Citation : 2009 Latest Caselaw 3287 Del
Judgement Date : 21 August, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP No.176/2009
% Date of decision: 21.08.2009
NATIONAL HIGHWAYS AUTHORITY OF INDIA ...Petitioner
Through: Mr. Sandeep Sethi, Sr. Advocate with
Ms. Padma Priya, Advocate
Versus
SHELADIA ASSOCIATES, INC. ..Respondent
Through: Mr. Janaranjan Das, Mr. Swetaketu
Mishra & Mr. P.P. Nayar, Advocates
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? Yes
2. To be referred to the reporter or not? Yes
3. Whether the judgment should be reported Yes
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. This petition under Section 20 r/w Section 2(6) of the
Arbitration Act, 1996 is preferred for a direction to be issued to the
arbitrator to hold the arbitration proceedings at Delhi as provided in
the written agreement between the parties. This court, vide ex-parte
order dated 2nd April, 2009 which continues to be in force, has stayed
the proceedings before the arbitrator. The respondent has contested
the petition, inter-alia on the ground of maintainability thereof.
2. The parties hereto are parties to a contract dated 31st January,
2001. Though in the said contract, the place of execution thereof has
not been stated but the address therein of the petitioner is of New
Delhi and of the respondent of USA. The contract is signed by an
official of the petitioner whose rubber stamp bears the address of
New Delhi. From the contract, it is not clear as to where the same
has been signed on behalf of the respondent. However, since it has
been signed on behalf of the petitioner as well as the respondent on
the same day, it is presumed to have been executed at New Delhi. In
any case, the address given of the petitioner in the said agreement
for service of all notices etc. is that of New Delhi and the address so
given of the respondent is of USA. This court thus is the court within
the meaning of Section 2(e) of the Act. The respondent also has
neither in its reply nor its arguments disputed the territorial
jurisdiction of this court.
3. The contract between the parties is for the respondent to
provide the construction supervision services to the petitioner for
development of the Golden Quadrilateral constituting inter-alia the
road on NH-5 & NH-60 from Chennai to Calcutta and, particularly
four laning and strengthening of the stretches between Khurda to
Bhubaneswar, Chandikhole to Bhadrak and Bhadrak to Balasore all
in the State of Orissa.
4. The contract provides for settlement of disputes by arbitration.
The arbitration was agreed to be either of a sole arbitrator or of an
arbitration panel composed of three arbitrators; where the parties
agreed that the dispute concerns a technical matter, they were given
liberty to agree to appointment of a sole arbitrator and failing such
agreement within 30 days, procedure is provided for the President,
Indian Roads Congress, New Delhi to furnish five nominees of which
the parties were entitled to select one; if the parties could not select
out of the said nominees also, the sole arbitrator is to be appointed
by the President, Indian Roads Congress, New Delhi; however,
where the parties do not agree that the dispute concerns a technical
matter, each party was to appoint an arbitrator with the two
arbitrators jointly appointing the third arbitrator; if the two
arbitrators are unable to agree on the third arbitrator, the same was
agreed to be appointed by the Secretary, Indian Council of
Arbitration, New Delhi (ICA). It is further the agreement that if
either parties fails to appoint its arbitrator within 30 days after the
other has appointed its arbitrator, the party which has appointed the
arbitrator may apply to the ICA to appoint a sole arbitrator for the
matter in dispute. It is further the agreement in Clause 8.2.5 of the
Special Conditions of contract as under:-
"8.2.5 Miscellaneous
In any arbitration proceedings hereunder:
a. Proceedings shall, unless otherwise agreed by the parties, be held in Delhi
b. ............."
5. It is the case of the respondent that disputes and differences
having arisen between the parties and the parties having not
considered the same as technical, the respondent appointed its
arbitrator and called upon the petitioner to nominate its arbitrator;
upon failure of the petitioner to so appoint the arbitrator, the
respondent approached the ICA which vide its letter dated 10th
September, 2008 appointed Mr. B.C. Tripathi, retired Chief
Engineer-cum-Member (Technical), Arbitration Tribunal C/8 404
Radhika Tower, Tankapani Road, Bhubaneswar, to act as the sole
arbitrator in the case.
6. The respondent had also filed Writ Petition (C) No.3765/2008
in High Court of Orissa, inter-alia for directions to the petitioner to
stop deducting amounts towards the damage liability from the bills
of the respondent. The petitioner took inter-alia a stand in the said
proceeding before the Orissa High Court that Shri B.C Tripathi
aforesaid having been appointed as the arbitrator and the arbitration
being underway, the writ was not maintainable.
7. The controversy which has led to the filing of the present
petition is as to the venue of arbitration. The arbitrator appointed by
the ICA, being based at Bhubneshwar issued notice dated 18th
October, 2008 for holding the first sitting of arbitration at
Bhubaneswar on 4th November, 2008. The order of the arbitrator of
that date shows that though the said notice was served on the
petitioner but none on behalf of the petitioner appeared before the
arbitrator. The arbitration proceedings were adjourned by issuing
certain directions. At the end of the said order, it is recorded "till
further decision, the place of arbitration will continue to remain at
the Conference Hall of Radhika Tower, Tankapani Road,
Bhubaneswar".
8. The next hearing before the arbitrator was fixed for 4th
December, 2008. The Project Director of the petitioner at
Bhubaneswar attended the said hearing. The order of the arbitrator
of that date shows that the official of the petitioner raised certain
points before the arbitrator on that date. It is the case of the
petitioner that one of the points raised by it before the arbitrator on
that date was of the agreement between the parties providing for the
venue of arbitration at New Delhi and the arbitrator was thus
requested to hold the arbitration proceedings at New Delhi.
However, the arbitrator at the end of the order of the said date again
recorded as aforesaid that till further decision the place of
arbitration shall remain at Bhubaneswar.
9. The petitioner filed an application dated 23rd December, 2008
before the arbitrator in which also it was stated that in the 2 nd
hearing the question of venue of arbitration was raised. In the said
application, it was also stated that the hearings held at Bhubaneswar
were not legal and valid. The petitioner also requested the arbitrator
to treat the pleas taken in the said application as preliminary
objections and deal with the same first. Though in the body of the
said application, no provision of law is mentioned but in the letter
dated 23rd December, 2008 of the petitioner under cover of which the
said application was forwarded, the application is described to be
under Section 16 of the Act.
10. The petitioner besides the said application filed another
application dated 1st January, 2009 before the arbitrator to intimate
the date and venue of the arbitration at New Delhi, to enable the
petitioner to participate in the proceedings.
11. The third sitting was held by the arbitrator at Bhubaneswar on
3rd January, 2009. None appeared on behalf of the petitioner before
the arbitrator on that date. With respect to the applications aforesaid
of the petitioner the arbitrator preserved the same for consideration
on compliance of the directions earlier issued regarding fee etc. and
which had not been complied with by the petitioner. The next date
of sitting was peremptorily fixed on 19th January, 2009 again at
Bhubaneswar. The copy of the order dated 3rd January, 2009 was
forwarded to the petitioner also.
12. On the next date before the arbitrator i.e. 19th January, 2009
also the petitioner remained unrepresented. The arbitrator thus
proceeded ex-parte against the petitioner. No reference in the
proceeding of that date is made to the applications aforesaid of the
petitioner. The case was adjourned to 21st January, 2009 and
intimation thereof sent to the petitioner also.
13. The petitioner continued to abstain from appearing before the
arbitrator at Bhubaneswar. On 21st January, 2009 it appears that the
respondent filed an objection dated 3rd January, 2009 before the
arbitrator to the application dated 23rd December, 2009 of the
petitioner. With respect to the venue of arbitration, it was stated in
the said opposition that the petitioner had already taken part in the
arbitration proceedings and had also not raised any question of
jurisdiction or competency of the arbitral in the writ petition before
the Orissa High Court also, and in fact it was owing to the plea of the
petitioner, of the arbitrator having been appointed that the writ
petition was disposed of; it was further contended that the cause of
action for the dispute had arisen within the State of Orissa and as
per the law jurisdiction could not be limited merely as per the
condition of agreement; that the venue of arbitration though fixed
prior to the disposal of the writ petition had also not been challenged
by the petitioner before the High Court - rather the petitioner had
admitted the said venue; that the ICA while appointing the sole
arbitrator had taken into consideration that the arbitrator may be
required to inspect documents, place of performance of contract,
convenience of parties and all of which was at Bhubaneswar and in
the absence of any compelling reason to insist on Delhi as the venue
of arbitration meetings, the petitioner ought to abide by the decision
of the Arbitral Tribunal as to the venue of the meeting of the
arbitration. It was further pleaded that both the parties had their
offices at Bhubaneswar, execution of the work was in Orissa and
thus the arbitration proceedings should continue at Orissa only.
14. The arbitrator in the 5th sitting held at Bhubaneswar on 21st
January, 2009 and from which the petitioner continued to abstain,
merely recorded that "the objection filed by the respondent stands
accepted and the petition filed by the petitioner (apparently of 23 rd
December, 2008 and 1st January, 2009) without any evidence is
dismissed". It was further held that challenging the arbitrator is
equal to challenging the appointing authority and the party
aggrieved on this account is at liberty to move the Competent
Authorities for appropriate actions like withdrawal of appointment of
arbitrator/replacement of arbitrator. The case was adjourned to
24,25&26th February, 2009 at Bhubaneswar only.
15. The hearings before the arbitrator continued thereafter in the
absence of the petitioner until the same were stayed vide ex-parte
order dated 2nd April, 2009 (Supra) of this court.
16. The senior counsel for the petitioner has drawn attention to
Section 20 (1) of the Act which gives freedom to the parties to agree
on the place of arbitration; Section 20 (2) empowers the Arbitral
Tribunal to determine the place of arbitration having regard to the
circumstances of the case including the convenience of the party
only "failing any agreement referred to in sub-Section (1)". It has
further been contended that the arbitrator being a creature of the
agreement between the parties has no jurisdiction to hold hearings
at a place other than the place agreed upon by the parties. It is
further highlighted that in the agreement between the parties, while
providing for the venue of arbitration at Delhi, Delhi is underlined.
Attention is also invited to para 30 of the judgment of this court in
Alcove Industries Ltd. Vs. Oriental Structural Engineer's Ltd.
(2008) 1 ARBLR 393 (Delhi) on the basis whereof it is urged that the
courts ought to, where it is so warranted nip any illegality being
committed by the Arbitral Tribunal in the bud rather than allow the
arbitration proceedings to go on and to deal with the same at the
stage of Section 34 of the Act. It is urged that procedure is the
handmaid of justice and the order sought by the petitioner is in aid of
justice and this court ought not to refrain from exercising
jurisdiction to stop the illegality being committed by the Arbitral
Tribunal and the action of the Arbitral Tribunal in contravention of
the agreement between the parties. It is argued that such conduct
ought not to be permitted to be perpetuated and powers of the
courts cannot be stifled. It is further contended that the Supreme
Court in Sanshin Chemicals Industry Vs. Oriental Carbons &
Chemicals Ltd. (2001) 3 SCC 341 has held that a decision
regarding the venue of arbitration could be assailed even in an
appeal under Section 34 of the Act. It is further argued that in any
case the matter is not res integra in view of the judgment of the
single judge of this court in Jagson Airlines Ltd. Vs. Bannari
Amman Exports Pvt. Ltd. 2003 (2) Arb. LR 315 (Delhi) where the
order of the Arbitral Tribunal fixing the venue of arbitration
proceedings at a place other than that agreed by the parties was set
aside. It was further argued that this court in Sharma Enterprises
Vs NBCC Ltd. (2008) 9 AD Delhi 571 has also leaned in favour of
the court under Section 14 of the Act being empowered to terminate
the mandate of the arbitrator. It was contended that in the present
case in-spite of the petitioner having taken objection to the venue of
arbitration on the very first opportunity, the arbitrator has not
decided on the same and is continuing to hold the proceedings at a
place not agreed upon by the parties.
17. Per contra, the counsel for the respondent has made
submission under four heads. Firstly, it is contended that the petition
is not maintainable. Secondly, it is contended that the petitioner has
by its conduct, express and/or implied agreed to the arbitrator
holding the proceedings at Bhubaneswar and has filed the present
petition as an after though. Thirdly, it is contended that since the
arbitrator is at Bhubaneswar, all the records are at Bhubaneswar, it
is convenient that the arbitration proceedings be held at
Bhubaneswar only. Lastly, it is contended that the clause in the
agreement providing for the venue of the arbitration at Delhi does
not provide for the said venue exclusively and on the same reasoning
as applied to a clause qua the jurisdiction of the courts, the
arbitrator is entitled to hold the proceedings at Bhubaneswar also, in
the exercise of his power under Section 20(2) of the Act.
18. On the aspect of maintainability, it is contended that the
judgment of this court in Jagson Airlines Ltd. (Supra) is no longer
good law in view of subsequent decision of the seven judge bench of
the Supreme Court in SBP & Co. Vs. Patel Engineering Ltd.
(2005) 8 SCC 618. Attention is drawn to the summary of conclusions
arrived at in the said judgment in para 142, to sub-paras (iv) to (vi)
where it has been laid down that the Arbitral Tribunal has power to
rule on its own jurisdiction under sub-Section (1) of Section 16 of the
Act; where the Arbitral Tribunal holds that it has jurisdiction, it shall
continue with the arbitral proceedings and make the arbitral award;
remedy available to the party aggrieved is to challenge the award in
accordance with Section 34 or Section 37 of the Act. It is argued that
the application in which the petitioner raised the plea of the venue of
arbitration was described by the petitioner itself in the covering
letter to the said application as under Section 16 of the Act, the
arbitrator has already dealt with the said application in the order
dated 21st January, 2009 (Supra) wherein the said objection of the
petitioner has been rejected. It is argued that the remedy, if any, if
the petitioner is now only under Section 34 of the Act and the court
is not empowered to interfere before that.
19. It is further contended that the reliance by the senior counsel
for the petitioner during the hearing on Section 14 of the Act is
misconceived in as much as the said plea was neither taken before
the arbitrator nor pleaded and cannot be permitted to be taken
orally.
20. On the argument of convenience, the submissions have already
been noted herein above.
21. On the petitioner having expressly or impliedly consented to
the venue of arbitration at Bhubaneswar, it is contended that the ICA
had appointed the arbitrator prior to the petitioner filing the counter
affidavit in the Orissa High Court; in the said counter affidavit no
plea was taken that the arbitrator was at Bhubaneswar while the
agreement was for arbitration at Delhi; it is further contended that in
fact prior to the disposal of the said writ petition the arbitrator had
already issued a notice for first hearing of arbitration to be held at
Bhubaneswar; the petitioner still did not raise the said aspect in the
writ proceedings and allowed the writ petition to be disposed of. In
this regard only, it is further pointed out that the petitioner had vide
its letter dated 2nd December, 2008 appointed its Project Director at
Bhubaneswar to represent the petitioner in the case and from the
appointment of an officer at Bhubaneswar (and not at Delhi) it is
apparent that the petitioner also intended the arbitration
proceedings at Bhubaneswar. It is further contended that the
petitioner participated in the second hearing before the arbitrator
and thereby also consented to the arbitration hearings at
Bhubaneswar only. It is further argued that this court ought not to
be swayed by the pleas of the conduct of the arbitration being
contrary to the agreement as much as similar questions can arise in
a large number of other arbitrations and which if allowed would lead
to courts interfering in arbitral proceedings otherwise than as
permitted under the statute.
22. The senior counsel for the petitioner has in rejoinder
contended that the agreement provides for the venue of arbitration
at Delhi, "unless otherwise agreed by the parties". Such agreement
has to be in writing only and cannot be by conduct. It is further
contended that there cannot be question of any acquiescence in as
much as the objection was taken to the venue on the very first date.
It is also contended that the arbitrator has not dealt with the said
aspect and has not treated the said objection as under Section 16 of
the Act. It is also contended that the use of the word "only" or
"exclusively" is not essential for vesting exclusive jurisdiction to a
certain place. Reliance in this regard is placed on Jatinder Nath Vs.
Chopra Land Developers Pvt. Ltd. AIR 2007 SC 1401. It is
argued that in the present case the intent to hold the arbitration
proceedings at Delhi is clear from the agreement of the parties.
23. The aspect of maintainability of the present petition has
obviously to be considered first in as much as if the petition is found
to be not maintainable, even if this court were to agree with the
contention of the petitioner on merits, the court would be unable to
grant any relief to the petitioner.
24. The petition as filed is under Section 20 & Section 2(e) of the
Act. Neither of the said provisions is of a nature whereunder any
role is attributed to the "court". The said provisions are not
actionable and the petition does not lie thereunder. However, the
nomenclature under which the a petition is filed is irrelevant, if
otherwise is found to be maintainable in law.
25. The effect of Section 5 of the Act barring the courts from
intervening in arbitral proceedings except where so provided in the
Act, need not be restated. In this case, as will be clear from the
above, the respondent is a foreign party. The arbitration under
Section 2 (f) relating to disputes arising out of commercial legal
relationship where at least one of the parties is a body corporate
which is incorporated in any country other than India, is an
"international commercial arbitration". At one stage, it was
considered whether the provisions of Section 5 and Section 20 would
be applicable to such arbitration. However, Section 2 (2) makes part
I of the Act applicable where the place of arbitration is in India. In
the present case there is no dispute that the place of arbitration is in
India and hence part I i.e. Sections 2 to 43 apply.
26. Though the counsels have during the hearing referred to
Section 14 & Section 16 r/w 37 only whereunder courts can
interfere, I had during the course of hearing, in the light of the
judgment of a single judge of the Bombay High Court in
Maharashtra State Electricity Board Vs. Datar Switch Gears
Ltd. MANU/MH/1187/2002 also drawn attention of the counsels to
Section 9 (ii) (e) of the Act, whereunder the court can be approached
for "such other interim measure of protection as may appear to be
just and convenient". Question was posed as to whether the said
provision can be said to permit interference by the courts.
27. First the applicability of Section 16 r/w Section 37 will be
considered in as much as if it is found that the plea of the petitioner
as to the venue of arbitration was under Section 16 of the Act and/or
if the order of the arbitrator thereon is under Section 16 of the Act,
then in view of the legislative provisions i.e. of Sections 16(5) and (6)
of the Act, the remedy, if any, of the petitioner would be at the stage
of Section 34 only and not before that. In the face of the legislative
provisions, no inherent powers of the court can also be invoked in
such as case.
28. I had during the hearing inquired from the counsel for the
respondent as to how the plea of venue of arbitration could be said
to be a plea of the jurisdiction of the arbitrator or with respect to the
existence of the arbitration agreement. No arguments were
addressed on this aspect. The petitioner in contending that the
arbitration proceedings be held at Delhi in accordance with the
agreement cannot be said to be calling upon the arbitral tribunal to
rule on its jurisdiction. Similarly the existence or validity of the
arbitration agreement was/is not being questioned by the petitioner.
The petitioner in insisting that the arbitration proceedings be held at
Delhi was rather seeking enforcement of the arbitration agreement.
Section 16 (3) refers to the Arbitral Tribunal exceeding the scope of
its authority. However, the same has to be read in conjunction with
Section 16(1) i.e. whether a particular dispute is arbitrable or not
and would not include objection as to the venue of arbitration. Thus,
in my view Section 16 is not attracted to such a plea and thus even if
it were to be said that the arbitrator had rejected the said plea, the
provisions of Section 16 (5) and (6) would not apply.
29. I also do not find any merit in the contention of the counsel for
the respondent that the petitioner in the covering letter of the
application dated 28th December, 2008 having described the
application in which the plea of venue was taken to be under Section
16 of the Act is now estopped from contending otherwise. Whether a
plea falls within the ambit of Section 16 of the Act or not is a
question of law and merely because the petitioner described the
same as under Section 16 of the Act would not make the plea if
otherwise not falling under Section 16 to fall thereunder to enable
the respondent to contend that the remedy only at the stage of
Section 34 is available with respect to the decision rejecting the
same.
30. I also do not find that the Arbitral Tribunal has taken any
decision on the said plea of the petitioner. The petitioner had in the
applications dated 28th December, 2008 and 1st January, 2009 taken
several pleas including the plea as to the venue. Under Section 28
(2) the Arbitral Tribunal is required to decide ex aequo et bono or as
amiable compositeur only if the parties expressly authorize so.
Russell on Arbitration 21st Edition at page 163 reads as under:
"The Tribunal has a duty to decide a dispute in accordance with the legal rights of the parties, rather than in what the tribunal considers a fair and reasonable way, unless there is specific agreement between the parties to the contrary. The tribunal may be specifically instructed by the arbitration agreement to decide the disputes on some basis other than the law; an agreement to this effect has generally become known as an 'equity clause'. For example, the parties may agree that the tribunal is to decide the dispute in accordance with concepts variously known as 'honourable engagement', 'amiable compositeur' 'equity', 'ex aequo et bono', the 'general principles of law recognized by civilized nations' or the 'lex mercatoria'. The expression 'lex mercatoria' is not found in arbitration clauses, and some commentators have doubted whether it has any meaning. Those who do assign it a meaning differ
as to whether it is a separate body of international commercial law or equivalent to freedom from strict legal constraint. Various wordings are encountered in arbitration agreements, and each has to be carefully interpreted."
31. Black's Law Dictionary defines the term 'Ex aequo et bono' as
'in justice and fairness' or according to equity and good conscience.
The word, 'amiable compositeur' is a French term. It means a person
who adopts a flexible approach brimful with fairness and reality.
Section 46 (i) (b) of the English Arbitration Act 1996 permits the
arbitrator to decide the dispute in accordance with such other
considerations as are agreed or determined. RUSSELL on
ARBITRATION, 21st Edn. at page 164 states as under on the subject.
"The courts will interpret the new statutory provisions allowing a tribunal to decide a dispute in accordance with such other considerations as are agreed or determined as obliging them to uphold equity clauses. In agreeing that a dispute shall be resolved this way, the parties are in effect excluding any right to appeal to the court, there being no question of law to appeal. Special transitional provisions apply to equity clauses to prevent retrospective changes to their meaning, Section 46(i)(b) of the Arbitration Act, 1996 does not apply to arbitration agreements that were made before the Act came into force (on January 31, 1997)."
Sir Michael J. Mustill and Stewart C. Boyd in 'Commercial
Arbitration' IInd Edn. at page 606 state as follows:
"A commercial arbitration agreement may contain a stipulation or a clause by which arbitrators are empowered not to apply strict or settled principles of law in the settlement of a dispute referred to them, but instead to settle such dispute by the application of what they may deem to be fair and reasonable. In other words, such arbitrators are then meant to act as amiables compositeurs. Considering that an agreement between the parties to an arbitration reference constitutes an essential basis for the establishment of conduct of a commercial arbitration, one would expect any such stipulation on clause in an arbitration agreement to be observed by arbitrators without judicial intervention. Obviously commercial arbitrators cannot be presumed to be entitled
to settle a dispute referred to them by applying what they deem to be fair and reasonable, in the absence of a specific authorization in an arbitration agreement. As an English appellant court Judge had occasion to stress in a recent symposium on international commercial arbitration. 'The arbitrator must not act as amiable compositeur unless authorized to do so."
32. Section 28 (3) also mandates the arbitral tribunal to decide in
accordance with the terms of the contract. It may be highlighted that
Section 28 is applicable to all stages of proceedings before the
arbitral tribunal and not merely to the making of the award. Under
Section 31 also, though applicable to an award, the arbitrator is
required to state reasons for its decisions. This was a change
effected in the 1996 Act from the 1940 Act whereunder the
arbitrator was not required to give any reasons. The requirement of
reasons was perhaps introduced so as to give more efficacy and to
strengthen the arbitration and to make it a alternative forum for
adjudication of disputes. In my opinion, the requirement of giving
reasons also extends to other stages of arbitral proceedings. Even if
it is to be held that the arbitrator has in the year on 21st January,
2009 also dealt with the plea of the petitioner qua the venue of
arbitration, I find that the arbitrator has not given any reasons
whatsoever for continuation to hold proceedings at Bhubaneswar in
the face of the agreement between the parties of the place of
arbitration being Delhi. This leads me to hold that the arbitrator has
not given any decision whatsoever even if the plea of the petitioner
as to venue is treated to have been made under Section 16 of the
Act.
33. Having held that the plea aforesaid was not under Section 16,
and having also found that Sections 20 and 2 (e) whereunder the
petition has been filed are not actionable, the next question is
whether Section 14 relied upon at the time of argument can be
permitted to be relied and if so to what effect.
34. In my view, again merely because the petition is not titled as
under Section 14 of the Act would not bar the petitioner from
contending that the same is maintainable under the said provision or
claims the relief permissible thereunder. On a perusal of Section 14,
I find nothing therein which would prohibit the petitioner from
without having filed the petition under the said provision, contending
that the same to be considered thereunder.
35. The Supreme Court recently in Nawab Shaqafath Khan Vs.
Nawab Imdad Jah Bahadur (2009) 5 SCC 162 has held that the
High Court, on appropriate case being made out and subject to
fulfillment of other requirements, if any, has jurisdiction to convert a
revision application or a writ petition into an appeal or vice versa, in
exercise of its inherent powers.
36. The next question is whether in such a situation it can be said
that the arbitrator has become de jure or de facto unable to perform
his function or for other reasons the arbitrator has failed to act
without undue delay.
37. As noticed above, under Section 28 (3) of the Act the arbitrator
is to act in accordance with the terms of the contract. Axiomatically,
the de jure or de facto inability of the arbitrator to perform his
functions or failure of the arbitrator to act without undue delay has
to be seen in the context of the agreement between the parties. If the
agreement of the parties is for the arbitration proceedings to be held
at Delhi and the arbitrator continues to hold arbitration proceedings
at Bhubaneswar, as in the present case, it would, in my opinion,
amount to the arbitrator being unable to perform his functions or for
other reasons failing to act in terms of the agreement without undue
delay. In the present case, the arbitrator has continued to hold the
proceedings at Bhubaneswar in contravention of the agreement in
writing between the parties and in-spite of objections having been
taken by the petitioner. The action of the arbitrator in-spite the plea
taken in this regard, of continuing to hold the arbitration
proceedings at a place other than Delhi is thus falling within failure
to act in terms of the agreement without undue delay. Thus Section
14 becomes attracted and the mandate of the arbitrator would stand
terminated. However, since the petitioner is persisting that the
arbitrator continues, a controversy within the meaning of Section 14
(2) remains on this ground and the petitioner is entitled to apply to
the court to decide on the said termination.
38. I also do not find any merit in the contention of the respondent
of the petitioner having agreed to the venue of arbitration at
Bhubaneswar. The writ petition preferred by the respondent before
the High Court of Orissa was not concerned with the venue of
arbitration. It was thus not necessary for the petitioner to take the
said plea therein and from the conduct of the petitioner of not taking
the said plea it cannot be said that the petitioner acquiesced in the
venue of arbitration being at Bhubaneswar. Also, merely because the
arbitrator appointed by the ICA was resident of Bhubaneswar did not
necessarily mean that the arbitration proceedings in contravention of
the written agreement between the parties were to be also at
Bhubaneswar. The petitioner cannot be expected to have known at
that time that the arbitrator intended to act in contravention of the
written agreement between the parties and with which he under
Section 28 (3) of the Act was bound. Also, the mere factum of the
arbitrator having given notice of the first sitting of the arbitration at
Bhubaneswar cannot be said to be such a fact which required the
petitioner to in the writ proceedings take up the said cudgels. The
petitioner was till then yet to draw the attention of the arbitrator to
the clause of the agreement aforesaid providing for the place of
arbitration to be at Delhi.
39. Similarly, I do not find the action of the petitioner authorizing
its Project Manager at Bhubaneswar to represent in the said case
cannot be said to be indicative of an intention of the petitioner to
arbitrate at Bhubaneswar. Since, admittedly the works subject
matter of disputes were executed within the area of operation of the
said Director, the said official only being in the know of the facts
would be authorized to act in the said arbitration irrespective of
wherever the place of arbitration may be.
40. I also do not find that the petitioner in any manner participated
in the proceedings at Bhubaneswar. Though, the respondent has
contended that the petitioner had in the second hearing, in which it
had appeared for the first time, not raised the said plea of venue but
in view of the petitioner having in the application filed immediately
thereafter recorded that the said plea was orally taken in the said
hearing, I tend to agree with the version of the petitioner that such
plea was taken before the arbitrator. Thus it is found that the
petitioner had at the first possible opportunity objected to the venue
of arbitration and requested for the venue at Delhi in terms of the
agreement and no case of any express or implied agreement
/acquiescence is made out. The plea of the petitioner having
acquiesced is also negatived from the orders passed by the Arbitral
Tribunal where the next proceeding was ordered at Bhubaneswar for
the time being only. Had the arbitrator taken any decision on the
said plea, such observation would not have appeared in the
successive orders of the arbitrator.
41. The next aspect to be considered is with respect to impact of
the words "only" and "exclusively" missing from the clause providing
for the place of arbitration at Delhi. In my view, the judgments
under Section 20 of the CPC on this aspect are not applicable.
Section 20 deals with a case where more than one courts have
territorial jurisdiction. What the said judgments have held is that the
parties can agree to the jurisdiction of one of such courts. Section 20
of the 1996 Act is however not dealing with the situation of
multifarious venues of arbitration. It gives freedom to the parties to
agree on the place of arbitration. It is not in dispute that in the
present case the parties agreed to Delhi. The parties having so
agreed, were not required to use the words "exclusively" or "only"
with agreed place of arbitration in as much as on such agreement
being reached, the place of arbitration has to be that place only and
none other. Be that as it may, it may also be noted that even the
judgment in Hanil Era Textiles Ltd. Vs. Puromatic Filters (P)
Ltd. (2004) 4 SCC 671 relied upon by the respondent also does not
come to the rescue of the respondent. In that judgment also, it has
been held that even without such words as "only", "exclusively",
"alone", in appropriate cases the maxim expressio unius est exclusio
alterius will apply.
42. Similarly, in the face of such an agreement, the question of
convenience does not arise. The agreement between the parties is
supreme.
43. Though neither counsel drew attention to Section 20 (3) of the
Act, in my view the same requires consideration. After providing in
sub-Section (1) that the parties are free to agree on the place of
arbitration and in sub-Section (2) that failing any agreement, the
place of arbitration shall be determined by the arbitral tribunal, sub-
Section (3) is as under:-
"Notwithstanding sub-section (1) or sub-section (2), the arbitral tribunal may, unless otherwise agreed by the parties, meet at any place it considers appropriate for consultation among its members, for hearing witnesses, experts or the parties, or for inspection of documents, goods or other property."
44. Considerable thought has been expended as to the meaning
thereof in as much as the same starts with a non-obstante provision.
The effect of the non-obstante provision is that notwithstanding any
agreement between the parties the arbitral tribunal may meet at any
place. However the same is again made subject to "unless otherwise
agreed by the parties". I have wondered whether the same gives
supremacy to the Arbitral Tribunal in the matter of place of
arbitration, notwithstanding agreement between the parties or as to
how to reconcile the same with sub-Sections (1)&(2). It cannot be
said that the same is not applicable to arbitration hearings but only
to consultations amongst members of the Arbitral Tribunal in as much
as the same is applicable for hearing witnesses, experts and the
parties as well. The only harmonious interpretation thereof with sub
Sections (1) & (2) is that if the facts & circumstances so demand that
the consultations or recording of statements of witnesses, experts or
the parties has to be at a particular place, owing to the close nexus
thereof with the disputes to be adjudicated, then the Arbitral
Tribunal, notwithstanding the agreement between the parties as to
the place of arbitration, is entitled to hold the proceedings at such
place. However, the same is again made subject to the agreement
between the parties. Such agreement of the parties can only be after
the Arbitral Tribunal has expressed its view to hold the proceedings
mentioned therein at a place other than agreed. At that stage also,
supremacy has been given to the agreement of the parties and the
parties are permitted to with their agreement overrule the
arbitrators at that stage also.
45. However, that stage has not arisen in the present case. The
single member of Arbitral Tribunal has not held that notwithstanding
the agreement of arbitration at Delhi, to enable him to return finding
on the disputes, he is required to conduct any of the stages
mentioned in sub-Section (3) at a place other than Delhi.
46. Though I had during the hearing drawn the attention of the
counsels to Section 9 (ii) (e) but it may be noticed that I have
recently in Shri Krishna Vs. Anand OMP No.597/2008 decided on
18th August, 2009 held that the same cannot be read as giving a
supervisory jurisdiction to the courts over the proceedings before the
Arbitral Tribunal.
47. It is thus found that the Arbitral Tribunal by refusing to hold
the arbitration proceedings at Delhi, in spite of attention having been
invited to the agreement providing so, has become de facto unable to
perform his functions and/or has failed to act without undue delay.
The mandate of the arbitrator thus has to be declared to have stood
terminated.
48. Before parting with the case, I must record that the chain of
events as happened herein is what brings bad name to arbitration.
In spite of the arbitrator having been appointed nearly one year ago,
nothing has been achieved till date and now the mandate of the
arbitrator has to be held to have terminated. I find the Indian
Council of Arbitration, the arbitrator as well as the respondent to be
blamed for the same. The Indian Council for Arbitration being the
appointing authority, in spite of clause in the agreement for the
place of arbitration to be at Delhi, appointed the arbitrator based at
Bhubaneswar. The arbitrator so appointed also in contravention of
the agreement insisted upon holding the arbitration proceedings at
Bhubaneswar and the respondent in contravention of its agreement
in writing supported such stand of the Arbitrator. It appears that the
respondent after obtaining the order from the Orissa High Court
restraining the petitioner from making deductions from the bills of
the respondent was in no hurry in the arbitration proceedings. It
was argued by the respondent before this court that the petitioner is
free to take this objection at the stage under Section 34 of the Act.
When the respondent is aware of the agreement of the place of
arbitration being Delhi and further when Section 34 (2) (a) (v)
permits the award to be set aside on this ground, such action is not
understandable. In the face of the written agreement as to the place
of the arbitration and the same being supreme under Section 20 (1),
it can reasonably be said that even in the event of the petitioner
losing in the arbitration, notice of a petition under Section 34 on this
ground alone is likely to be issued and the arbitral award even, if
any, in favour of respondent would remain in abeyance. It was with
this motive only that on one of the earlier dates it was suggested to
the counsel for the respondent to, for the sake of expediency agree
to the arbitration proceedings at Delhi in accordance with the
agreement. However, the counsel has expressed inability and the
matter was fully argued. It is in these circumstances that finding that
the case can be said to be covered under Section 14 of the Act, I was
loath to allow the respondent and the Arbitral Tribunal to continue
proceedings in contravention of the agreement and to allow the
proceedings to be multiplied in such manner.
49. Arbitration as a mode of settlement of disputes was evolved to
lessen the load on the court and to provide for expeditious resolution
of disputes. However, stand of the parties such as has emerged in
these proceedings is not allowing the same to happen. Though,
undoubtedly the jurisdiction of the courts is limited but wherever
permissible and wherever needed to be exercised for achieving the
said purposes, the courts ought not to fail from exercising their
jurisdiction to serve the said objectives.
50. Thus the petition is treated as one under Section 14 of the Act
and is allowed. The mandate of Mr. B.C. Tripathi is held to have
stood terminated. The parties in accordance with Section 15 (2) of
the Act shall be entitled to appointment of a substitute arbitrator, if
so deemed necessary. In the facts aforesaid, the respondent is also
burdened with costs of Rs.50,000/- of the present petition.
RAJIV SAHAI ENDLAW (JUDGE) August 21, 2009 pp
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!