Citation : 2009 Latest Caselaw 5292 Del
Judgement Date : 18 December, 2009
* HIGH COURT OF DELHI : NEW DELHI
Judgment reserved on : December 10, 2009
Judgment delivered on : December 18, 2009
+ F.A.O. (OS) No. 612/2009
% M/s. Sukumar Chand Jain ... Appellant
Through: Mr. Sandeep Sharma, Advocate.
versus
Rail Vihar Sehkari Avas Samiti Ltd. ... Respondent
Through: Nemo.
CORAM:
HON'BLE MR. JUSTICE VIKRAMAJIT SEN
HON'BLE MR. JUSTICE SUNIL GAUR
1. Whether the Reporters of local
papers may be allowed to see
the judgment?
2. To be referred to Reporter or not?
3. Whether the judgment should be
reported in the Digest?
SUNIL GAUR, J.
1. The Respondent-Society invited tender for the execution of the
"Development of Housing Site (laying of sewerage system) at
Sadaullabad, Loni, District Ghaziabad (U.P.). Appellant-Firm of
Engineers and Contractor (said to be engaged in doing construction
work) was awarded the work of laying of sewerage system as
aforesaid in December, 1996. The stipulated date for completion of
the aforesaid work was 3rd July, 1997. It is the precise case of the
Appellant that during the abovesaid contractual period, no substantial
F.A.O. (OS) No. 612/2009 Page 1 work could be executed and in this regard, correspondence was
exchanged between the parties and in the meanwhile, the cost of
construction increased tremendously. Appellant claims that the
construction of the septic tank was stopped by the Secretary of the
Respondent-Society. Since dispute between the parties in this matter
arose, statement of claim was made by the Appellant before the
Arbitrator, which was contested by the Respondent and the Arbitral
Proceedings resulted into an Award of 5th December, 2009.
2. Appellant had preferred objections under Section 34 of the
Arbitration & Conciliation Act, 1996 against this Award, which have
been dismissed in limini by the learned Single Judge vide impugned
order of November 09, 2009.
3. Sole Arbitrator has awarded a sum of Rs.3,46,624/- with
pendentelite interest at the rate of 18% per annum in favour of the
Claimant/Appellant. The objection of the Appellant to the aforesaid
award of 5th October, 2009 pertained to Claim No.1, 4 and 6. Claim
No.1 relates to payment for the work done by Appellant/Contractor.
Out of the ten running bills, payment for the 9th running bill has been
granted to the Appellant as this bill was verified by the Respondent.
For the remaining running bills, payment to the Appellant has been
declined by the Arbitrator as well as by the learned Single Judge
because the remaining running bills were not verified by the
Respondent. In fact, the main reason for declining the payment of the F.A.O. (OS) No. 612/2009 Page 2 remaining nine running bills to the Appellant was that the
measurement book to support these bills was not produced before
the Arbitrator. Learned Single Judge in the impugned order has
rightly relied upon Section 114 of the Evidence Act to draw an
adverse inference against the Appellant for not producing the
measurement book before the Arbitrator. In this appeal, learned
counsel for the Appellant has not been able to justify the non-
production of the measurement book. What has been emphasized by
the learned counsel for the Appellant is that even the remaining
running bills were verified by the Respondent. This aspect pertains to
the merits of the claim. Although, we are not required to go into this
aspect, but it needs to be noted that because Counsel for the
Respondent could not give the clarification to the Arbitrator regarding
the 9th running bill, therefore, the payment of this bill has been
awarded to the Appellant.
4. Claim No.4 related to interest for delayed payments. It has
been noticed by the learned Single Judge in the impugned order that
non-filing of the measurement book was the reason for the delay in
making the payment. For this, the Appellant is to be blamed.
Appellant has been rightly denied the interest on the delayed
payment by the Arbitrator and the learned Single Judge has correctly
not found any merit in the objection against denial of Claim No.4 by
the Arbitrator.
F.A.O. (OS) No. 612/2009 Page 3
5. Claim No.6 relates to infructuous expenditure, i.e., on account
of labour of the Appellant remaining idle. This claim has been
disallowed by the Arbitrator, as it was found that the letters relied
upon by the Appellant in respect of this claim were of no help and the
bills in question did show that the work was being done and in that
situation, Appellant/claimant was compensated on account of loss of
profit.
6. The challenge to an Award under Section 34 of the Arbitration
& Conciliation Act, 1996 can be on limited grounds, as provided in
Section 34 itself.
7. In Fiza Developers and Inter-Trade Pvt. Ltd. Vs. AMCI (I) Pvt.
Ltd. & Anr. 2009 (1) SCALE 371, Apex Court has reiterated the scope
of Section 34 of Arbitration and Conciliation Act, 1996, in these
words:-
"The grounds for setting aside the award are specific. Therefore necessarily a Petitioner who files an application will have to plead the facts necessary to make out the ingredients of any of the grounds mentioned in sub-section (2) and prove the same. Therefore, the only question that arises in an application under section 34 of the Act is whether the award requires to be set aside on any of the specified grounds in sub-section (2) thereof. Sub Section (2) also clearly places the burden of proof on the person who makes the application."
8. It is neither stated in the appeal nor it was pointed out by
counsel for the Appellant during the course of the arguments as to
under which sub-section of Section 34, the case of the Appellant falls.
F.A.O. (OS) No. 612/2009 Page 4 In fact, the Award in question is neither patently illegal nor is against
the public policy and is not covered by any of the grounds of
challenge as provided under Section 34 of the Arbitration &
Conciliation Act, 1996. The learned Single Judge has correctly, in our
opinion, not acted as a Court of Appeal and we find that the reliance
placed by the learned counsel for the Appellant upon Oil & Natural
Gas Corporation Ltd. vs. Saw Pipes Ltd., (2003) 5 SCC 575 is
misplaced.
9. In the light of the aforesaid, impugned order cannot be faulted
with. Learned Single Judge was justified in dismissing the objections
of the Appellant but the costs imposed while doing so, appears to be
on the higher side. We think it appropriate to reduce the costs from
Rs.50,000/- to Rs.20,000/- and modify the directions issued by the
learned Single Judge in this regard. Appellant is granted two weeks
time to deposit the reduced costs of Rs.20,000/- with the Registrar
General of this Court, who shall ensure that it is sent to the Prime
Minister Relief Fund.
10. With aforesaid modification, this appeal is dismissed in limini.
Sunil Gaur, J.
Vikramajit Sen, J.
December 18, 2009 pkb F.A.O. (OS) No. 612/2009 Page 5
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!