Citation : 2009 Latest Caselaw 3107 Del
Judgement Date : 11 August, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP No.455/2009 (U/s.34 of the Arbitration Act, 1996) with
IA No. 10038/2009 (u/S 33(2) r/w Section 14(1)(a) of the Arb.
Act, 1996).
% Date of decision: 11th August 2009
National Highways Authority of India ....Petitioner
Through : Mr. Chetan Sharma, Sr. Advocate with
Mr. Vikas Goel, Mr. R.N. Sharma and
Mr. S.K. Tyagi, Advocates
Versus
M/s. ITD Cementation India Ltd. ... Respondent
Through: None.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? Yes
2. To be referred to the reporter or not? Yes
3. Whether the judgment should be reported
in the Digest? Yes
RAJIV SAHAI ENDLAW, J.
1. The petition raises the question of maintainability of a petition
under Section 34 of the Arbitration Act, 1996 during the pendency of
applications under Section 33 of the Act before the Arbitral Tribunal
and as to the interpretation of Section 33 (6) of the Act.
2. The OMP under Section 34 of the Act is accompanied with IA
No.10038/2009 under Section 33 (2) r/w Section 14 (1)(a) of the Act
for restraining the Arbitral Tribunal from considering the
applications under Section 33 of the Act.
3. The OMP U/s.34 of the Act is preferred with respect to an
arbitral award dated 22nd April, 2009 signed copy whereof is stated
to have been received by the petitioner on 27th April, 2009. It is the
case of the petitioner that the petitioner on 15th May, 2009 i.e. well
within the time prescribed in Section 33 (1) of the Act applied to the
Arbitral Tribunal for correction of the alleged computation
clerical/typographical errors in the award. The petitioner further
informs that the respondent herein also on 19th May, 2009 made an
application to the Arbitral Tribunal under Section 33 (4) of the Act
for an additional award.
4. The senior counsel for the petitioner has contended that the
time prescribed under Section 33(2) of the Act for the Arbitral
Tribunal to make the correction or to give any interpretation sought
under Section 33(1) is 30 days from the receipt of the request; that
the time for making the additional award as stated to have been
sought by the respondent is 60 days from the receipt of such request
as provided in Section 33(5) of the Act. The senior counsel for the
petitioner has contended that the arbitral tribunal in the present
case neither within 30 days of 15th May, 2009 nor within 60 days of
19th May, 2009 corrected the typographical errors or pronounced the
additional award. It is argued, that the Arbitral Tribunal having not
done so, under Section 32 of the Act became functus officio.
Reliance in this regard is placed on the judgment of a single judge of
the Punjab & Haryana High Court in Executive Engineer,
H.S.A.M. Board Vs. Dharam Pal 2000 (Suppl.) Arb. LR 375.
5. It is further contended by the senior counsel for the petitioner
that after the petitioner had first filed the OMP in this court on 27th
July, 2009, on 28th July, 2009 a communication was received by the
petitioner from the Arbitral Tribunal, proposing to hold five meetings
for consideration of the two applications aforesaid dated 15 th May,
2009 and 19th May, 2009 filed under Section 33 of the Act; the
Arbitral Tribunal proposed the said meetings between 25th July, 2009
and 20th August, 2009. The petitioner notwithstanding the receipt of
the said letter has re-filed the OMP and has contended that the
Arbitral Tribunal having not dealt with the application under Section
33 of the Act within the prescribed time, is now not empowered to do
so and as such the OMP under Section 34 of the Act is maintainable.
Application as aforesaid is also filed for restraining the Arbitral
Tribunal from considering the applications under Section 33.
6. I have inquired from the senior counsel for the petitioner as to
whether there is any proof on record of the date when the requests
dated 15th May, 2009 and 19th May, 2009 were served on the Arbitral
Tribunal. Though it was earlier informed that the same is not
available, at the time of dictating it was submitted that the said proof
can be furnished. I have also inquired as to whether there is any
proof on record of the petitioner having received the communication
from the arbitral tribunal on 28th July, 2009, in the form of the
envelope in which the same was received etc. Though earlier it is
indicated otherwise, at the time of dictating it has been stated that
the same can also be looked at. It is further pointed out that the said
letter which is filed as Annexure A at Page 37 (I) is undated and is
not signed by one of the three arbitrators.
7. Since the letter aforesaid fixes the meetings with effect from
25th July, 2009; it was put to the senior counsel for the petitioner that
the date of issuance thereof appears to be of prior thereto. However
it was informed that it was received by the petitioner on
28th July, 2009 only. The letter fixes the second hearing on
29th July, 2009, thereafter on 30th July, 2009, 11th August, 2009 and
20th August, 2009. On inquiry it is informed that the petitioner
did not appear/participate in the hearings on 29th July, 2009 and 30th
July, 2009 also inspite of receipt of the communication on 28th July,
2009; it is stated that since according to the petitioner, the Arbitral
Tribunal was functus officio the petitioner did not deem it proper to
appear before the arbitral tribunal and also did not pay the fee
demanded by the Arbitral Tribunal.
8. Attention of the senior counsel for the petitioner has been
drawn to Section 33(6) which permits the Arbitral Tribunal to extend
if necessary the period of time within which it shall make the
correction or due interpretation or make an additional award under
Section 33(2) or 33(5) of the Act. The Punjab and Haryana High
Court in the case supra has also not noticed the said provision and
has in fact proceeded on the erroneous premise that there is no
provision in the Act whereby the time provided under Section 33(2)
and 33(5) of the Act can be extended.
9. The senior counsel for the petitioner has argued that the
extension of time under Section 33(6) of the Act can only be with the
consent of the parties and not in the discretion of the Arbitral
Tribunal itself. Strength in this regard is sought to be drawn from
Section 33 (1) which provides for the period of 30 days from the
receipt of the arbitral award for filing an application for correction of
an error in the award, unless another period of time has been agreed
upon by the parties. It is further urged that arbitration being
consensual in nature, the Arbitral Tribunal ought not to be held
entitled to extend the time itself without the parties agreeing so. It
is also sought to be suggested that the extension of time if any under
Section 33 (6) of the Act can only be before the expiry of the time
provided in Section 33(2) or Section 33(5) of the Act and not
thereafter.
10. As far as the first of the aforesaid contentions is concerned, the
literal construction of Section 33(6) does not permit inference of the
Arbitral Tribunal being empowered to extend time only with the
consent of the parties. Had it been the legislative intent, nothing
prevented the legislature from providing so in Section 33 (6): The
time provided in Section 33(1) is for making of applications by the
parties. The same has been made subject to agreement of the
parties. On the contrary the time provided in Section 33 (6) is for the
Arbitral Tribunal to decide the said applications. The Arbitral
Tribunal in carrying out the correction or in making the additional
award is to perform an adjudicatory function and cannot be put
under any constraints of time. In this regard it may be noticed that
the 1996 Act does away with the time of four months for making of
the award provided under 1940 Act and unless the agreement itself
between the parties provides for the award to be made within a
particular time, places no restrictions whatsoever on the Arbitral
Tribunal qua time for making of the award. The same is the position
under Section 33(6) of the Act.
11. Similarly, the other contention of the senior counsel for the
petitioner of the arbitral tribunal being entitled to extend the time
only before the expiry of the time fixed/provided under Section 33(2)
or 33(5) of the Act does not find favour with me. The language of
Section 33 (6) does not permit any such limitation to be imposed on
the Arbitral Tribunal. Section 32 also does not provide for
termination of arbitration proceedings on expiry of time mentioned
in Section 33 (2) or Section 33(5) of the Act. Interpreting Section
33(6) as contended by petitioner would make it onerous and give rise
to other contentious issues.
12. The senior counsel for the petitioner has also argued that the
petitioner cannot be left waiting endlessly for the Arbitral Tribunal to
adjudicate applications under Section 33 and in the meanwhile the
time provided under Section 34(3) may run out.
13. That however does not appear to be the position. Section 34(3)
provides for the application under Section 34(1) of the Act to be
made not after three months from the date the parties have received
the arbitral award or if a request has been made under Section 33
from the date on which request has been disposed of by the Arbitral
Tribunal. In the present case before the OMP under Section 34 of
the Act came up for consideration before this court, the Arbitral
Tribunal has communicated extension of time for disposal of the
applications preferred before it under Section 33 of the Act. The
said applications are still pending.
14. The Act does not appear to permit the party to pursue two
remedies i.e. under Section 33 as well as under Section 34 of the
Act. The Supreme Court also in Amba Lal Sarabhai Enterprises
Ltd. Vs. Amrit Lal & Co. AIR 2001 SC 3580 has provided for
election and held that a party ought to choose one of the two
alternative remedies which may be available to it. The petitioner in
the present case has not withdrawn the application under Section 34
of the Act till date. Even today during the course of hearing no
statement has been made for withdrawing the said application. In
any case, even if any such statement is to be made, the same would
not change the position in as much as application filed by the
respondent under Section 33 of the Act is still pending and is not
informed to have been disposed of.
15. That being the position, the OMP is found to be pre-mature. In
view of Section 33(6) of the Act, the relief claimed in the IA
No.10038/2009 of restraining the Arbitral Tribunal from considering
the applications under Section 33 of the Act, also cannot be granted.
The OMP as well as the applications are dismissed. Needless to
state that the OMP having been dismissed as pre-mature, the
petitioner if required to prefer an OMP after the disposal of the
applications under Section 33 of the Act shall be entitled to urge all
the grounds including those taken in the present OMP. No order as
to costs.
+IA No.10037/2009 (of the petitioner u/s. 151 CPC) in OMP No.455/2009 (U/s.34 of the Arbitration Act, 1996)
Allowed subject to just exceptions.
RAJIV SAHAI ENDLAW (JUDGE) August 11, 2009 J
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!