Citation : 2009 Latest Caselaw 3305 Del
Judgement Date : 21 August, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP 648/2008
% Date of decision:21.08.2009
NATIONAL SMALL INDUSTRIES
CORPORATION LTD ....Petitioner
Through: Mr. A.K. Thakur & Mr. Rajiv Arora,
Advocates
Versus
DUAL STRUCTURAL & INDUSTRIES LTD ... Respondent
Through: Mr. Jayant Nath, Sr. Advocate with Mr.
Upendra Thakur & Mr. Amesh Tandon,
Advocates.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? No
2. To be referred to the reporter or not? No
3. Whether the judgment should be reported No
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. This petition under Section 34 of the Arbitration Act, 1996 is
with respect to the arbitral award dated 30th August, 2008. The
proceeding has a chequred history. Disputes and differences
between the parties arose out of an agreement dated 9th October/2nd
November, 1998 for construction of Phase-I of the Software
Technology Park by the respondent for the petitioner at Chennai.
The arbitration clause in the said agreement enabled the Chairman-
cum-Managing Director of the petitioner to appoint the arbitrator.
Accordingly Mr P Krishnan, former Director General CPWD was
appointed as the sole arbitrator vide letters dated 26th September,
2002 and 8th October, 2002 of the Chairman-cum-Managing Director
of the petitioner, in the matter of the disputes between the petitioner
and the respondent relating to the aforesaid agreement.
2. The respondent made claims against the petitioner:
(i) for refund of Rs 40,23,524/- wrongly recovered by the
petitioner from the respondent as liquidated damages;
(ii) for interest @ 21% per annum on the above amount from 16 th
August, 2002 to 20th November, 2002;
(iii) Rs 20,40,287/- for recovery of overheads and establishment
costs during the contract period;
iv) for recovery of Rs 5,33,404/- towards additional site
establishment and overhead costs for the extended period of
contract beyond the originally stipulated period;
v) for recovery of Rs 8,38,222/- towards increase in the costs of
inputs for the work carried out after the originally stipulated
contract completion period;
vi) for recovery of Rs 3,49,519/- towards loss of interest on the
account of late release of running bill payments;
vii) for interest at 21% per annum, pre suit, pendente lite and post
award on the aforesaid amount and for costs.
3. The petitioner herein also made a counter claim against the
respondent for recovery of Rs 65,93,668/- on account of loss of
revenues due to undue delay in completion of the work by the
respondent. A sum of Rs 8,91,000/- was also claimed by the
petitioner on account of extra expenditure incurred on establishment
and contingency due to delay by the respondent in completion of
work.
4. The arbitrator published the award dated 25th September,
2004. Only the claim of the respondent for refund of Rs 40,23,524/-
recovered by the petitioner towards liquidated damages was allowed
and the petitioner was also directed to pay interest on the said
amount at 8% per annum from 16th August, 2002 to 2nd September,
2002, at 10% per annum from 3rd September, 2002 to 25th
September, 2004 and at 12% per annum from 26th September, 2004
till the date of payment. All the other claims of the respondent
against the petitioner as well of the petitioner against the
respondent were rejected.
5. The petitioner herein preferred OMP 5/2005 in this court
under Section 34 of the Act with respect to the said award. Notice
thereof was issued. The respondent did not prefer any petition
under Section 34 of the Act with respect to the award. OMP 5/2005
was disposed of vide order dated 10th May, 2006. This court set
aside the award directing refund of Rs 40,23,524/- by the petitioner
to the respondent and consequently the award for interest on the
said amount. The rest of the award was maintained. The arbitral
record was ordered to be sent back to the arbitrator.
6. Pursuant to the aforesaid order, the arbitration proceedings
were resumed before the same arbitrator who has now published the
award titled "Reconsidered award" dated 30th August, 2008 with
respect whereto the present petition has been preferred. The
arbitrator has reaffirmed his award for refund of Rs 40,23,524/- by
the petitioner to the respondent together with interest at the rate as
awarded in the earlier award.
7. For appreciating the contentions of the counsel for the
petitioner, it is appropriate to set down the relevant dates.
S.No. Date Particulars
1. 9.10.1998 Date of contract between the
2.11.1998 parties
2. 21.10.1998 The petitioner added additional work of construction of one canteen and two additional rooms in the existing hostel
building
3. 21.10.1998 The petitioner handover the construction site to the respondent
4. 10.11.1999 Further additional work of phase-II of the building is added to the work already allotted by the petitioner to the respondent.
5. 02.02.2000 The respondent seeks extension of time for completion of works.
6. 20.02.2000 Stipulated date of completion of works including additional works according to the petitioner.
7. 09.06.2000 The petitioner by a letter of this date extended the time for completion of works till 31st August, 2000, reserving its right to levy liquidated damages (LD) on the respondent.
8. 29.09.2000 The respondent seeks extension of time for completion of works.
9. 17.11.2000 The petitioner vide letter of this date extended time till 31st December, 2000 reserving its right to levy LD.
10. 21.06.2001 Work completed.
8. The contract entitled the petitioner to levy LD for delay in
completion or works @ 1% of the contract value per week and
subject to maximum of 10%. The petitioner levied LD in the sum of
Rs 40,23,524/- aforesaid under the said provision of the contract and
deducted the same out of the monies admittedly payable to the
respondent. It was in these circumstances that the respondent in its
claim petition before the arbitrator sought refund of the said monies
disputing/controverting the levy of liquidated damages by the
petitioner.
9. The arbitrator in the first award dated 25th September, 2004
held that as per the contract of the work initially awarded by the
petitioner to the respondent the stipulated date of completion was
20th February, 2000; that when the additional works were awarded
to the respondent, neither any specific time frame was fixed by the
petitioner or was mutually agreed by the parties for those works nor
made essence of the contract; that the time till 20th February, 2000
for completion of the works initially awarded though of the essence,
upon the award of additional works ceased to be of the essence of
the agreement; that after 20th February, 2000 no new period of
completion was fixed and it is to be deemed that the time had been
set at large and no longer the essence of the agreement; the
contention of the counsel for the petitioner that levy of LD is
automatic upon failure of the respondent to complete the works
could not be accepted as the scope of the work had been
substantially enlarged without fixing specific additional time; that
there was initial delay on the part of the petitioner in handing over
the full site and in decision, issue of drawings, the last drawing
having been issued only on 13th November, 2000. The arbitrator
thus held the respondent not entitled to LD and axiomatically
allowed the claim of the respondent for refund of the amounts
deducted towards LD.
10. This court in order dated 10th May, 2006 in OMP 5/2005 and
which order has attained finality held that a conjoint reading of
clauses 9, 11 and 30 of the contract show that the time was of the
essence of the contract and in case of the respondent's failure to
complete the work within stipulated time provision for LD is made in
the contract; that as per clause 9, the petitioner was within its right
to award additional work to the respondent and such work had to be
executed by the respondent in the manner specified in the contract
and treating the same as part of the works as originally awarded;
that on award of additional work time for completion of the work was
to be extended in the proportion which the additional cost of the
additional work bears to the original contract sum plus 25% of the
time calculated in the said manner; and when the time is extended in
such manner, the extended time becomes the essence of the
contract. This court found that the arbitrator had not considered the
implication of clauses 9, 11 and 30 of the contract and had in
contravention thereof wrongly concluded that while awarding the
additional work no specific time frame was stipulated and time did
not remain the essence of the contract. This court noted that the
arbitrator had imputed some delay on the petitioner but held that the
arbitrator was mainly influenced by the fact of the time being not of
the essence after the award of substantial additional work. This
court thus set aside the award to the said extent. While doing so this
court noticed the submissions of the respondent also and held that it
would be for the arbitrator to decide the issue afresh after
considering submissions of both the parties and with reference to
legal position clarified in the said order.
11. The arbitrator has in the reconsidered award noticed that
under clause 9.2 of the contract, upon award of additional work, the
time for completion is to be extended as noticed above in the order
of the High Court or "such further additional time as may be
considered reasonable by the engineer-in-charge" (there is no
dispute as to the contract providing so). The arbitrator has further
held that it was necessary for the petitioner to assess extra time
required for the additional work before commencement of the same
and that the extended time could be the essence of the contract only
if time was so assessed and known to both parties when the
additional work was taken up. He has further held that only then LD
could be levied for non-completion of the works within the said time.
The arbitrator further found that the petitioner had not
communicated to the respondent the extended time available taking
into consideration the additional work and letter in this regard was
written for the first time on 9th June, 2000 only granting provisional
extension upto 31st August, 2000. The arbitrator has held that there
was no definite stipulated date for completion of work and
assessment of delay in terms of clause 30.1 and hence levy of LD was
not justified.
12. The arbitrator further found that the petitioner had computed
delay of 139 days on the part of the respondent. The arbitrator
found that the petitioner had in the hindrance register maintained by
it and produced before the arbitrator, arbitrarily arrived at the delay
on the part of the respondent of 139 days; that the last two columns
of the hindrance register which were to be worked out were blank
and the details of arriving at the period of 189 delays had not been
communicated by the petitioner to the respondent. The arbitrator
also found the reasons given by the petitioner for computation of net
hindrance period to be arbitrary and not supported by calculations.
It was thus held that the levy of LD was not justified. Accordingly,
the earlier award was reaffirmed.
13. Though the counsel for the petitioner had attempted to argue
that the clause regarding levy of LD in the present case was
identical/similar to that before the Supreme Court in ONGC Ltd Vs.
Saw Pipes Ltd. 2003 5 SCC 705, but in my view the said question
does not arise for adjudication in the present case. Though, the
arbitrator has in the reconsidered award noticed the contention of
the counsel for the respondent that no losses had been suffered by
the petitioner owing to the delay, even if any, and thus the petitioner
was not entitled to any LD which is in the nature of penalty, but the
arbitrator having found no delay on the part of the respondent for
which LD could be levied did not deal with the said aspect. The
reconsidered award turns only on the finding of the arbitrator of
there being no delay inviting levy of LD. The challenge by the
petitioner to the reconsidered award has to be thus confined to the
said finding only of the arbitrator.
14. Faced with the aforesaid the counsel for the petitioner
contended that the arbitrator has misconducted himself in not
treating the award dated 25th September, 2004 earlier published by
him to have been set aside by this court vide order dated 10 th May,
2006 (supra) and by merely giving another reason for support of the
finding in the earlier award. It is further contended that inspite of
the direction of this court the arbitrator has in the reconsidered
award not dealt with clause 9.2 of the contract. He has in the course
of the hearing also handed over copies of the letters dated 29th April,
2000 and 29th September, 2000 of the respondent to the petitioner
and contended that the respondent had therein admitted delay. He
has also drawn attention to the letter dated 15th June, 2001 copy
whereof is on the record and wherein the respondent had admitted
the delay for the reasons of its precarious financial conditions and
requested for waiver of LD or levy of token LD. It is contended that
the same is an admission by the respondent of its liability for LD and
which has not been considered by the arbitrator.
15. It is next argued that the only case set up by the respondent
before the arbitrator was of time not being of the essence and it is
argued that it was never the case of the respondent that there was
no delay.
16. The counsel for the petitioner qua the hindrance register first
contended that the arbitrator had after the order dated 10th May,
2006 (supra) of this court directed the petitioner to produce the
hindrance register; however, upon the senior counsel for the
respondent pointing out that the hindrance register had been filed by
the petitioner before the arbitrator as far back as in the year 2003,
the same was admitted to be the correct position by the counsel for
the petitioner also; it was however contended that the arbitrator
before the reconsidered award did not seek any clarifications from
the petitioner with respect to the hindrance register and that the
finding of the arbitrator with respect to the hindrance register are
factually incorrect.
17. Per contra the senior counsel for the respondent has
contended that the arbitrator had after the order dated 10 th May,
2006 of this court reached the conclusion that there was no delay.
He has drawn attention to clause 9.2 of the contract providing for
computation as aforesaid of time upon additional work being allotted
and has highlighted that the formula provided therein is only one of
the alternatives and the other alternative is "or such further
additional time as may be considered reasonable by the engineer-in-
charge". It is urged that it was thus incumbent upon the petitioner
to, after the award of additional work, communicate to the
respondent the time for completion in terms of the formula
prescribed in clause 9.2 or as considered reasonable by the
engineer-in-charge. It is argued that no such time was communicated
and thus the respondent was not in the know of the time within
which, after the award of additional work, the works were to be
completed. He has also drawn attention to the hindrance register
copies whereof have been filed on record and to the typed copy
thereof filed by the petitioner also containing the explanation
therefor. He has also drawn attention to the copies of the internal
notes submitted by the petitioner before the arbitrator under cover
of letter dated 19th December, 2003 wherein the petitioner has also
recorded that the major portion of the additional construction was
completed by 31st December, 2000 and only some minor external
works and rectification works could not be completed during the
extended period and also praising the respondent for the works; in
the said note it is also recorded that there were delays in getting the
electric connection and the building licenses for various other
reasons and owing to which inspite of the respondent completing the
works the same could not be occupied; the worldwide slowdown in IT
Sector due to the then recent development in USA was also cited as
a reason for non-occupation of the software technology park. The
senior counsel for the respondent has thus argued that even if there
was any delay, no loss has been suffered by the petitioner for which
penalty in the form of LD could be awarded. The senior counsel for
the respondent has also contended that the findings of the arbitrator
are factual in nature and non- interfereable under Section 34 of the
Act.
18. The counsel for the petitioner in rejoinder has contended that
the findings of the arbitrator with respect to the hindrance register
are contrary to the admission of liability as aforesaid by the
respondent.
19. This court had in the order dated 10th May, 2006 interpreted
clauses 9, 11 and 30 of the contract. The said interpretation was
binding on the arbitrator. Thus, the arbitrator was not required to
deal again with the said clauses and no flaw can be found with the
award on this ground.
20. As far as the contention of the counsel for the petitioner of the
arbitrator having misconducted himself is concerned, I do not find
that the arbitrator has in any manner shown any obstinacy or
insistence on sticking to his earlier award which had been set aside
by this court. The arbitrator is not a person steeped in law or
familiar with legal language. Thus by picking a word here and there
in the reconsidered award it cannot be argued that the arbitrator
inspite of earlier award having been set aside refused to budge from
the same. The arbitrator had in the first award negatived the claim
for LD holding time not to have been of the essence. Certain
observations were made in that first award also of delay being on the
part of the petitioner. However, as observed / held by this court in
the order dated 10th May, 2006, the said observations were in
passing in the first award and otherwise it turned on the reasoning
of time not being of the essence. The arbitrator has in the
reconsidered award, following the interpretation of the clauses
aforesaid of the agreement permitting/making time to be of the
essence even on award of additional work, held that the petitioner
did not compute the said time while awarding the additional work.
This finding of the arbitrator cannot be said to be inconsistent with
the order dated 10th May, 2006 of this court.
21. This court in the order dated 10th May, 2006 had not
adjudicated on the alternative provided in clause 9.2 of the contract
whereunder the engineer-in-charge is entitled to fix additional time
for completion after award of additional work. The arbitrator has
interpreted the said clause of the contract and held that such
additional time ought to have been fixed by the engineer-in-charge at
the time of award of additional work, for the respondent to know the
time of completion. The arbitrator has not and could not have
controverted the finding of this court of upon such time being fixed,
the same being of the essence of the agreement. The senior counsel
for the respondent has in this regard rightly relied upon the
judgment in McDermott International Inc. Vs. Burn Standard
Co. Ltd. (2006) 11 SCC 181 holding that interpretation of a contract
is a matter for arbitrator to determine and the court ought not to
interfere with such interpretation unless the same is not possible at
all on a reading of the contract. In the present case, I find the
interpretation by the arbitrator of clause 9.2 of the contract to be a
possible one and not such which could not have been arrived at by
any reasonable prudent person. Clause 9.2 provides a formula for
arriving at the extended time and in the alternative empowers the
engineer-in-charge to fix the extended time. It is not the case of the
petitioner also that the petitioner at the time of awarding the
additional work intimated to the respondent that the completion time
would be determined in accordance with the formula and would not
be fixed by the engineer-in-charge. Thus no fault can be found with
the reasoning of the arbitrator that the respondent did not know the
date of completion. The situation can be compared to that of in a
written examination hall. If the examination time is left to be
determined by a convoluted formula or to be determined by the
invigilator, the examinee would be unable to plan out the time to be
devoted to different questions and cannot be all of a sudden told that
the time is up. That is what appears to have prevailed with
arbitrator also.
22. As far as the letters of the respondent seeking extension of
time are concerned, the stipulated completion period for the work
originally awarded was 16 months. The said letters appear to have
been written with reference to the said date and which admittedly,
after the award of additional work was not the stipulated date of
completion. It thus cannot be said that merely because the letters
seeking extension were written by the respondent that the
respondent was aware of the date of completion or that the award is
inconsistent with the said conduct of the arbitrator. Similarly, no
weightage can be given to the contents of the said letter or to the
respondent having sought waiver of LD. The Supreme Court in
National Insurance Co. Ltd. Vs. Boghara Polyfab Pvt. Ltd. AIR
2009 SC 170 has though in a different context, taken note of the
practices prevailing in the government departments qua such
construction contracts i.e. of insisting upon the contractors
furnishing No Due Certificate before even admitted payments are
released to them. I consider the letters in this case to have been
written in the same fashion/circumstances.
23. Be that as it may, the finding of the arbitrator of there being no
delay whatsoever on the part of the respondent in completing the
works is factual in nature. It is not as if the stipulated date of
completion could be fixed even on the basis of the formula given in
clause 9.2. The petitioner itself admits that there were other
hindrances to completion of the works and benefit whereof has been
given to the respondent. The arbitrator on going through the said
hindrances register has come to the conclusion that the benefit of
some days only given by the petitioner to the respondent is
misplaced/arbitrary and the respondent is entitled to benefit of
additional days. The question which arises is, can this court in
exercise of jurisdiction under Section 34 of the Act, also say that
such finding of the arbitrator is contrary to public policy. The
answer can be in the negative only. Reference in this regard, can be
made to i) State of U.P. Vs. Allied Constructions (2003) 7 SCC
396 where the conclusion of the arbitrator as to force majeure was
held to be non-interferable u/S 30 of the 1940 Act; ii) NHAI Vs.
Afcons Infrastructure Ltd. 152 (2008) DLT 24 where this court
held that interpretation arrived at by the arbitral tribunal being not
palatable to petitioner is no ground for setting aside of the award; iii)
New Delhi Apartment Group Housing Society Vs. Jyoti
Swaroop Mittal 2008 (100) DRJ 439 (DB) holding that unless the
view taken by the arbitrator is grossly irrational or perverse, the
court cannot substitute its own view and iv) MMTC Ltd. Vs. Irano
Hind Shipping Co. 2008 III Ad (Delhi) 315 holding that
appraisement of evidence by the arbitrator is never a matter which
court questions, relied upon by the senior counsel for respondent in
this regard.
24. The contention of the counsel for the petitioner of the
arbitrator having not given any opportunity to the petitioner to
explain the hindrance register is also not found to be correct. A
perusal of the proceedings before the arbitrator shows that the
arbitrator had in the proceedings on different dates noted the
contentions of the parties with respect to the hindrance register.
The arbitrator had in fact also given an opportunity to the petitioner
to furnish its explanation for the various entries in the hindrance
register and it is thereafter that the typed copy of the hindrance
register with the remarks of the petitioner came to be filed. Thus,
the petitioner's version of the hindrance register was before the
arbitrator and has been rejected by the arbitrator. The argument of
the petitioner that it was not for consideration before the arbitrator
as to whether there was any delay or not is also incorrect. The
parties were aware that after the order dated 10th May, 2006 of this
court, the question to be gone into before the arbitrator was this
only. Though arguments were raised that the arbitrator ought to
have directed the parties to file fresh pleadings but on inquiry as to
whether the petitioner sought any such opportunity, the reply is in
the negative.
25. Though the arbitrator has not dealt with the contention of the
respondent qua the petitioner being not entitled to levy LD without
proving loss I may notice that in the present case also it is the
admitted position that no evidence of loss, if any, was produced
before the arbitrator. Though the counsel for the petitioner has
relied upon ONGC Ltd. Vs. Saw Pipes Ltd., AIR 2003 SC 2629 a
judgment of two judges of the Supreme Court, the fact remains that
a five Judge Bench of the Supreme Court in Fateh Chand Vs.
Balkishan Das AIR 1963 SC 1405 had held that proof of such loss is
necessary. Saw Pipes Ltd., (Supra) turned on its own facts.
Though the counsel for the petitioner has contended that the clause
in the contract in the present case is the same as that before the
Supreme Court in Saw Pipes Ltd., (Supra) the fact remains that
there was also before the arbitrator the admission of the petitioner
himself as aforesaid that in spite of completion of construction by the
respondent the same could not be occupied for other diverse
reasons. Thus, material existed before the arbitrator showing that
no loss had been suffered by the petitioner for the reason of the
construction having been completed after the date which according
to the petitioner was the date for completion. In these circumstances
and in the light of the judgment in Fateh Chand (Supra), again it
cannot be said that the award negativing the claim for LD was not a
possible award or is perverse or ought to shock the judicial
conscience.
26. Thus no ground under Section 34 of the Act is found to have
been made out. The petition is dismissed with costs of Rs.35,000/-
payable by the petitioner to the Prime Minister's Relief Fund.
RAJIV SAHAI ENDLAW (JUDGE) August 21st , 2009 M
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!