Citation : 2009 Latest Caselaw 5021 Del
Judgement Date : 7 December, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
CS(OS) NO. 2461/1997
07th December, 2009
M/S GOOD VALUE ENGINEERS ...Petitioner
Through: Ms. Jaya Tomar, Advocate
VERSUS
1. M.M.S.NANDA, SOLE ARBITRATOR
2. UNION OF INDIA. .....Respondents
Through: Mr. Sachin Dutta, Advocate. CORAM: HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
% JUDGMENT (ORAL) VALMIKI J.MEHTA, J I.A No. 8922/1998 in CS(OS) No. 2461/1997
1. These are the objections of the respondent under Sections 30 and 33 of
the Arbitration Act, 1940. The challenge by means of these objections is with
respect to claim nos. 1,4,5,6,7,8,9 and 12 besides the issue of interest granted
by the Award at the rate of 15% per annum.
CS(OS) 2461/1997 Page 1
2. One common finding which runs through the entire Award and which I
will be referring to is that the disputes centres around what was the extent of soft
soil, hard soil or hard rock at the site. This is relevant because the cost for
excavation of hard rock is obviously more than the excavation of hard soil or
soft soil. Further, if there is a rate given in the contract for excavation of soft
soil which is lesser and excavation is done on hard rock for which the rate is
higher then the deviation order based on the rates of the hard soil/soft soil in the
contract would obviously not be much relevant to determine the rates of
payment for hard rock. With respect to each of the claims, the Arbitrator after
arriving at a finding that the hard rock was approximately 95% has however
awarded compensation to the contractor not at the figure of 95% but only at the
figure of 87%. The basic grievance of the Union of India is that hard rock
should have been taken only at 78% and not at 87%. The difference is therefore
only of 9%. With this prorogue, I am taking up each of the claims as argued by
the counsel for the objector one by one.
3. The first challenge is to Claim no.1. Under this claim, the claimant
claimed an amount of Rs.45,974/- towards excavation of hard rock in the
foundations. The Arbitrator after considering the different contentions of the
parties has narrated in para 13.6 the facts as urged by the contractor and on the
basis of which he has awarded the claim under this head. This para 13.6 reads
as under:-
CS(OS) 2461/1997 Page 2
"13.6 The claimant brought out that on page 86 of MB No. 448 in
add portion the excavation in the foundation has been indicated in soft rock whereas at site hard rock was met with. The claimant referred item No.3 on page 87 of MB No 448 and item No.3 on page No.1 of MB No 11 the excavation has been shown as hard rock whereas while preparing DO No 15 the excavation has been considered in hard soil. The claimant further referred item No.4 and item No.5 on page 75 and 76 of MB No. 448 the width of foundation has been shown as 0.98 meter as against 1.03 m for the building walls and .68 meter against 0.98 for dwarf wall. The drawing for the foundation was supplied by the department and claimant produced, it is seen on the perusal of MB No. 448 on pages 75 & 76 only one step has been considered in the wall foundation as against 3 Nos given on the drawing and actually executed at site." (Emphasis added)
In view of the aforesaid para, it becomes clear that the MB(Measurement
Book) did not record the correct measurements at different places.
Simultaneously, the Arbitrator has not accepted the hard rock percentage at 95%
as found or 78% as claimed by the objector. The Arbitrator has resorted to
honest guess work after duly considering the various facts, evidence and
circumstances as narrated in this part of the Award pertaining to Claim no.1, and
which is also the golden thread otherwise running through each of the claims
awarded. I do not find any perversity or unreasonableness whatsoever in the
actions of the Arbitrator, in that, it can be said that the Arbitrator has
misconducted himself or the proceedings by making an honest guess work. It is
settled law and so held right since Mohd. Salamatullah vs. State of A.P. AIR
1977 SC 1481 that an Arbitrator is wholly justified once there are some
materials on record to make honest guess work on the basis of the same. This
view of the Supreme Court was further reiterated by it in the case of M/s A.T
Brij Paul Singh Vs. State of Gujrat AIR1984 SC 1703. There are also other
similar judgments holding that the Arbitrator is entitled to arrive at a finding CS(OS) 2461/1997 Page 3 of fact which may not be perfect to the extent of being tested on a golden scale.
In fact, the Arbitrator in my opinion has been very reasonable because he has
not accepted the hard rock at 95%, although he has found it to be so, but has
only awarded cost for excavation at 87%. I do not therefore, find that the
Arbitrator has misconducted himself or the proceedings while allowing this
claim.
4. The next claim which was argued was Claim no.4, which I may very
sarcastically add is for „huge‟ amount of Rs.4410/-. I fail to understand as to
how the time of this court can indeed be wasted by such objections which seem
to be taken by Union of India and other authorities in routine. I need not say
further on this claim except that I find that the same basis which was applied of
the hard rock being at 87% has been taken as the basis for awarding this claim
of Rs.4410 and I do not find any misconduct of the Arbitrator in this regard.
The objection against this claim is therefore dismissed.
5. Claim no. 5 urged before the Arbitrator pertains to excavation work with
respect to making of a drain. I again need say no further except that once again
as stated above the Arbitrator has awarded hard rock excavation at 87%. The
counsel for the objector has contended that whereas the claim was only of
Rs.37,344/-, the Arbitrator has awarded Rs.40,780/- and therefore the Arbitrator
has misconducted himself. This contention is in my opinion baseless for two
reasons. Firstly, during the conduct of the proceedings, although a different
figure may have been initially stated in the statement of claim, it may thereafter
CS(OS) 2461/1997 Page 4 transpire that actual work and the entitlement or actual rate arrived at by the
Arbitrator may entitle a person to a higher amount than as claimed and the
Arbitrator cannot be said to have committed any illegality because such a course
is even permissible to a Civil Court under Order 7 Rule 7 of the Code of Civil
Procedure, 1908. In fact the Arbitrator is not even bound by the technicalities of
pleadings as provided in the CPC, but the CPC itself entitles the Arbitrator as
per Order 7 Rule 7 to take the course he has taken. In this case, in any case,
there is not too much of difference and the difference is only of about Rs.3000/-.
I may note that there is a valid basis for increase of this figure inasmuch as the
counsel for the non-objector has drawn my attention to the fact that the figure of
Rs.37,340/- has gone up to Rs.40,780/- because the latter figure includes the
claim of escalation. In view of the aforesaid, I do not find that the Arbitrator
has at all misconducted himself while awarding amount under Claim no.5.
6. The next claim which has been objected to is Claim No.6. While dealing
with Claim no.6, the Arbitrator has given the following observations in para
18.3 of the Award and which runs as under:-
"18.3 The claimant argued that actual excavation has been done in the hard rock whereas department has considered 100% hard soil. The claimant produced page 14 of MB No. 11. The respondent has depicted the area as rocky but item shown there is in hard soil. If area is rocky, the question of excavation in hard soil does not arise. The claimant further referred schemetic representation of Road near static tank in MB No. 11 page 12 is not true representation of road, it is seen that width of road has not been correctly taken by respondent thus actual work done by the claimant stands reduced substantially." (Emphasis added)
CS(OS) 2461/1997 Page 5 Once again the Arbitrator has referred to the mistake apparent from the
measurement book and therefore the Arbitrator has resorted to the honest guess
work of the figure of 87% for hard rock excavation. In view of my discussion
with respect to Claim no.1, I do not again find any fault with respect to
awarding of this claim.
7. Claim no. 7 is the major claim and which has been awarded by the
Arbitrator for a sum of Rs.16,28,707/-. The claim under this head has three sub-
heads. The first sub-head is once again as to the percentage of the hard rock.
The second sub-head is with respect to the depth of the excavation and the third
sub-head is for the area of jungle clearance.
The Arbitrator has in this regard, held in para 19.8 as under:
"19.8 Keeping in view of above para discussed, statement of claims, pleading in defence and examining the submissions by both the parties I hold that:-
(a) Lease element of hard rock has been considered by the respondent. The respondent confirmed at site @ 95% hard rock and claimant 100% rock however I consider 87% hard rock and 13% hard soil.
(b) The respondent has considered excavation upto 1.5 meter depth and recorded in MB. In add back DO No 3 excavation upto 6 meter has been considered by the respondent and work done at site is as per scope of work given in DO No 3 and has not been denied by the respondent. The claimant is entitled upto depth of 6 meters. I consider the excavation actually done at site is to be paid to the claimant.
(c) The rates of item 5 of Sch A section VII jungle clearance accepted by the Accepting Officer is frequently high ie. Rs 18 per sq. m. and no restriction has been imposed by increasing the quantity if required. The amendment No.1 issued by jungle clearance at the rate of Rs.1.80 per sq. me for 100 sq meter only. Whereas the extent of work done is 6962 sq. meter against 100 sq meter. Thus quantity of work got executed is abnormally high as specified in contract agreement. After visit of site I consider Rs 6/- per sq. meter including %age quoted by the contractor is reasonable for the balance quantity."
CS(OS) 2461/1997 Page 6 So far as sub para (a) of para 19.8 above is concerned once again the same is on
the basis of 87% hard rock excavation and which I have repeatedly referred to
while dealing with earlier claims. So far as the depth of excavation is concerned,
I note that the Arbitrator has correctly noted that the deviation work order itself
mentions for excavation up to 6 metres and therefore the Arbitrator has
accordingly awarded excavation up to a depth of 6 metres and not 1.5 metres as
recorded in the MB. In order to appreciate as to how exc19avation charges for a
greater depth is awarded, I must at this stage, refer to paras 19.6 and 19.7 of the
Award which are the precursors to the conclusions given in paragraph 19.8. The
said paras 19.6 and 19.7 read as under;
"19.6 The claimant referred page 46 of MB No. 11, the formation level of the radar platform has been shown as 333.15 as against 333.10. Similarly, in different parts of radar platform different formation levels have been considered. The claimant referred drawing No. S/RP-1 forming part of CA, the final level of radar platform was fixed as 333.50. Out of that 15 cm is WBM and 25 cm is RCC of top of WBM which clearly explains that the formation of radar platform was to be kept 333.10. To substantiate his argument he referred para 2(e) of GEs letter No. 8015/RCP/134/E8 dt. 28th December, 1993. The claimant further argued that place where the radar platform has been built was the highest feature on the ground in the general area consisting of 100% rock and whole of platform was brought to one level i.e. 333.10. Thus respondent has reduced the actual work done by considering different level of formation on radar platform and also increasing formation level to 333.25.
19.7 The claimant further brought out while referring page 46 to page 50 of MB No. 11, the reading have been altered by overwriting and erasing the old reading with the intention to cause loss to the claimant. Referring page No. 47 of MB No. 11 the respondent has considered initial and final level as 00 with a view to reduce the work done. Left side of radar platform, the final levels have not been considered for computing the volume in cutting and also large number of triangles have been omitted on both side of radar platform thereby reducing the volume of work done."
CS(OS) 2461/1997 Page 7
8. It is quite clear that the aforesaid paras clearly show that the
claimant/non-objector not only caused the unnecessary levelling of the platform
which was made of total rock, the claimant in fact brought out as to how volume
of work was wrongly reduced. The Arbitrator has further also noted that there
are over writings and erasing of the old readings in the MB. After recording the
aforesaid facts, the Arbitrator arrived at the conclusion with respect to the depth
as stated in para 19.8 (b). Surely, this was one plausible view which the
Arbitrator was entitled to take from the facts which were found by him on
account of the actual work done at site by the non-objector and also the
discrepancies and alterations in the measurement book. In my opinion,
therefore no fault can be found with regard to the conclusion in para 19.8 (b).
9. As regards the third sub-head with respect to awarding of the rate of
jungle clearance at Rs.6 per sq. m instead of Rs.1.80 per sq. m. I may note that
counsel for the objector vehemently contended that there was initially a
typographical mistake in the contract and the rate of jungle clearance was in fact
Rs. 18 per ten sq. m. In my opinion this argument is of no consequence because
the contractual rate will only apply to the contractual area. When the actual area
goes way- way beyond the contractual area, the contractor is not bound by the
contractual rate. In this case, the contractual extended area was 100 sq. m but
the arbitrator notes that the jungle clearance was done for 6962 sq. metres
instead of Rs.100 sq. m. The Arbitrator has thereafter made an honest guess
work and increased the rate to Rs.6 per sq. mt. I have already referred to the
CS(OS) 2461/1997 Page 8 judgments in the case of Mohd. Salamatullah(supra) and M/s A.T Brij
Paul(supra), and I am of the view that the Arbitrator was fully justified, once
certain material was available before him, to resort to making an honest
guesstimate to award a particular rate for jungle clearance once the area of
jungle clearance exceeded well beyond the contractual amendment area which
was prescribed under the contract.
10. The next claim which was objected to was Claim no.9 pertaining to the
work done towards concreting etc. The basic contention of the contractor in
this regard was that whereas he has done M-20 concreting work but the
objector has given it a rate which is lesser even than the M-15 rate as stated in
the contract document.
The relevant paragraphs pertaining to this claim are paragraphs 21.3 and
21.4 which reads as under:
"21.3 The respondent further brought out that quantities of items shown in Appendix I are not supported with measurement details. The respondent submitted that star rate for M-20 grade design mix concrete as worked by the department is Rs. 1564.37 per Cum. The claimant vide his letter No. 003/23/GV/TR dt. 31.5.94 (Exhibit 7 of claimant contractor) stated that the actual rate of M-20 concrete works out to Rs. 3700/- per Cum and has now made out a rate of 2614.98 Cum and is not agreed to.
21.4 The claimant brought out that star rates forwarded by AGE (B/R) letter No. 807/RCP/BR/367/E8 dt. 3rd August, 95--one year three month after completion of concreting and six months after completion of work the rate for M-20 concrete was even lower than the rate of M-15 concrete in CA. This was not agreed and DO was signed under protest. In addition railing was provided around the radar platform have not been accounted properly. A dwarf wall was constructed around platform has also not been recorded."
CS(OS) 2461/1997 Page 9 Accordingly, in view of the aforesaid discussion, I am not persuaded to
interfere with respect to this finding as I do not feel that the Arbitrator has
misconducted himself or the proceedings.
11. Claim No.12 is only for an amount of RS.14,580. This is a claim for
transportation because according to the contractor it transported the cement bags
from different locations than as was envisaged in the contract resulting in higher
cost. I do not think that for this amount of Rs.14,580/- I need spend much time
because the Arbitrator has given a finding of fact with respect to the different
locations from where the cement bags were taken up than as specified in the
contract. Accordingly, no challenge can be led with respect to this claim.
12. That takes me to the last issue of the rate of interest which has been given
under the Award. The Supreme Court in the recent catena of judgments
reported as Rajendra Construction Co. Vs. Maharashtra Housing & Area
Development Authority & ors.2005 (6) 678, McDermott International Inc. Vs.
Burn Standard Co. Ltd.& ors 2006 (11) SCC 181, Rajasthan State Road
Transport Corpn. Vs. Indag Rubber Ltd. (2006) 7 SCC 700 and Krishna
Bhagya Jala Nigam Ltd. Vs. G.Harischandra, 2007 (2) SCC 720 and State of
Rajasthan vs. Ferro Concrete Construction Pvt. Ltd (2009) 3 Arb. LR 140(SC)
has held that the courts in accordance with the changed economic scenario and
the liberalization of the interest regime, which has resulted in the consistent fall
in the rates of interest, must grant the lower rate of interest instead of high rate
of interest as granted by the Award. The Supreme Court has also mandated the
CS(OS) 2461/1997 Page 10 courts to take notice of the fact that lower rate of interest must be granted more
so if the Arbitration proceedings and the objections before the court are pending
for a long time. In the present case, the Award is of more than 12 years back
and the objections are also pending since more than 11 years, therefore, in
accordance with the mandate of the Supreme Court judgments, I award interest
at the rate of 9% per annum simple. Therefore, wherever interest is granted at
15% per annum in the Award, the same shall be read as 9% per annum simple.
However, I am not changing the date from which the interest has been granted.
13. Though, I have reduced the rate of interest and which is because of the
mandate of the Supreme Court judgments, I find that the objections, in this case
were totally misconceived. If these objections were decided in the year of their
filing i.e in the year 1998, the rate of interest need not have been at 9% per
annum simple. I therefore, hold that the non-objector is to be compensated for
the costs which he has incurred. Accordingly, the objections are dismissed with
costs quantified at Rs.25,000/-. Let the Award be made a rule of the court
subject to the modification in the rate of interest from 15% to 9% simple.
14. With these observations, the objection petition and the suit stands
disposed of.
DECEMBER 07, 2009 VALMIKI J.MEHTA, J Ne/ib CS(OS) 2461/1997 Page 11
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!