Citation : 2009 Latest Caselaw 483 Del
Judgement Date : 11 February, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ Arb. Appl. No. 211/2008
*
%11.02.2009 Date of decision :11th February,2009
M/S. S.K. SHARMA ....Petitioner
Through: Mr. Vivekanand, Advocate
Versus
UNION OF INDIA & ORS. .... Respondents
Through: Ms. Geetanjali Mohan and Ms.
Vaishnavi, Advocates
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? YES
2. To be referred to the reporter or not? YES
3. Whether the judgment should be reported
in the Digest? YES
RAJIV SAHAI ENDLAW, J.
1. The question whether disputes/claims under an agreement
with respect whereto a receipt of full and final settlement has been
given or a settlement agreement has been signed, are arbitrable or
not has been repeatedly vexing the Courts. Two streams of
judgments/precedents exist. While one stream takes the view that a
claim for arbitration cannot be rejected merely or solely on the
ground that a settlement agreement or discharge voucher has been
executed by the claimant, if its validity is disputed by the claimant;
the other stream takes the view that upon performance/discharge,
the contract stands discharged and nothing remains neither any
right to sign performance nor any obligation to perform, resultantly
there cannot be any dispute and consequently there cannot obviously
be reference to arbitration of any dispute arising from a discharged
contract. Naturally, the two views are on distinguishable facts of
their respective cases.
2. I am, personally, of the view that a party to a contract
containing an arbitration agreement, when faced with a situation of
being required to sign a full and final discharge or a settlement
agreement, howsoever, economically coerced it may be, has two
choices. Either the party can at the cost of its economic detriment
and delay in receiving even admitted payments, to not succumb into
signing of such discharge or settlement agreement and ought to
invoke the arbitration process at that stage itself. In such a
situation, the remedy of seeking interim relief/directions from the
Court or from the Arbitral Tribunal of payment of admitted amounts
is available to such a party. Thus, though there may be delay in
receiving the admitted and/or offered amounts but it cannot be said
that the party is remediless. Alternatively, such a party can succumb
to the coercion, pressure and sign the discharge voucher and/or the
settlement agreement. It will then immediately receive the
offered/admitted amounts. Naturally when such a party makes
further claims, the other will set up a plea of the contract having
been discharged and no disputes or arbitration thereof thereunder
being possible. It is not as if the claimant party in such a situation is
remediless. The claimant party in such a situation has the option of
a civil suit available to it. In such civil suit, it will be decided
whether the discharge or settlement is legal or not. If not found to
be legal and valid, the same court would also adjudicate the
remaining claims of such party. The other party in such eventuality
would not be entitled to take the plea of the Court being not entitled
to adjudicate the claims for the reason of being covered by the
arbitration clause inasmuch as such party would have forfeited the
rights to take such a plea by contending that the contact stood
discharged.
3. In my view, once a discharged voucher or a full and final
receipt or a settlement agreement is signed, the same is novation,
rescission or alternation of the original contract between the parties
(within the meaning of Section 62 of the Contract Act) containing the
arbitration agreement. Such new contract unless itself containing an
agreement of arbitration, the claim/dispute thereunder that such
new contract is vitiated by fraud, undue influence, coercion can only
be adjudicated by a civil court and not under the arbitration
agreement under the original contract. Adjudication of such issues
of fraud, undue influence, coercion in the matter of novation,
rescission or alternation of the contract could not be within the
ambit of the arbitration agreement in the original agreement.
Section 62 of the Contract Act is clear in this regard. Where the
parties to a contract agree to submit to a new contract or to rescind
it or to alter it, the original contract need not to be performed.
Similarly, it is always open to the to the other party, if willing to
follow the dispute resolution mechanism of arbitration to always give
up the plea of the contract having been so discharged and to agree
on the arbitration. The other party in such case would be entitled to
contest the claim on the ground that the same was validly
settled/discharged and not rely merely on the written agreement of
discharge/settlement. However, if it does not choose to do so, it
cannot subsequently upon civil court finding the
discharge/settlement to be void for the reason of fraud, undue
influence or coercion, fall back on the arbitration clause and defeat
the claim on that ground.
4. The courts are inundated with applications under Section 11
(6) of the Arbitration Act which are being contested on such grounds
of full and final settlement/discharge/settlement. As per dicta in
SBP & Co. vs. Patel Engineering Ltd. 2005 (8) SCC 618, the Chief
Justice and/or his designate, when faced with such a plea has to
either a) adjudicate the said plea and i) upon finding the
discharge/settlement being under coercion or a result of undue
influence, appoint an arbitrator to go into the claims, or ii) upon
finding discharge/settlement to be not under coercion, undue
influence etc., dismiss/reject the application for appointment of
arbitrator OR b) leave the plea to be adjudicated fully and finally by
the arbitrators.
5. The adjudication under Section 11 (6) of the Act of such a plea
is likely to entail cross-examination of witness, thereby delaying the
possible arbitration proceeding. The courts thus have a tendency to
leave such questions to be decided in arbitration. The approach
suggested by me hereinabove, would obviate such delays/situations
inasmuch as the parties would have clarity that if they are signing or
insisting upon signing of such a discharge/settlement for immediate
benefits, they would subsequently not have the agreed remedy of
arbitration and will be open to the jurisdiction of the civil courts. If
such interpretation is followed, it will lead to clarity, and prevent the
parties from being subjected to arbitration after obtaining
documents of discharge/settlement. In such a situation, the law as
developed on Section 34 of the 1940 Act is applicable. It was held in
Narsingh Prasad Vs. Dhanraj Mills AIR1943 Pat 53 that where an
agreement is impeached on the grounds of fraud and as to the
factum or validity of contract, such a dispute does not fall under the
arbitration clause and should be decided by the court. So where
allegations of fraud and coercion in the matter of execution of
discharge/settlement agreement is averred, the same cannot possibly
be within the ambit of arbitration clause in the agreement which was
admittedly discharged/settled even if by fraud, misrepresentation or
coercion. Even otherwise it is settled position that the party against
whom averment of fraud/coercion is made has a right of having the
same adjudicated by court. See Abdul Kadir Vs. Madhav
Prabhakar AIR 1962 SC 406.
6. My view aforesaid is but a suggestion; otherwise, the recent
dicta of the Apex Court in National Insurance Co. Ltd. vs.
Boghara Polyfab Pvt. Ltd. MANU/SC/4056/2008 after noticing the
two streams of judgments aforesaid and after discussing most of
them, succinctly set out the law in para 19 of the judgment as
under:-
"19. We may next examine some related and incidental issues. Firstly, we may refer to the consequences of discharge of a contract. When a contract has been Page 4071 fully performed, there is a discharge of the contract by performance, and the contract comes to an end. In regard to such a discharged contract, nothing remains - neither any right to seek performance nor any obligation to perform. In short, there cannot be any dispute. Consequently, there cannot obviously be reference to arbitration of any dispute arising from a discharged contract. Whether the contract has been discharged by performance or not is a mixed question of fact and law, and if there is a dispute in regard to that question, that is arbitrable. But there is an exception. Where both parties to a contract confirm in writing that the contract has been fully and finally discharged by performance of all obligations and there are no outstanding claims or disputes, courts will not refer any subsequent claim or dispute to arbitration. Similarly,
where one of the parties to the contract issues a full and final discharge voucher (or no due certificate as the case may be) confirming that he has received the payment in full and final satisfaction of all claims, and he has no outstanding claim, that amounts to discharge of the contract by acceptance of performance and the party issuing the discharge voucher/certificate cannot thereafter make any fresh claim or revive any settled claim. Nor can he seek reference to arbitration in respect of any claim. When we refer to a discharge of contract by an agreement signed by both parties or by execution of a full and final discharge voucher/receipt by one of the parties, we refer to an agreement or discharge voucher which is validly and voluntarily executed. If the party who has executed the discharge agreement or discharge voucher, alleges that the execution of such discharge agreement or voucher was on account of fraud/coercion/undue influence practiced by the other party and is able to establish the same, then obviously the discharge of the contract by such agreement/voucher is rendered void and cannot be acted upon. Consequently, any dispute raised by such party would be arbitrable"
7. Having summarized the law as aforesaid, the Apex Court
noticed P.K. Ramaiah & Co. vs. Chairman & Managing Director,
NTPC 1994 Suppl (3) SCC 126, State of Maharashtra vs. Nav
Bharat Builders 1994 Suppl (3) SCC 83 and Nathani Steels Ltd.
vs. Associated Constructions 1995 Suppl. (3) SCC 324 in each of
which cases the Court held the claims to be not arbitrable. It was
found that in P.K. Ramaiah (supra) there was an unconditional
acknowledgment and acceptance and the same was sought to be
challenged and reference to arbitration sought after several years.
In Nav Bharat Builders (supra), it was found that upon claims
being raised a Committee had been constituted to examine the same
and the Committee had suggested acceptance of the claim subject to
certain terms; the contractor had agreed to accept the terms as
worked out by the Committee and thereafter accepted the monies
and agreed to withdraw the application filed under Section 20 of the
1940 Act. It was in these circumstances that a subsequent
contention that the letter was obtained by coercion was negated. In
Nathani Steels (supra), the settlement deed referred to prior
discussion between the parties and recorded the amicable settlement
in the presence of architect; in these circumstances, the contention
of the contractor that the settlement was liable to be set aside was
not accepted. It will therefore be seen that it was owing to the
aforesaid fact that the request for arbitration under the original
agreement was negated. It was further held that the observations in
Nathani Steels that "unless that settlement is set aside in proper
proceedings, it cannot lie in the mouth of one of the parties to the
settlement to spurn it on the ground that it was mistake and proceed
to invoke the arbitration clause" was in reference to the plea of
mistake and not with reference to allegations of fraud, undue
influence or coercion.
8. The Apex Court in Boghara Polyfab Pvt. Ltd (supra) also
noticed the other stream of judgments in Damodar Valley
Corporation vs. K.K. Kar MANU/SC/0026/1973, in Bharat Heavy
Electricals Ltd., Ranipur vs. Amar Nath Bhan Prakash
MANU/SC/0001/1980, in Union of India vs. L.K. Ahuja & Co.
MANU/SC/0544/1988, in Jayesh Engineering Works vs. New
India Assurance Co. Ltd. MANU/SC/1394/1999, in Chairman and
Managing Director, NTPC vs. Reshmi Constructions, Builders
& Contractors MANU/SC/0003/2004 and in Ambica Construction
vs. Union of India 2006 (13) SCC 475. In Damodar Valley
Corporation (supra) a full and final receipt was asked for but was
not submitted and thus it was held that the claims remained
arbitrable. In Bharat Heavy Electricals Ltd. (supra), the question
of full and final settlement was left for adjudication to the arbitrator.
In L.K. Ahuja & Co., the court did not find any full and final
discharge or accord or satisfaction. In Jayesh Engineering Works,
again the matter was left to be decided by the arbitrator. In Reshmi
Constructions, the contractor had on the same date as signing the
full and final settlement sent a letter to the effect that the same was
signed under threat and coercion; because of such conduct, it was
held that the arbitration under the original agreement was not
barred. Ambica Constructions merely followed Reshmi
Constructions.
9. The Apex Court thus in Boghara Polyfab Pvt. Ltd. concluded
that dependent upon the facts of each case and conduct of the
parties, it has to be determined whether the full and final settlement
discharges the arbitration agreement in the original contract or not.
The Apex Court further noticed that all the aforesaid cases were
under the 1940 Act and the perspective of the new Act was different
from the old act.
10. Under Section 16 of the new Act, the Arbitral Tribunal is
competent to rule on its own jurisdiction. The Apex Court further
noticed that in United India Insurance Co. Ltd. vs. Ajmer Singh
Cotton & General Mills MANU/SC/0463/1999, consumer
complaints were held maintainable even after signing of the
discharge voucher. The practice of obtaining undated receipts in
advance by the government departments and corporate sector was
also noticed. The Apex Court finally in para 28 set out illustrations
(though not exhaustive) as to when in spite of discharge of contract
the claims would be arbitrable and when they would be not.
11. Before proceeding to the facts of the present case, I may also
notice the recent judgment of the Division Bench of this Court in
Harivansh Chawla Vs. Prem Kumar Cooperative Group
Housing Society Ltd. ILR (2008) II Delhi 1295; in that case a plea
for arbitration was negated after full and final settlement. I may
further notice that in that case there was no case of any coercion,
undue influence, etc.
12. The petitioner in the present case was awarded works contract
on 13th September, 2002, the scheduled date of completion whereof
was 12th December, 2003. The petitioner contended that for reasons
attributable to the respondent Railways, the work could not be
completed in time and for this reason the time for competition was
extended from time to time without any penalty till 31st March, 2006
by which date the works were completed. Attention was drawn to
letter dated 28th May, 2004 of the petitioner to the respondent
Railways whereunder the respondent Railways were notified of all
the additional claims of the petitioner for the reason of delays
attributable to the respondent. It was pleaded that the defect
liability period of six months also expired satisfactorily without any
complaint, by 30th September, 2006 whereafter the petitioner
requested the respondent to release the security deposit with full
and final payments; that the respondent ultimately prepared a final
bill and called the petitioner for signing the same; however, the bills
proposed did not include all the payments to which the claimant was
entitled and even the escalation already paid was proposed to be
withheld/recovered in the final bill. It is averred that the petitioner
thus signed the proposed final bill under protest. Significantly, this
fact was admitted by the counsel for the respondent during the
hearing.
13. It is further averred that since applicant signed the final bill
under protest, the respondent wanted the applicant to sign blank
formats and bill forms as condition precedent for processing of the
release of the bank guarantees of Rs. 15 lacs and cash security
deposit as well as the payments under the proposed final bill to the
tune of about Rs. 12 lacs. The petitioner claims that he refused to do
so leading the respondents into invoking the bank guarantees even
though there were no claims of the respondents against the
petitioner and defect liability period was also over. The petitioner
has averred that faced with the threat of payments under the bank
guarantees being made, the petitioner had no option but to sign the
blank formats and bill formats. The petitioner has specifically
averred that had he at that time taken recourse to arbitration and
other proceedings, the payment under the bank guarantees would
have been made and he would have been deprived of the sum of Rs.
12 lacs also being offered by the respondents against the final bill.
The petitioner thus admits to have signed the blank cyclostyled
formats and bill formats and whereafter the respondents withdrew
the invocation of encashment of bank guarantees and released the
bank guarantees in favour of the petitioner and also made payments
of Rs. 12 lacs towards final bill in May, 2006.
14. The petitioner thereafter vide letter dated 27th June 2007
invoked the arbitration clause for its claims against the respondents.
The respondents after several reminders ultimately vide letter dated
24th December, 2007 refused appointment of arbitrator for the
reason of the petitioner having signed a supplementary agreement.
The petitioner thereafter filed the present petition.
15. The respondents file a counter affidavit to the petition,
generally denying each and every averment in the petition and
further stating that the petition did not require reply on merits. It
was pleaded that the parties had entered into a supplementary
agreement dated 7th April, 2007 which stipulated that in
consideration of the sums already paid by the respondents to the
petitioner against all outstanding dues and claims for all works done,
the principle agreement stood discharged in toto including the
arbitration clause. It was thus pleaded that the petitioner was not
entitled to invoke the arbitration clause. Reliance in this regard was
placed on judgment dated 7th December, 1984 of this Court in
Sarvesh Chopra vs. UOI.
16. The petitioner has along with the petition filed copy of letter
dated 12th April, 2007 of the respondent Railways releasing the bank
guarantees and withdrawing the earlier letters dated 19th January,
2007 and 20th March, 2007 for encashment of bank guarantees and
requesting the bank to release the bank guarantees in favour of the
petitioner. The petitioner has also filed photo copies of the cheques
dated 31st March, 2007 for Rs. 10,23,860/- and dated 11th April, 2007
of Rs. 51,122/- in favour of the petitioner.
17. The photocopy of the settlement agreement has been filed by
the respondents along with their counter affidavit. The same is in
cyclostyle form with blanks filled in hand. The date thereof has been
filled up in hand as 7th April, 2007. The petitioner does not dispute
his signatures on the same on both the pages thereof. The
signatures on both the pages bear the date 31st March, 2007
underneath. The signatures on behalf of the respondents are of 4th
April, 2007 and the witness on behalf of the respondents has signed
on 7th May, 2007. Though the names of the witnesses on behalf of the
petitioner are not decipherable but they appear to be officials of the
respondent only.
18. It is in the aforesaid state of facts, that the law as summarized
in Boghara Polyfab Pvt. Ltd. has to be applied. For the following
reasons:-
a. The signatures of the petitioner bearing the date 31st March , 2007 and the settlement agreement bearing the date 7th April, 2007 and which shows the same to be signed in advance, as pleaded by petitioner.
b. The payments under the final bill having been released to the petitioner on 31st March, 2007 vide cheques aforesaid and which falsify the statement in settlement agreement of all payments having been made prior thereto.
c. The witnesses to the settlement agreement being officials of the respondent only and which again show lack of mutuality, discussion prior to signing thereof.
d. The settlement agreement records payments having being made which admittedly were made thereafter.
e. The factum of invocation of bank guarantees and withdrawal of the said invocation after the signing of the settlement agreement by the respondents.
f. No reason having been given as to why the bank guarantees were invoked and which invocation was subsequently withdrawn and which show coercion exercised by the respondent Railways.
g. The detail pleas of the petitioner of circumstances leading him to sign the settlement agreement in blank having not been controverted;
I am prima facie of the view that the present case does not fall
in the class of cases as P.K. Ramaiah, Nav Bharat Builders,
Harivansh Chawla and Nathani Steels Ltd. and rather falls in the
class of cases as in Reshmi Constructions. The settlement
agreement appears to have been signed under coercion, meaning
that the claims shall remain arbitrable under the original agreement.
19. I, however, at this stage do not deem it appropriate to return a
positive finding on this aspect. In my view a positive binding finding
on the averments of coercion, undue influence, etc. in the face of a
written document ought not to be returned without examination of
witnesses. Though it is permissible to examine witnesses while
adjudicating an application under Section 11(6) of the Act but in my
view if the said exercise is undertaken here, the same will lead to
further delays. The parties having agreed to arbitration, it is
apposite that the said claims/disputes are also adjudicated by the
arbitrator only. Another single judge of this court recently in M/s
Hero Exports Vs. M/s Tiffins Barytes, A.A No.121/2008 decided
on 2nd September, 2008 left the questions of coercion and extortion
to be decided by arbitrator.
20. The next question to be considered is of the relief to be
granted. I have recently had occasion to consider Clause 64 of the
Railways Contract as in the present case in M/s. S.B. Construction
vs. General Manager, Northern Railway & Anr. AA 467/2007
decided on 27th January, 2009. The agreed procedure for arbitration
where claims are in excess of Rs. 10 lacs, as they are in the present
case is of the respondent Railways sending a panel of not more than
three gazetted railway officers to the petitioner and the petitioner
suggesting up to two names out of the said panel for appointment as
his nominees. The General Manager is to appoint one at least out of
them as the Contractor's nominee and to appoint the balance
number of arbitrators either from the panel or from outside the panel
and also indicating the presiding arbitrator.
21. The respondent having failed to act as required under the
procedure, has forfeited the right to do so as laid down in Datar
Switchgears Ltd. vs. Tata Finance Ltd. 2000 (8) SCC 151.
However, even though the respondent has failed to act but
considering the arbitration agreement between the parties, the
petitioner is not entitled to appointment of an independent
arbitrator. The Apex court in Northern Railway Administration,
Ministry of Railways; New Delhi vs. Patel Engineering
Company Ltd. VII 2008 SLT 432 has held that the Court as the
nominee of the Chief Justice, under Section 11 (8) of the Act is to
give due regard to any qualification required of the arbitrator by the
agreement of the parties and other considerations as are likely to
secure the appointment of an independent and impartial arbitrator.
22. The parties had agreed to a qualification of the arbitral
tribunal. It was agreed that the arbitral tribunal shall comprise of
gazetted railways officers not below JA grade and of whom at least
one shall be from the accounts department. Harmonizing the law
laid down in Datar Switchgears with Northern Railway
Administration, in my view, even upon the failure of the respondent
as aforesaid, the arbitrators having the agreed qualification only can
be appointed by this Court. The only effect of the respondent
Railways having forfeited the right to appoint two out of the three
arbitrators would be that instead of the respondent Railways being
entitled to nominate two out of the three arbitrators, it is the
petitioner who would be entitled to nominate all the three arbitrators
and to also designate one as the presiding arbitrator, however all
having the qualification agreed.
23. Accordingly, it is directed that upon the petitioner intimating
to the respondent Railways three arbitrators having the
qualifications as agreed under Clause 64, the respondent Railways
shall constitute the Arbitral Tribunal which shall go into claims and
counter claims, if any, of the parties in accordance with law.
24. With these directions, the petition is allowed leaving the
parties to bear their own costs.
RAJIV SAHAI ENDLAW (JUDGE) February 11, 2009 rb
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!