Citation : 2009 Latest Caselaw 3296 Del
Judgement Date : 21 August, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ Arbitration Petition No.113/2006
Patel Engineering Ltd. ... Petitioner
Through Mr.Aspi Chinoy, Sr. Advocate with
Mr.Zar T. Andhyarunina,
Ms.Bhanu Kapadia, Ms.Seema
Sudd, Mr.Abhishek Roy,
Mr.Somnath Shukla, Advocates
Versus
Northern Railway Admn. ... Respondent
Through Ms.Geetanjali Mohan and
Mr.S.Rajappa, Advocates
Coram:
Hon'ble the Chief Justice
ORDER
% 21.08.2009
The respondent - Northern Railway Administration had
awarded to the petitioner a contract for construction of a single
line BG Tunnel No.4 (which includes cut and cover) between
14.961 Km. to 16.300 Km., as per the approved plan for
Udhampur - Srinagar - Baramulla Rail Link Project. Certain
differences and disputes arose between the parties, which were
referred by the petitioner to the respondent under Clause 63 of
the General Conditions of Contract. Almost all the claims of the
petitioner were rejected by the respondent. The petitioner then invoked the arbitration clause and called upon the respondent to
refer the disputes to the arbitration and this request was also
declined without stating any reasons. Thereafter, a considerable
correspondence was exchanged between the parties and finally
the respondent vide its letter dated 11th August, 2003 informed
the petitioner that the request for reference of the disputes to the
arbitrator cannot be acceded to as the petitioner's claims were
"excepted matters" and accordingly could not be referred to
arbitration. The petitioner is, therefore, constrained to file this
application under Section 11(6) of the Arbitration and Conciliation
Act, 1996 for the appointment of an arbitrator to adjudicate upon
the disputes between the parties.
2. In the reply filed by the respondent, the defence raised is the
same, namely, disputes do not fall within the scope of
arbitration clause and are "excepted matters". Since the
disputes have arisen and there is an arbitration agreement
between the parties as well, the only question, therefore,
needs determination is as to whether the disputes raised by
the petitioner are to be treated as "excepted matters" and
consequently beyond the scope of arbitration. A conjoint
reading of Clauses 63 and 64 is necessary for this purpose.
Therefore, it would be necessary to reproduce both the
Clauses in their entirety:
"63. Matters finally determined by the Railway - All disputes and differences of any kind whatsoever arising out of or in connection with the contract, whether during the progress of the work or after its completion and whether before or after the determination of the contract, shall be referred by the contractor to the Railway and the Railway shall within a reasonable time after receipt of the Contractor's representation make and notify decisions on all matters referred to by the contractor in writing provided that matters for which provision has been made in clauses 18, 22(5), 39, 45(a), 55, 55-A(5), 61(2) and 62(1)(xiii)(B)(e)(b) of the General Conditions of Contract or in any clause of the Special Conditions of the Contract shall be deemed as 'excepted matters' and decisions thereon shall be final and binding on the contractor provided further that 'excepted matters' shall stand specifically excluded from the purview of the arbitration clause and not be referred to arbitration. 64 Demand for Arbitration - (1) (i) In the event of any dispute or difference between the parties hereto as to construction or operation of this contract or the respective rights and liabilities of the parties on any matter in question, dispute or difference on any account, or as to the withholding by the Railway of any certificate to which the contractor may claim to be entitled to, or if the Railway fails to make a decision within a reasonable time, then and in any such case, save the 'excepted matters" referred to in clause 63 of these conditions, the contractor, after 90 days but within 180 days of his presenting his final claim on disputed matters, shall demand in writing that the dispute or difference be referred to arbitration.
64 (1)
(ii) .......
(iii) .......
(2) .......
(3) Arbitration - (i) A sole Arbitrator who shall be
the General Manager or a Gazetted Railway Officer nominated by him in that behalf in cases where the claim in question is below Rs.5,00,000/- (Rupees Five Lakhs) and in cases where the issues involved are not of a complicated nature, the General Manager shall be the Sole Judge to decide whether or not the issues involved are or a complicated nature.
(3)(a)(ii) Two Arbitrators who shall be Gazetted Railway Officers of equal status to be appointed in the manner laid in clause 64(3)(b) for all claims of Rs.5,00,000/- (Rupees Five Lakhs) and above, and for all claims irrespective of the amount or value of such claims if the issues involved are of a complicated nature. The General Manager shall be the sole judge to decide whether the issues involved are of a complicated nature or not. In the event of the two Arbitrators being divided in their opinions, the matter under disputes will be referred to an Umpire to be appointed in the manner laid down in Clause 3(b) for his decision.
(3)(a)(iii) ............
(3)(a)(iv) ............
(3)(b) For the purpose of appointing "two arbitrators"
as referred to in sub-clause (a)(ii) above the Railway will send a panel of more than three names of Gazetted railway officers of one or more departments of the Railway to the Contractor who will be asked to suggest to the General Manager one name out of the list for appointment as the Contractor's nominee. The General Manager, while so appointing the Contractor's nominee, will also appoint a second arbitrator as the Railway's nominee either from the panel or from outside the panel, ensuring that one of the two arbitrators so nominated is invariably from the Accounts Department. Before entering upon the reference the two Arbitrators shall nominate an Umpire who shall be a Gazetted Railway Officer to whom the case will be referred to in the event of any difference between the two arbitrators. Officers of the Junior Administrative grade of
the Accounts Department of the Railways shall be considered as of equal status to the officers in the intermediate administrative grade of other departments of the Railway for the purpose of appointment as arbitrator.
(3)(c)............
(3)(d)............
(3)(e)............
(3)(f) Subject as aforesaid, Arbitration Act 1940 and the Rules thereunder and any statutory modification thereof shall apply to the Arbitration proceedings under this clause."
3. Mr.Chinoy, learned counsel appearing for the petitioner,
strenuously contended that the items / claims in question do
not constitute excepted matters and the respondent's refusal
to appoint the arbitrator is based on a patent misreading as to
the meaning and import of Clause 63. He contended that
Clause 63 of the General Conditions clearly provides that only
matters for which provision has been made for a final and
binding determination in certain specified clauses of the
General Conditions, or in any clause of the Special Conditions,
shall be deemed to be "excepted matters". Learned counsel
submitted that none of the claims falls within any of the
specified clauses of the General Conditions, or those clauses of
the special conditions in which provision has been made for a
final and binding determination / decision by the Engineer-in-
Charge. None of the relevant clauses provides for such claims
not capable of being raised or adjudged by employing such
phraseology as "shall not be payable" or "no claim whatsoever
will be entertained by the Railway" or "no claim will/shall be
entertained". They are not "no claim" or "no liability"
clauses. On the other hand, Ms.Geetanjali Mohan, learned
counsel appearing for the respondent, maintained that almost
all the claims fall in the excepted category and cannot be
referred to the arbitration. She contended that Clause 63
specifically states that matters falling in any clause of Special
Conditions of the contract shall be deemed as "excepted
matters" and consequently the claims are not referable to the
arbitration.
4. Both the learned counsel relied upon the decision of the
Supreme Court in the case of General Manager, Northern
Railways & Anr. v. Sarvesh Chopra reported in AIR 2002
SC 1272. In that case, the Supreme Court construed the very
clause 63 in the context of certain claims raised by the
contractor under certain clauses of the Special Conditions of
Contract. The clauses in question being 9.2, 11.3 and 21.5
read as follows:
"9.2. No material price variation or wages escalation on any account whatsoever and compensation for "Force Majaure" etc. shall be payable under this contract.
11.3. No claim whatsoever will be entertained by the Railway on a/c of any delay or hold up of the works arising out of delay in supply of drawings, changes, modifications, alterations, additions, omissions, omissions in the site layout plans or detailed drawings or designs and or late supply of such materials as are required to be arranged by the Railway or due to any other factor on Railway Accounts.
21.5. No claim for idle labour and/or idle machinery etc. on any account will be entertained. Similarly no claim shall be entertained for business loss or any such loss."
The argument before the Supreme Court was that so long as the
remedy of the decision by someone though he may be an
authority of the Railways is not provided for, the contractor's
claim cannot be left in lurch by including the same in the
"excepted matters". The Supreme Court held as follows:
"7. A bare reading of Clause 63 shows that it consists of three parts. Firstly, it is an Arbitration Agreement requiring all disputes and differences of any kind whatsoever arising out of or in connection with the contract to be referred for adjudication by arbitration, by the Railways, on a demand being made by the
contractor through a representation in that regard. Secondly, this agreement is qualified by a proviso which deals with 'excepted matters'. 'Excepted matters' are divided into two categories: (i) matters for which provision has been made in specified clauses of the General Conditions, and (ii) matters covered by any clauses of the Special Conditions of the Contract. Thirdly, the third part of the clause is a further proviso, having an overriding effect on the earlier parts of the clause, that all 'excepted matters' shall stand specifically excluded from the purview of the Arbitration Clause and hence shall not be referred to arbitration. The source of controversy is the expression "matters for which provision has been made ... in any clauses of the Special Conditions of the contract shall be deemed as 'excepted matters' and decisions thereon shall be final and binding on the contractor." It is submitted by the learned counsel for the respondent that to qualify as 'excepted matters' not only the relevant clause must find mention in that part of the contract which deals with special conditions but should also provide for a decision by an authority of the Railways by way of an 'in-house remedy' which decision shall be final and binding on the contractor. In other words, if a matter is covered by any of the clauses in the Special Conditions of the contract but no remedy is provided by way of decision by an authority of the Railways then that matter shall not be an 'excepted matter'. The learned counsel supported his submission by reading out a few clauses of General Conditions and Special Conditions. For example, vide Clause 18 of General Conditions any question or dispute as to the commission of any offence or compensation payable to the Railway shall be settled by the General Manager of the Railway in such manner as he shall consider fit and sufficient and his decision shall be final and conclusive. Vide Clause 2.4.2.(b) of Special Conditions a claim for compensation arising on account of dissolution of contractor's firm is to be decided by Chief Engineer (Construction) of the Railway and his decision in the matter shall be final
and binding on the contractor. Vide clause 12.1.2. of Special Conditions a dispute whether the cement stored in the godown of the contractor is fit for the work is to be decided by the Engineer of Railways and his decision shall be final and binding on the contractor. The learned counsel submitted that so long as the remedy of decision by some one though he may be an authority of the Railways is not provided for, the contractor's claim cannot be left in lurch by including the same in 'excepted matters'. We find it difficult to agree.
8. In our opinion those claims which are covered by several clauses of the Special Conditions of the Contract can be categorized into two. One category is of such claims which are just not leviable or entertainable. Clauses 9.2., 11.3 and 21.5 of Special Conditions are illustrative of such claims. Each of these clauses provides for such claims being not capable of being raised or adjudged by employing such phraseology as "shall not be payable", "no claim whatsoever will be entertained by the Railway", or "no claim will/shall be entertained". These are 'no claim', 'no damage', or 'no liability' clauses. The other category of claims is where the dispute or difference has to be determined by an authority of Railways as provided in the relevant clause. In such other category fall such claims as were read out by the learned counsel for the respondent by way of illustration from several clauses of the contract such as General Conditions Clause 18 and Special Conditions Clause 2.4.2.(b) and 12.1.2. The first category is an 'excepted matter' because the claim as per terms and conditions of the contract is simply not entertainable; the second category of claims falls within 'excepted matters' because the claim is liable to be adjudicated upon by an authority of the Railways whose decision the parties have, under the contract, agreed to treat as final and binding and hence not arbitrable. The expression "and decision thereon shall be final and
binding on the contractor" as occurring in Clause 63 refers to the second category of 'excepted matters'.
5. It is apparent from the above observations that Clause 63
contemplates two categories of "excepted matters". The first
category is an "excepted matter" because the claim as per the
terms and conditions of the contract is simply not
entertainable. The second category of claims fall within the
"excepted matters" because the claim is liable to be
adjudicated upon by an authority of the Railways whose
decision the parties have, under the contract, agreed to treat
as final and binding and hence not arbitrable. In the light of
the decision of the Supreme Court what needs to be
determined is whether the claim preferred by the petitioner for
which the petitioner is invoking arbitration, falls in either
category of "excepted matters".
6. The first claim of the petitioner pertains to Welded Wall Beams
which the petitioner was to fabricate pursuant to Clause 8.14
of the Special Contract Conditions and Instructions to Tenders,
("Special Conditions"). The respondent had agreed to supply
the Rolled Steel Joists (150 x 150) for fabrication of the steel
supports / wall beams under item NS.3 of the BOQ. However,
on account of short supply of Rolled Steel Joists sections during
October, 2000 to March, 2001, the Engineer-in-Charge directed
the petitioner to use generated steel scrap pieces (1.0 m in
length) for fabrication of the wall beams, instead of full length
Rolled Steel Joists. This resulted in the petitioner incurring
additional expenditure in welding and fabricating of wall
beams. Clause 8.14 is reproduced below:
"8.14 Fabrication : Fabrication of the steel support shall be done in accordance with the drawings. Workmanship and finish shall be comparable to the best general practice in modern steel fabrication shop. All ring beam segment shall be fabricated in such a manner that required number of segment selected at random may be easily assembled and bolted together to form a complete support of specified dimensions. Finished diameters of the holes in the beams, butt plates splice plate or wall plates joints etc. shall not be less than that shown in the drawing which is more by 1.5 mm than normal diameter of the bolt. The holes will be drilled and reamed with the parts to be bolted in assembled position."
7. The second item is cutting & threading of tie rods. Item NS-3
of the BSQ required the Railway to supply free of cost, tie rods
which were required to be used by the petitioner for the
manufacture and fabrication of permanent steel supports. The
respondent, however, supplied plain rods instead of tie rods.
The petitioner, therefore, had to incur additional expenses for
fabrication of tie rods by cutting and threading the plain rods.
NS-3 states:
"NS-3 : Manufacturing, leading and erecting permanent steel supports in tunnels as per approved drawings including cutting drilling, welding/riveting cold/hot bending threading, leveling, aligning, fixing in position with all nuts and bolts and washers, providing timber struts and presstressing by blocking against rock/soil including all lead and lifts from fabrication yard to erection site. Railway will supply free of cost only steel sections such as joists, bars, plates, tie rods of sizes at Railway Godown at Manwal / Jammu Railway station or from any other suitable stores within the project site. All other materials including nuts, bolts, washers shall be arranged by contractor at his own cost."
8. The third claim is for overbreak in bottom lining. Clause 7.9.1
of the Special Conditions of the Contract, stipulated for
payment lines i.e. the limit upto which the contractor would be
paid, irrespective of whether the actual excavation fell outside
these lines, except in the case of the natural cleavages etc. An
overbreak occurs when a break or excavation takes place
beyond the 'limit' / 'payment lines' specified. In the present
case the payment line was defined as a measure (normally and
readily) 150 mm beyond the minimum excavation line, which
marked the minimum excavation that the contractor was
required to carry out. Overbreaks that occur on account of the
contractor's fault were not to be paid for by the respondent.
On the other hand, overbreaks which occurred on account of
adverse geological conditions of the rock, known as geological
overbreaks, were to be paid for by the respondent. According
to the petitioner overbreaks occurred to the bottom, sides and
crown portion of the tunnel on account of adverse geological
conditions: concealed joints, inclined bedding planes, faults
and heavy seepage due to poor rock configuration. The
petitioner had to incur additional expenditure on removing the
loose rock fragments and mud and in putting additional
concrete in such overbreaks. The relevant Clause 7.9.4 which
deals with overbreak in bottom lining reads as follows:
"7.9.4 : Geological overbreak
'Geological overbreak' consists of that portion of the overbreak outside a line parallel to and 100 mm beyond the "payline", the occurrence of which, as per the decision of Engineer-in-Charge, is an unavoidable result of adverse geological conditions due to concealed joints faults and other structural defects in rock and not due to lack of reasonable care and skill in excavation on the part of the contractor."
9. The following claim is overbreaks in 300 mm band. This covers
overbreaks beyond the pay line of 150 mm (and upto 300 mm)
which could not be avoided on account of adverse geological
conditions in the rock (concealed joints, faults and other
structure defects). The petitioner claimed payment for the
additional excavation and concreting done between pay line of
150 mm and upto 300 mm, from the respondent at the rate
specified in Clause 7.9.6 and 7.9.7 respectively. The Clauses
are reproduced below:
"7.9.6 payment for "Geological overbreak"
Payment for "Geological overbreak" shall be made at ½ (half) of the basic rates for tunnel excavation.
7.9.7 When the excavation of tunnel is in progress, if directed by Engineer-in-Charge, contractor shall backfill portions of 'over break' and 'geological overbreak' as defined in para 7.9.3 and 7.9.4 by concrete of suitable quality as approved by Engineer- in-Charge. Measurement and payment of such a backfill concrete shall be regulated in accordance with relevant provisions made under item of concrete (measurement & payment)."
10. The next claim is balance quantity of geological overbreak. It
is the case of the petitioner that during the course of the
excavation overbreaks occurred to the sidewalls and the
trolley refuges. These were on account of adverse geological
conditions in the rock and, therefore, constituted "geological
overbreaks" and were admittedly "outside a line parallel to
300 mm beyond the 'pay line' ". According to the petitioner
the respondent was liable to compensate the petitioner for
these "geological overbreaks". Clause 7.9.4 of the Special
Conditions of Contract reads as follows:
"7.9.4 : Geological overbreak
'Geological overbreak' consists of that portion of the overbreak outside a line parallel to and 100 mm beyond the "payline", the occurrence of which, as per the decision of Engineer-in-Charge, is an unavoidable result of adverse geological conditions due to concealed joints faults and other structural defects in rock and not due to lack of reasonable care and skill in excavation on the part of the contractor."
11.In none of the above clauses being Clause 8.14, Clause NS.3,
Clause 7.9.1, Clause 7.9.4 and Clauses 7.9.6 and 7.9.7 it is
provided that the claim of the contractor shall not be
entertainable. Further, none of these clauses provide for
determination of the claim by officer of the Railway and attach
any finality to such decision. Thus, the claims do not fall in
either of the excepted categories as held by the Supreme
Court in General Manager, Northern Railways & Anr. v. Sarvesh
Chopra's case.
12.Claims No.6 to 8 are relating to the difference between tender
and negotiated rates. It is the case of the petitioner that
during the course of the work the quantities of eight items of
work specified in the schedule to the tender exceeded the
amounts specified in the tender by the respondent. For the
purpose of fixing the rate payable to the petitioner for the
additional quantities of these eight items of work, the parties
met for negotiations and under duress, the petitioner was
constrained to agree to such rates under protest and without
prejudice to its contentions and its right to claim the rates
specified in the Agreement. It is seen from the record that the
petitioner had signed the negotiations under protest and
without prejudice to its contentions and its right to claim the
contract rates even for the increased quantities of work. The
contention of the respondent is that renegotiation of rates
results in supplementary contract which is not covered by
Clause 64 of the General Conditions. The contention is stated
only to be rejected. Merely because the parties had re-
negotiated the rates does not mean that a new contract has
come into being. It is clearly seen from the record that all
these negotiations and re-negotiations were part of the same
contract.
13.The next claim is for refund of works contract tax which
according to the respondent is not covered by excepted
matters. Lastly, there is claim for interest on delayed
payments. All these issues will have to be decided by the
arbitral tribunal appointed in accordance with Clause 64 of the
General Conditions. Learned counsel appearing for the
respondent has placed on record a list of the panel of twelve
Railway Gazetted Officers nominated by the General Manager.
Out of the three, one has to be from the accounts department.
By consent of the parties, I constitute a panel of Shri Tanvir
Ahmed - FA&CAO/FOIS, Shri Nikhil Pandey - CEGE and Shri
D.D. Singh - CWM/GZB as the Arbitral Tribunal to adjudicate
upon the disputes between the parties. The petition stands
disposed of accordingly.
CHIEF JUSTICE August 21, 2009 "dk/nm"
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!