then and there and the

matter would have been set at rest. However, the very fact that this Court did not

dismiss the suit and gave 15 days time to the plaintiff/applicant to move a fresh

application under Section 5 of the Limitation Act, shows that although this Court while

passing earlier part of the order observed that the application was without merit as it

gave no explanation, but still in the later part, a liberty was granted to the

plaintiff/applicant to move fresh application.

4. It is settled law that an order has to be read as a whole and an order cannot

be read in piecemeal. If the order dated 10th July 2007 is read as a whole, it is

apparent that a liberty was given to the plaintiff to make a fresh application.

5. In the fresh application, the applicant has stated that the moment the award

was received, it was forwarded to the concerned department on 12 th November 2002

itself for contacting counsel for department for further action. A copy of the letter has

been placed on record. The applicant then sought opinion of MCD counsel regarding

action to be taken who gave his opinion that the application under Section 14 and 17

of the said Act for making the award a rule of court was to be moved immediately.

This opinion was given vide letter dated 22nd November 2002. Applicant's previous

CS (OS) 228/2003 MCD vs.Prabhat Construction Page 2 Of 3 counsel Mr. Sanjeev Jha then filed an application before the Tis Hazari Court for

making the award as a rule of court but since the pecuniary jurisdiction exceeded

Rs.5 lac, it was returned. To avoid any further delay, Executive Engineer requested

the same counsel to file an application before High Court and the same was filed on

24th January 2003 and he intimated to the Executive Engineer vide his letter dated

24th January 2003.

6. It is submitted that the post facto approval was obtained from Chief Law

Officer for filing this application before this Court. This shows that the department

wanted to avoid any further delay and was diligent in pursuing the matter.

7. The dispute in this case was arisen sometime in 1987 and was referred to the

Arbitration for adjudication in 1993. The Arbitrator took around 10 years for

adjudicating the matter and his award was received by the department/MCD. The

MCD was not that negligent that it delayed the matter for any unreasonable period.

Since MCD works in different manner and the sanctions are to be obtained from

senior officers, it takes time for obtaining sanctions. It is settled law that the matter

should not be dismissed merely on technical grounds and wherever reasonable

grounds are given, the court should condone the delay. There is no doubt that

Section 5 of the Limitation Act is applicable in this case but the delay in filing the

present suit has been sufficiently explained.

8. I allow this application under Section 5 of the Limitation Act. The application

stands disposed of.

CS(OS) 228/2003

List for further on 31st March, 2009.

February 13, 2009                                   SHIV NARAYAN DHINGRA J.
rd




CS (OS) 228/2003      MCD vs.Prabhat Construction                Page 3 Of 3
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter