Citation : 2009 Latest Caselaw 3324 Del
Judgement Date : 24 August, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS) No.1764A/1996
% Date of decision: 24.08.2009
UNION OF INDIA ....Petitioner
Through: Ms. Zubeda Begum, Advocate for the
Petitioner with Mr. G.R. Sangwan, Ex.
Engineer.
Versus
SHRI S.K. CHOPRA ....Respondent
Through: Mr. Harish Malhotra, Sr. Advocate with
Mr. Rajender Agarwal & Mr. Vipul
Gupta, Advocates.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? No
2. To be referred to the reporter or not? No
3. Whether the judgment should be reported No
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. The suit was registered on the filing of arbitration award dated
24th October, 1994 in this court by the arbitrator. Notice of the filing
of the award was issued to both the parties. Objections under
Sections 30 & 33 of the Arbitration Act 1940 in the form of IA
No.1118/1996 by the petitioner Union of India and IA No.1119/1996
by the respondent Shri S.K. Chopra have been preferred with
respect to the parts of the award against the respective parties and
claimed to be severable from the other part of the award. Though,
the objections have been pending for long but as per the prevalent
practice, the usual issues had remained to be framed. The same
were framed on 7th July, 2009. The counsels for the parties stated
that the arbitral record received in this court only would be relied
upon by them in support of their respective objections and no
affidavits by way of evidence are required to be filed. The counsels
for the parties have been heard.
2. The agreement between the parties with respect whereto
disputes arose, was of award of contract by the petitioner Union of
India to the respondent of construction of Flyover and Retaining
Walls near the Flated Factories at Jhandewalan, New Delhi. The
date of start of the work was 6th December, 1985 and the stipulated
date of completion was 5th December, 1986. However, the work
continued to be executed beyond the stipulated date of completion
also and the time for completion was repeatedly extended by the
petitioner Union of India. The said work was not completed by the
respondent and disputes and differences arose between the parties.
The contract was rescinded on 15th November, 1989. The award
records that only the claims of the petitioner Union of India were
referred to the arbitrator vide letter dated 9th December, 1992. The
award also records that the respondent made counter clams before
the arbitrator on which pleadings were completed though the said
counter claims had not been referred by the appointing authority to
the arbitrator. The award nevertheless deals with the claims and the
counter claims together under one head only.
3. The arbitrator has held that initially the petitioner Union of
India was in breach in its failure to handover a part of the site to the
respondent and later the respondent had inordinately prolonged the
work; the arbitrator in view of the fact that the contract had been
rescinded by the petitioner Union of India belatedly without making
the time for performance as essence, holds that legally no risk and
cost action in terms of the agreement subsists in favour of the
petitioner UOI against the respondent and nothing could be awarded
to the petitioner UOI against the respondent under the claim No.2 in
this regard. For the same reason the claim No.1 of the petitioner
UOI for levy of compensation for delay in execution of work was also
declined. On the same reasoning the counter claim No.5 of the
respondent for losses due to idle establishment etc. due to
prolongation of the contract was also declined. The award also holds
that the petitioner Union of India had already paid the escalation
under the provisions of clause 10(CC) of the agreement for the work
done during the stipulated period of the contract and finding the
delays attributable to both parties, no further payment on this
account has been allowed to the respondent. The award also
negatives the claim of the respondent for wrongful deduction of the
rebate for timely payment of the bills. The award also negatives the
claim of the respondent for centering/shuttering.
4. The award holds the respondent entitled to refund of security
deposit of Rs.1 lac and also holds the respondent entitled for the
value of work done, less recoveries admissible to the claimant. The
arbitrator has found a sum of Rs.1,47,699/- to be due to the
respondent against the final bill. The award also has allowed a sum
of Rs.5,000/- to the respondent against the wrongful withholding
from the respondent's bill of sum of Rs.4,000/- and Rs.1,000/- for
non-sanction of AHR items. Thus a total sum of Rs.2,52,699/-
(Rs.1,47,699/- + 1,00,000/- + 5,000/-) has been found due to the
respondent from the petitioner Union of India.
5. The arbitrator has found that the respondent failed to return
51.62 M.T. of steel of the value of Rs.3,35,530/- issued to it for the
purposes of the works. The arbitrator in terms of the clause 42 of
the contract held the petitioner Union of India to be entitled to
double the value of the said steel i.e. Rs.6,71,060/-.
6. Besides the said amount certain other small amounts with
respect whereto no arguments have been addressed, were also found
due to the petitioner Union of India from the respondent. Thus a
total sum of Rs.7,28,737/- was found due to the petitioner Union of
India from the respondent. After deducting Rs.2,52,699/- (Supra)
therefrom, the petitioner Union of India was held entitled to recovery
of Rs.4,76,038/- from the respondent. Costs of Rs.5,000/- and simple
interest at 12% per annum from 13th October, 1992 to the date of the
award have also been awarded to the petitioner Union of India
against the respondent.
7. As far as the objections preferred by the petitioner Union of
India are concerned, there are virtually no pleadings whatsoever
therein. It is merely stated that the award is grossly erroneous and
the arbitrator has not analyzed all the claims of the petitioner Union
of India. Besides, it is merely stated that "the petitioner is mainly
challenging Clause 2 of the arbitration". However, in view of the
submissions of the counsel, the effect of such cursory pleadings in
the petitions under Sections 30 & 33 of the Act need not be gone into
these proceedings. The counsel for the petitioner Union of India has
challenged the finding of the arbitrator of the delays being
attributable to the Union of India also. It is contended that under
Clause 2 of the contract, in the event of the contractor failing to
comply with the conditions mentioned therein he is liable for
compensation of an amount equal to 1% or such smaller amount as
the Supdt. Engineer (whose decision in writing shall be final) may
decide on the said estimated cost of the whole work. It is contended
that Supdt. Engineer had decided the liability of the respondent as
Rs.5,61,123/- on this account and the decision of the Supdt.
Engineer was final and not arbitrable. The counsel urges that
however since arbitration was claimed qua other claims, recovery in
the said amount was also shown in the claim petition but the
arbitrator was not competent or entitled to return a finding thereon,
the same being non-arbitrable.
8. Though the petitioner Union of India itself made the claim
before the arbitrator, which upon being disallowed by the arbitrator
is being challenged before this court as non-arbitrable but the said
matter is no longer res integra in view of the judgment of the
Division Bench of this court in DDA Vs. M/s Sudhir Bros. 57 (1995)
DLT 474. It has been held therein that when a matter is not
arbitrable, the court can order so in objections under Section 33 of
the Act, notwithstanding the party seeking the said relief having
itself sought arbitration with respect thereto. It was held that the
court has to in such cases merely order the said part of the award to
be struck of.
9. The senior counsel for the petitioner has also fairly conceded
that in view of the judgment aforesaid, this court may order so with
respect to the said claim of the petitioner Union of India, subject of
course to the right of the respondent to the appropriate remedy as
and when the said claim is sought to be enforced by the petitioner
Union of India against the respondent.
10. Accordingly, it is directed that the claim of the petitioner for
Rs.5,61,123/- being an accepted matter could not have been
arbitrated upon and the award in that respect shall stand struck of.
The said claim having not been arbitrated upon and thus there being
the question of this court returning any finding on the same, the
respondent shall have the remedies, if any, available to him as and
when the said claim is enforced by the petitioner Union of India
against the respondent.
11. The arguments centered around the award qua 51.62 M.T.
steel with respect whereto double the value thereof has been
awarded in favour of the petitioner. The senior counsel for the
respondent has challenged the said award on three grounds; (1) on
the ground of being without reason as required under the
agreement; (2) the finding of misappropriation of 51.62 M.T. of steel
by the petitioner being contrary to the record and (3) the law not
permitting payment of double the value thereof by way of penalty,
without proof of any loss.
12. The award deals with the contention of the respondent that he
had left the surplus steel at the work site after rescission of the
contract and the same was deemed to have been in the custody of
the petitioner and the petitioner being thus not entitled to claim the
value thereof. The arbitrator has held that it was the obligation of
the respondent to handover the surplus steel to the petitioner at the
time of closure of the contract and having not done so the
respondent is liable for the same. Another plea in this respect dealt
with in the award is on account of overweight. The arbitrator has
held that the respondent never raised the said plea at any time
during the execution of the work and is thus not entitled to raise the
same as an afterthought.
13. The senior counsel for the respondent has taken me through
the pleadings and the documents in the arbitral record in an attempt
to demonstrate that there is absolutely no basis for the arbitrator to
assume that 51.62 M.T. of steel was in excess/surplus. The senior
counsel has successfully demonstrated that the said quantity was
seriously challenged by the respondent before the arbitral tribunal.
The senior counsel for the respondent has shown the statement of
the claim of the petitioner Union of India in which it was mentioned
that 446.435 M.T. of steel had been issued to the respondent as
borne out from unstamped receipt (USR) filed as CE 19 to 36. He
has also shown the reply filed by the respondent to the said
settlement of claim wherein the respondent has denied that 446.435
M.T. of steel had been issued to it; it is further pleaded that as per
the recovery statement attached with the 19th RA Bill paid on 18th
May, 1989, a total quantity of 389 M.T. only had been recovered;
that the quantities issued as shown in the statement attached to the
final (20th Bill) were entirely different; that the total quantities as per
the USR's filed by the petitioner worked out to 436.121 M.T., out of
which 28.094 M.T. had been transferred by the petitioner to the
other works leaving a net quantity of 408.118 M.T. only issued to the
respondent; out of this 382.396 M.T. was consumed in the work and
after adding wastage and variation as per the terms of the
agreement, theoretical consumption works out to 401.746 M.T. The
fact remains that the arbitrator has not dealt with the same and from
the bare reading of the award it cannot even be said that there was
any dispute before the arbitrator as to the quantity of the steel.
14. It is not in dispute that steel consumed in the works is 382.396
M.T. It is also not in dispute that 28.094 M.T. of steel issued by the
petitioner to the respondent was transferred to other projects; this
was admitted by the petitioner in its rejoinder. The senior counsel
for the respondent has contended that the petitioner however in its
rejoinder and to which the respondent had no opportunity to file any
further pleadings, totally changed its stand; the petitioner now
contended that in fact the total quantity of steel issued to the
respondent was 474.449 M.T. and after transfer of 28.094 M.T., the
net quantity issued was worked out to 446.435 M.T.
15. The counsel for the petitioner Union of India did not controvert
the argument of respondent that the USR's on the arbitral record
were not with respect to the entire 474.449 M.T. It is however
argued that all these figures are shown in the final bill. It is
contended that there are other USR's and a register is also
separately maintained of the steel issued; the figures in the final bill
are taken from the said register which is maintained in the normal
course and that is why there is no error in the shortfall of 51.62 M.T.
believed by the arbitrator.
16. The senior counsel for the respondent has urged that in the
aforesaid circumstances, it is clear that the arbitrator being human
has erred in believing the shortfall to be 51.62 M.T. and further
having failed to decide the said disputed contentions. It is argued
that it is not a case where the arbitrator has even recorded that he
after perusal of the record he is of the opinion that the shortfall is
51.62 M.T. and not as contended by the respondent. Thus setting
aside of the award to the said extent is sought.
17. The argument of the respondent appears attractive. However,
the same is to be judged in the light of the jurisdiction being
exercised by this court i.e. under Sections 30 & 33 of the Arbitration
Act. The award on the very first page thereof records "NOW
THEFREFORE, AFTER PERUSAL OF THE PLEADINGS AND
DOCUMENTS FILED AND HAVING HEARD AND CONSIDERED
THE ARGUMENTS ADVANCED BY THE CLAIMANT AND THE
RESPONDENT, I V. NAINANI, DO HEREBY MAKE AND PUBLISH
THIS AWARD AS FOLLOWS".
18. Attention of the senior counsel for the respondent was invited
to the judgment of the Supreme Court in Arosan Enterprises Ltd.
Vs. Union of India 1999 3 Arbitration Law Reporter 310 (SC). A
five Judge Bench of the Supreme Court in Goa Daman Diu Housing
Board Vs Rama Kant V.P. Darvotkar AIR 1991 SC 2089 in an
appeal from the order of the Bombay High Court setting aside the
award for being without reasons inspite of being required to give
reasons, accepted the argument that the mere statement of the
arbitrator that the award had been made after hearing the parties
and after consideration of papers and documents filed by the parties
to be enough and it was held that such an award could not be said to
be illegal or suffering from any misconduct. It was further held that
unless there was anything to show that the arbitrator has
misconducted himself or the proceedings in any other manner or to
show that the award had been improperly procured, or that the
arbitrator has not fairly considered the submissions of the parties in
making the award in question, the award cannot be set aside. The
Supreme Court held that from the statement aforesaid of the
arbitrator it was evident that the arbitrator had considered all the
specific issues raised by the parties in the arbitration proceedings
and come to the finding returned. The Division Bench of this court in
a recent Judgment in DDA Vs Madhur Krishna
MANU/DE/0984/2009 has also relied upon the said constitution
bench judgment. In D.D. Sharma Vs Union of India (2004) 5 SCC
325 also the arbitrator had in the award stated that he had
examined and considered the pleadings submitted by and on behalf
of the parties and documentary and oral evidence produced before
him. The same was held sufficient by the Supreme Court to hold that
there did not exist any material on record to show that the
arbitration while making the award ignored any material documents.
The same was the position in Bijendra Nath Srivastava Vs
Mayank Srivastava 1994 6 SCC 117. There also the challenge to
the award for being without any reasons was met, by the arbitrator
recording the award that he had heard the parties and considered all
the points raised by them, the rights and claims of the parties
involved and the accounts and evidence produced by them.
19. The contention of the senior counsel for the respondent that
the arbitrator was performing a judicial function and must give
reason on each and every contentious issue raised is thus not
acceptable. A reading of the entire award in the present case does
not show that the arbitrator was oblivious of the case of the
respective parties before him. In the circumstances, it cannot be
said that the arbitrator has not applied himself before coming to the
conclusion that 51.62 MT of steel delivered by the respondent had
been misappropriated by the petitioner. That being the position, and
this being a finding of fact, this is his non- interferable in the
exercise of jurisdiction under Sections 30 and 33 of the Act.
20. The senior counsel for the respondent has next urged that as
per the dicta of the Five Judge Bench of the Supreme Court in Fateh
Chand Vs Balkishan Das AIR 1963 SC 1405, even if there is to be
no dispute as to the quantity of steel for which the respondent is to
compensate the petitioner, clause 42 of the contract providing for
payment of double the value of the steel is penal in nature and in the
absence of any proof of loss, the award for double the value of the
said steel is contrary to law. Reliance in this regard is also placed
upon Pearl Hosiery Mills Vs UOI 1978 RLR 1994, Marimuthu
Gounder Vs Ramaswamy Gounder AIR 1979 Madras 189 (DB),
State of Orissa Vs Calcutta Company Ltd AIR 1981 Orissa 206
Maula Bux Vs UOI AIR 1970 SC 1955.
21. The attention of the senior counsel for the respondent during
the hearing only was invited to ONGC Ltd Vs Saw Pipes Ltd AIR
2003 SC 2629. The Supreme Court in the said case though
speaking through a Bench of Two Judges only but after considering
the judgments of the larger Bench in Fateh Chand and Maula Bux
(supra) held that there could be cases where loss can not be proved.
Examples were cited of delays in construction of road or the bridge;
neither any person/individual or municipal nor any government
suffers any loss therein. The loss is of the public at large. The
Supreme Court in such a situation held that when the clause
provided for a particular amount to be paid in the event of default,
that could be directed to be paid even without proof of loss. Of
course in that case the clause was more specific, providing for the
amount to be a pre-estimate arrived at by the parties. Clause 42 is
not so specific; but in my view, the principle would be applicable also
where the government from its own stocks supplies materials to the
contractor for carrying out certain works, and obligation is placed on
the contractor to return the excess/unused material and it is further
provided that if the material is not so returned, the contractor shall
be liable to pay double the amount thereof.
22. The senior counsel for the respondent has contended that the
only loss which can be suffered by non-return of such material is of
the difference in price of the material supplied and the price
prevailing on the date of failure to return. It is argued that the same
being calculable, the loss in such cases cannot be equated to the
losses subject matter of consideration in Saw Pipes Ltd (supra)
where it was found to be incalculable. I, however, am unable to
accept the said contention. The procurement / purchase of material
by the Government / government department is not as simple.
Considerable effort goes in the same. Tenders have to be prepared,
invited, bids screened and only thereafter the material can be
procured. It is virtually impossible to calculate the costs of all the
said steps. Further, the said materials of the government are not
necessarily for one project only and can be used in other projects if
returned on time. Non return of the material and resultant delays in
procurement can also lead to consequent delays in other projects
and can have a cascading effect. In the aforesaid state of law, it
cannot be said that the award enforcing the clause for payment of
double the value of the material is so contrary to law or so
improbable which no reasonable person could have arrived at. Once
that test is satisfied, interference under Section 30 and 33 is not
permissible.
23. Thus no error is found in the part of the award challenged by
the respondent. No other plea has been urged. Also, no element of
perversity or shocking the judicial conscience, essential for the court
to set aside the award is found.
24. Accordingly, IA 1118/1996 of the petitioner Union of India is
allowed to the aforesaid extent and IA.No. 1119/1996 of the
respondent is dismissed. The award as modified above is made rule
of the court and decree is passed in terms thereof. However, in the
facts of the case, since the parties are found to have raised a bona
fide conflict for adjudication by this court, the parties are left to bear
their own costs.
RAJIV SAHAI ENDLAW (JUDGE) August 24, 2009 PP/M
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!