Thursday, 23, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

I.T.I. Limited vs Par Pressings & Anr.
2009 Latest Caselaw 4978 Del

Citation : 2009 Latest Caselaw 4978 Del
Judgement Date : 4 December, 2009

Delhi High Court
I.T.I. Limited vs Par Pressings & Anr. on 4 December, 2009
Author: Vipin Sanghi
*            IN THE HIGH COURT OF DELHI AT NEW DELHI

                 Judgment reserved on:      24.04.2009
%                Judgment delivered on:     04.12.2009

+                        O.M.P. No.214/2000

      I.T.I. LIMITED                                  ..... Appellant
                        Through:    Mr. Dayan Krishnan with Mr.
                                    Gautam Narayan and Mr. Mahfooz
                                    Nazici, Advocates.

                              Versus

      PAR PRESSINGS & ANR.                            ....Respondents
                     Through:       Mr. C. Mukund with Mr. Ashok Jain
                                    and Mr. Pankaj Jain, Advocates.

CORAM:
HON'BLE MR. JUSTICE VIPIN SANGHI

1.    Whether the Reporters of local papers may        No
      be allowed to see the judgment?

2.    To be referred to Reporter or not?               Yes

3.    Whether the judgment should be reported          Yes
      in the Digest?


VIPIN SANGHI, J.

1. By this order I propose to dispose of the objections under

Section 34 of the Arbitration and Conciliation Act, 1996 (the Act) filed

by the petitioner ITI Limited against the preliminary award dated

10.05.2000 passed by the sole arbitrator, Devender Kumar Sangal,

former Secretary and Director General, Department of

Telecommunications, whereby the preliminary objection of the

petitioner with regard to the claim of the respondent being barred by

limitation has been rejected. Briefly stated, the facts are as under:

2. The petitioner ITI Limited undertakes the manufacture and

assembly of various mechanical products. The respondent, Par

Pressings - a small scale industry, was selected as an Ancillary Unit for

the supply of „Unit Assemblies‟ (UTAs). These UTAs were the sub-

assemblies of the Cross Bar Telephone Exchanges manufactured by

the Petitioner Company which they supplied to Department of

Telecommunications (DOT). At one point of time the Cross Bar

Exchanges were phased out by the DOT. Consequent to the phasing

out of the Cross Bar Exchanges, the DOT cancelled the orders placed

by it on the petitioner. The petitioner company vide its

communications dated 05.02.1992, 07.03.1992 and 30.04.1992

required the respondent to stop the supply of UTAs. This gave rise to

claims by the respondent against the petitioner.

3. Respondent through its letter dated 03.10.1994 addressed to

Chairman & Managing Director (CMD) of the petitioner, inter alia,

requested him to constitute a competent authority duly empowered to

negotiate a settlement and resolve the claims and disputes with the

respondent. In the eventuality of no settlement being arrived at, the

respondent sought reference of the dispute to arbitration and stated

that they are agreeable to the CMD of the petitioner acting as the sole

arbitrator. Again on 14.02.1995 the respondent sent another

communication to the CMD of the petitioner, inter alia, requesting him

to refer the matter to arbitration as per the petitioners‟ policy direction

dated 29.03.1993.

4. It appears that the petitioner company initially paid no heed

to the request of the respondent to either settle the claims made by it,

or even to refer the matter to arbitration. Due to the persistent

pressure mounted by the respondent to settle their claims, the

petitioner company finally held a High Level Committee meeting on

30.04.1999 in presence of the representative of DOT to review the

claims of the respondent. In the said meeting a decision was taken to

appoint "an independent outside eminent personality who will

scrutinize the whole claim of M/s. Pressing and decide upon the

amount payable, if any, to M/s Par Pressing by M/s. ITI. The decision of

such independent person will be binding on both the parties."

5. In pursuance of the above resolution, the petitioner addressed

a letter dated 09.06.1999 to Sh. D.K. Sangal to look into the disputed

claim of the respondent and to give his decision. A copy of this letter

was also sent to respondent, inter alia, seeking its confirmation of

acceptance of appointment of Sh. D.K. Sangal to look into the disputed

claims.

6. The respondent responded to the above communication vide

letter dated 15.06.1999 whereby it agreed "to the appointment of Mr.

D.K. Sangal as the sole Arbitrator to adjudicate the dispute between ITI

Ltd. and Par Pressings". On 11.11.1999, the petitioner sent a

communication to Mr. D.K. Sangal with the subject "In the matter of

Arbitration between" the respondent herein as the claimant and the

petitioner herein as the respondent. It was further stated:

"Referring to the above subject, we write to inform you that S/Sri.N. Venkatraman, Dy. General Manager [P&A-IR], Corporate Office, and JP Mishra, Dy. General Manager, Mankapur Unit have been nominated to represent the company in the Arbitration Proceedings." "We shall be thankful if you could kindly intimate the above two officials and the Claimant, indicating a convenient date and time to hold a Preliminary Meeting to discuss and decide the procedure for the conduct of the Arbitration Proceedings including Payment of Fees of the Arbitrator, Costs of the Arbitration, Time Schedules for filing of representations by both the parties, Time schedule for depositing money etc."

......................

"2. It is suggested that the Arbitration Proceedings may be held at our Business Co- ordination Office, 1st Floor, Core No. 6, Scope Complex, 7, Lodhi Road, New Delhi-110 003. You may kindly intimate your convenience and the facilities required at the venue to enable us to make necessary arrangements."

7. Admittedly, in the first meeting of the parties with the

arbitrator on 18.12.1999, the arbitrator entered into reference upon

the receipt of the claim.

8. I have extracted from the aforesaid correspondence and

narrated some of the aforesaid undisputed facts for the reason that a

faint submission was made by the petitioner that the proceedings

before Mr. D.K. Sangal were not an „arbitration‟, as he was not

appointed as an „Arbitrator‟ but only as an "independent outside

eminent personality" to scrutinize the claim of the respondent. This

submission cannot be accepted because Mr. D.K. Sangal was evidently

invested with the authority to independently scrutinize the claim of the

respondent and to render his `decision‟, which the petitioner stated

would be binding on both the parties. Moreover, the petitioner itself

repeatedly and expressly described him as an „Arbitrator‟ and that is

how his appointment was understood and treated by both the parties.

This objection does not appear to have been raised before the learned

Arbitrator, though it could have been raised. It cannot be permitted to

be raised in these proceedings for the first time. This submission is

accordingly rejected.

9. Before the arbitrator the petitioner raised a preliminary

objection about the claim of the respondent being barred under the

law of limitation. The arbitrator after considering the submissions of

both the parties has given a reasoned preliminary award to the effect

that the claimant‟s claim was not barred by limitation under the

Arbitration & Conciliation Act, 1996 read with the Limitation Act, 1963.

Aggrieved by this preliminary award the petitioner has preferred these

objections to the preliminary award dated 10.05.2000.

10. The notice in this petition was issued on 17.08.2000. By order

dated 29.09.2000 this court directed that the proceeding before the

arbitrator will continue but the final award will not be passed.

However, by the order dated 22.02.2001, this court allowed the

arbitrator to pass the final award. On 16.06.2001, the arbitrator

passed the final award against the petitioner company where he

awarded most of the claims of the respondent. This award is also

under challenge in a separate petition filed under Section 34 of the

Arbitration and Conciliation Act, 1996.

11. The petitioner submits that claim had been filed by the

respondent before the learned arbitrator on 27.07.1999 whereas the

same pertained to the period 1989 to 1992 as the supply orders that

were rescinded pertained to that period. It is argued that the period of

limitation for the recovery of price for goods supplied and for

compensation for alleged breach of contract is three years from the

date when the liability, if any, to pay arises or from the date when such

liability was last acknowledged by the person liable to pay such

amounts. In the absence of any acknowledgment of the purported

claim, the claim is barred by limitation. By placing reliance on Steel

Authority of India Limited Vs. J.C. Budhraja, Government and

Mining Contractor (1999) 8 SCC 122, it is contended that the

arbitrator was duty bound to outrightly reject the claim which was, on

the face of it, time barred.

12. It is next submitted by the counsel for the petitioner that the

letter dated 03.10.1994 cannot be considered as a proper notice for

invoking arbitration and, therefore, no right accrues to the respondent

therefrom. Alternatively, it is submitted that even if the letters dated

03.10.1994 and 14.02.1995 are assumed to be notices invoking

arbitration, even then the claim is barred by limitation. It is argued

that the right to seek appointment of an arbitrator under Section 8 of

the Arbitration Act 1940 accrued on the expiry of 15 days from the

date of service of notice, and even this right should have been

exercised within three years from the date of accrual of the right. The

observation of the arbitrator that Section 8 of the Arbitration Act, 1940

lays down no outer limit for approaching the court for appointment of

an arbitrator is assailed by relying on the decisions in Utkal

Commercial Corporation v Central Coal Fields Ltd. (1999) 2 SCC

571; Morena Mandal S.S.K. Ltd v New India Assurance Company

Ltd. (1999) 5 SCC 697; J.C. Budhraja v Chairman, Orissa Mining

Corporation Ltd. 2008 (2) SCC 444 where the courts have held to the

effect that if the party seeking appointment of an arbitrator fails to

move the court under Section 8 within the period of three years when

such right accrues, the right to approach the court to seek

appointment of an arbitrator would be barred by limitation. It is

submitted that the position under Section 11 of the Arbitration and

Conciliation Act 1996 is similar. Reliance is placed on the decisions in

P. B. Enterprises, Engineers and Contractors Vs. Eastern

Coalfields Ltd. AIR 2004 Jhar 71 and M.V.V. Satyanarayana Vs.

U.O.I., Rep. by Dy. Chief Engineer (Cons.), S.C. Railway,

Secunderabad and Ors. 1999 (2) RAJ 173 (A.P) in this regard.

13. It is also contended that the finding of the arbitrator that

there is no outer limit of time under Section 8 of the Arbitration Act,

1940 is against the settled principles of limitation and hence against

public policy of India. By referring to the decision in N. Balakrishnan

v M. Krishnamurthy (1998) 7 SCC 123, it is contended that the

question of limitation is a matter of public policy and is a good ground

for setting aside the award under Section 34 of the Act. It has been

held that the public policy with regard to prescription of limitation is

enshrined in the maxim interest reipublicae up sit finis mum, that is,

for the general welfare that a period be put to litigation.

14. Petitioner also relies on the decisions in U.P. Rajkiya Nirman

Nigam Ltd v Indure Pvt. Ltd. (1996) 2 SCC 667 and Dresser Rand

S.A. v Bindal Agro Chem Ltd. (2006) 1 SCC 751 to bring home the

point that mere acquiescence to the jurisdiction of arbitrators by a

party would not estop a party to have remedy to challenge the award,

as acquiescence does not necessarily confer jurisdiction. Hence the

arbitration proceedings can be challenged as being barred by

limitation even if the petitioner itself appointed the arbitrator.

15. On the other hand, submission of the respondent is that none

of the ingredients of Section 34 of the Act for setting aside of the

award is made out in the present petition. It is submitted that a

decision on the issue of limitation is primarily a question of fact. The

decision of the arbitrator is clearly a decision on the facts of this case.

The arbitrator‟s is the last word on facts and this Court not being an

appellate forum vis-à-vis the arbitral award cannot go into the

correctness or otherwise of the findings of fact. It is argued that the

learned Arbitrator has rightly held that the letter dated 03.10.1994

constitutes a notice for invocation of arbitration. In any event, the

letter dated 14.02.1995 was clearly a letter invoking the arbitration

agreement. Consequently by virtue of Section 37(3) of the Arbitration

Act, 1940, as also Section 43(2) of Arbitration and Conciliation Act,

1996, the arbitration proceedings stood commenced upon the issuance

of the said notices. He refers to decisions in Milkfood Ltd. v. GMC

Ice Cream (P) Ltd. (2004) 7 SCC 288; J.C. Budhraja v. Chairman,

Orissa Mining Corporation Ltd. and Anr. (2008) 2 SCC 444; Utkal

Commercial Corporation v. Central Coal Fields Ltd. (1999) 2 SCC

571; Morena Mandal S.S.K. Ltd. v. New India Assurance Co.

Ltd. (1999) 5 SCC 697 to submit that the arbitration commences by

service of notice and issuance of request for appointment of an

arbitrator. He submits that the interpretation of these documents

(dated 3.10.1994 and 14.2.1995) by the learned arbitrator cannot be

said to be an implausible interpretation. The same cannot be

interfered with in these proceedings merely because the Court may be

of the view that another interpretation was equally possible.

16. The counsel for the respondent further submits that at no

point of time the respondent had given up their claim. The respondent

was always making efforts to realize its dues from the petitioner

company. By referring to the decision in Lata Constructions & Ors.

v. Dr. Rameshchandra Ramniklal Shah & Anr. (2000) 1 SCC 586

and Basic Shiksha Parishad & Anr. v. Sugna Devi (Smt.) & Ors.

(2004) 9 SCC 68 it is argued that since the claim had not been given

up by the respondent, there was a continuing cause of action running

against the appellant and the claim was, therefore, not barred by

limitation.

17. Alternatively, it is argued that even if one were to assume

that the remedy to seek appointment of the arbitrator (which accrued

to the respondent upon issuance of the notice dated 03.10.1994 and/or

dated 14.02.1995) was barred by limitation, that does not mean that

the respondents‟ right to get the claims/disputes resolved through

arbitration was also extinguished. Reliance is placed on the decisions

in Punjab National Bank & Anr. v. Surendra Prasad Sinha 1993

Supp. (1) SCC 499 and Prem Singh & Ors. v. Birbal & Ors. (2006) 5

SCC 353 to submit that Limitation Act bars only the remedy but does

not destroy the right to which the remedy relates.

18. Before going further, it would be pertinent here to analyze the

reasoning of the arbitrator whereby he held that the claim was not

barred by limitation. The arbitrator had arrived at his finding by

examining the provisions of both: Arbitration Act, 1940 (the old Act)

and the Arbitration and Conciliation Act, 1996 (the new Act). He was

concerned with the claim which fell due during in the period February,

1992 to September, 1993. He returned the finding that the arbitration

proceeding stood commenced on 03.10.1994 by virtue of notice/letter

dated 03.10.1994 of the respondent when a request for appointment of

arbitration was made for the first time. He was of the view that the

matter was continuously pursued by the respondent and was even

receiving the attention of the petitioner company. In his view, Section

8 of the old Act is an enabling Section, which only prescribes minimum

period of 15 days after service of notice for approaching the Court for

appointment of an arbitrator and it lays down no outer (upper) limit.

He further goes on to observe that the original notice is not invalidated

and barred by limitation if the party chooses not to come to the Court,

but to pursue the matter himself with the other party.

19. Both parties have filed their respective written submissions

and have also relied on them. Having considered the rival submissions

of the parties and in view of the facts disclosed above, I am of the view

that there is no merit in the objections raised by the petitioner to the

impugned award on the ground that the claims of the respondent were

barred by limitation.

20. Section 37(3) of the old Act and Section 43(2) of the new Act

substantially provide that an arbitration shall be deemed to have

commenced on the date request for the disputes to be referred to

arbitration is received by the respondent. In this case the learned

Arbitrator has found, as a matter of fact, that the claims pertained to

the period 1992-93. This is also evident from the aforesaid narration of

facts which is also not disputed. The learned Arbitrator has further

found that the respondent had issued two notices to invoke arbitration,

the first on 03.10.1994 and the second on 14.02.1995. The limitation

for invoking arbitration was three years from the date of accrual of the

cause of action, which as aforesaid, accrued in the years 1992-93.

Consequently, the invocation of arbitration on 3.10.94 or at the latest

on 14.2.1995 was well within the period of limitation by virtue of

Sections 37(3) of the old Act or Section 43(2) of the new Act. The

arbitration was deemed to have commenced upon the receipt of the

aforesaid notice(s) by the petitioner.

21. The finding of the learned arbitrator that there is no outer

limitation of time for a party to avail of the remedy to get the arbitrator

appointed may not be correct in view of the Supreme Court decisions

in Utkal Commercial Corporation (supra) and J.C. Budhraja v.

Orissa Mining Corpn. Ltd. (supra). However, this erroneous finding

of the learned arbitrator does not make any difference in the facts of

this case for the reasons stated hereinafter.

22. No doubt, the Arbitrator was not appointed within the period

of three years from the date of commencement of arbitration i.e.

3.10.1994 / 14.2.1995. Article 137 of the Limitation Act, 1963 applies

to a proceeding under Section 8 of the old Act or Section 11 of the new

Act. But in the present case, no application/petition was made to a

competent Court by the respondent to seek appointment of an

arbitrator. The appointment of the learned arbitrator Sh. D.K. Sangal

was not made by the Court either in proceedings under Section 8 of

the old Act or Section 11 of the new Act, but by the petitioner.

Therefore, the question of the appointment being made within

limitation did not arise.

23. Consequently, in my view Article 137 of the Limitation Act is

of no relevance in the facts of this case. At best, what could be said is

that on the expiry of the period of three years from the date of

invocation of arbitration i.e. 3.10.1994/14.2.1995, the remedy of the

respondent to approach the Court to seek the appointment of the

Arbitrator got barred by limitation. However, the respondents‟ right to

get its disputes with the petitioner resolved through arbitration did not

get extinguished and the arbitration agreement, though not

enforceable through a judicial process, continued to subsist.

Consequently, if an Arbitrator was appointed by the petitioner (even

after the expiry of the period of limitation within which the respondent

could enforce the arbitration agreement by approaching the Court

under Section 8 of the old Act or Section 11 of the new Act), it cannot

be said that the appointment of the arbitrator is illegal or that the

claim of the respondent preferred before the Arbitrator, so appointed

by the petitioner, was barred by limitation. I may refer to the following

extract from J.C. Budhraja v. Orissa Mining Corpn. Ltd. (supra) at

this stage:

"25. The learned counsel for the appellant submitted that the limitation would begun to run from the date on which a difference arose between the parties, and in this case the difference arose only when OMC refused to comply with the notice dated 4.6.1980 seeking reference to arbitration. We are afraid, the contention is without merit. The appellant is obviously confusing the limitation for a petition under Section 8(2) of the Arbitration Act, 1940 with the limitation for the claim itself. The limitation for a suit is calculated as on the date of filing of the suit. In the case of arbitration, limitation for the claim is to be calculated on the date on which the arbitration is deemed to have commenced.

26. Section 37(3) of the Act provides that for the purpose of Limitation Act, an arbitration is deemed to have been commenced when one party to the arbitration agreement serves on the other party thereto, a notice requiring the appointment of an arbitrator. Such a notice having been served on 4.6.1980, it has to be seen whether the claims were in time as on that date. If the claims were barred on 4.6.1980, it follows that the

claims had to be rejected by the arbitrator on the ground that the claims were barred by limitation. The said period has nothing to do with the period of limitation for filing a petition under Section 8(2) of the Act. Insofar as a petition under Section 8(2) is concerned, the cause of action would arise when the other party fails to comply with the notice invoking arbitration. Therefore, the period of limitation for filing a petition under Section 8(2) seeking appointment of an arbitrator cannot be confused with the period of limitation for making a claim. The decisions of this Court in Major (Retd.) Inder Singh Rekhi v. DDA (1988) 2 SCC 338, Panchu Gopal Bose v. Board of Trustees for Port of Calcutta (1993) 4 SCC 338 and Utkal Commercial Corpn. v. Central Coal Fields Ltd. (1999) 2 SCC 571 also make this position clear." (emphasis supplied)

24. Had the petitioner not appointed the Arbitrator, the

respondent would have been remediless to seek the appointment of an

Arbitrator through the process of the Court. However, that does not

mean that the appointment of the Arbitrator by the petitioner itself

after the commencement of the arbitration proceedings, which already

stood commenced on 3.10.1994/14.02.1995, could be said to be

barred by limitation. The date of filing of the claim before the

Arbitrator so appointed, in my view, was of no relevance, just as the

date of appointment of the Arbitrator (who was appointed by none

other than the petitioner) was of no relevance.

25. The decisions in U.P. Rajkiya Nirman Nigam Ltd. (supra) as

well as the decision in Dresser Rand S.A. (supra), in my view have no

application in the facts of this case. In U.P. Rajkiya Nirman Nigam

Ltd. (supra), the appellant without prejudice to its rights to question

the existence and validity of the arbitration clause as well as the

agreement itself proceeded to nominate an Arbitrator. The Court held

that in the absence of a binding contract, by merely nominating an

Arbitrator the appellant would not be estopped from maintaining an

application under Section 33 of the old Act, as acquiescence does not

confer jurisdiction. However, in the present case there is hardly any

issue raised with regard to the existence of arbitration agreement

contained in the petitioner‟s own circular, which is in writing, and on

the basis of which both parties proceeded to deal with the matter

before Shri D.K. Sangal as an arbitration proceeding. As aforesaid,

since the underlying arbitration agreement was not the subject matter

of dispute, the nomination of the Arbitrator by the petitioner had the

effect of fulfillment of the obligation to take the disputes to arbitration,

even though the period within which the arbitration agreement could

have been legally enforced had already expired. An arbitrator

appointed belatedly by the appointing authority does not lose his

authority as an Arbitrator on the ground of delay in his appointment

and once appointed, he gets vested with all the powers and authority

of an Arbitrator. Similarly, in Dresser Rand S.A. (supra), the issue

was with regard to the existence of the arbitration agreement itself

and this case did not deal with a fact situation like in the present case.

Consequently, the same in my view has no application in the present

case. For the aforesaid reasons, I find no merit in this petition and

dismiss the same leaving the parties to bear their respective costs.

(VIPIN SANGHI) JUDGE

DECEMBER 04, 2009 as/rsk

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter