Citation : 2009 Latest Caselaw 3076 Del
Judgement Date : 10 August, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP No.313/2006
% Date of decision:10.08.2009
BHARAT SANCHAR NIGAM LTD. ....Petitioner
Through: Mr. Chandan Kumar, Advocate
Versus
KAVVERI TELECOM PRODUCTS LTD. & ANR. ... Respondents
Through: Mr. Ankur S. Kulkarni & Mr. Nirnimesh
Dube, Advocates for the Respondent
No.1.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? YES
2. To be referred to the reporter or not? YES
3. Whether the judgment should be reported YES
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. A petition under Section 9 (ii) (e) of the Arbitration Act, 1996 is
preferred challenging inter-alia the order of the arbitral tribunal
holding that as per its mandate it could not entertain the counter
claims preferred by the petitioner before it. It is the contention of the
counsel for the petitioner that the court under Section 9 (ii) (e) is
empowered to issue any interim measure of protection as may
appear to be just and convenient and not necessarily in the form of
protection of any property or asset or for securing the amounts due
in arbitration. The contention of the petitioner if accepted would lead
to this court under Section 9 (ii) (e) exercising the jurisdiction as
exercised by this court under Article 227 of the Constitution of India
qua proceedings before courts/tribunals inferior to this court.
2. The disputes between the parties arose out of an agreement
containing an arbitration clause. As per the said clause, any
question, dispute or difference arising under the agreement or in
connection therewith was to be referred to sole arbitration of the
Director General, Deptt. of Telecommunication or of an officer
holding the equivalent designation. The Director General, under the
said clause, if unwilling to act as the arbitrator, was also empowered
to appoint any other person as the arbitrator.
3. Disputes and differences having arisen between the parties the
respondent applied to the petitioner for appointment of the
arbitrator. Upon failure of the petitioner to appoint the arbitrator the
respondent preferred writ petitions No.30700-701 of 2004 before the
High Court of Karnataka at Bangalore. The said writ petitions were
rejected, however with a direction that the petitioner herein shall
nominate the arbitrator within two weeks therefrom and the
arbitrator so appointed shall dispose of the claims of the parties
expeditiously. Directions were also issued with respect to the bank
guarantees furnished by the respondent to the petitioner.
4. The Chairman & Managing Director of the petitioner vide
order dated 27th January, 2005, referring to the order aforesaid of
the High Court of Karnataka, appointed one Shri V.P. Sinha as the
arbitrator to settle the disputes so arbitrable.
5. The respondent filed its claim before the arbitrator and the
petitioner filed its counter claim. The respondent filed replies to the
counter claim of the petitioner. Even though there was no objection
by the respondent to the maintainability of the counter claim of the
petitioner before the arbitrator or of the jurisdiction of the arbitrator
to entertain the same, the arbitrator vide his letter, Annexure R-1 to
the petition, date whereof is disclosed by counsels for both the
parties to be 29th August, 2005 inter-alia ordered that the scope of
his mandate was in terms of the order dated 27th January, 2005
(Supra) i.e. to arbitrate to settle the disputes with regard to the
balance bills & performance bank guarantee against the supply of
HDSL equipment and the counter claim preferred by the petitioner
could not be taken on record. It was further ordered that either a
fresh mandate is to be given for the arbitrator to entertain the said
counter claim or the petitioner can go to any other court/arbitrator
for redressal of its grievance.
6. The petitioner after nearly one year of the date of the aforesaid
letter, on 13th July, 2006 filed the present petition. The relief claimed
herein is for setting aside of the aforesaid order of the arbitrator and
for a direction to the arbitrator to consider the counter claim of the
petitioner already filed.
7. The respondent has in its reply to this petition raised a plea as
to the maintainability of the petition.
8. The counsel for the petitioner has urged that the language of
Section 9 (ii) (e) is very wide. Reliance is placed on Maharashtra
State Elect. Board Vs. Datar Switchgears Ltd. 2003 (Suppl.) Arb.
LR 39 (Bomb.) & on BLB Institute of Financial Markets Ltd. Vs.
Ramakar Jha 154 (2008) DLT 121 in support of the wide amplitude
of Section 9 (ii) (e). However, the counsel for the petitioner, on
inquiry as to whether any of the said judgments lay down that the
powers thereunder can be invoked to set aside any errors in the
arbitral proceedings, even if necessary to provide protection to any
of the parties, the counsel for the petitioner has fairly stated that in
none of the judgments such proposition has been laid down. I may
however notice that the single judge of Bombay High Court in
Maharashtra State Electricity Board, though holding the powers
of the court under Section 9 (ii) (e) to be very wide, made the said
observations only in the context of ensuring compliance of interim
order of the Arbitral Tribunal. Else therein also, relying on Bhatia
International Vs. Bulk Trading SA (2002) 4 SCC 105, it was held
that the Act does not contemplate the interference of courts at the
interim stage in matters of jurisdiction of the Arbitral Tribunal and
that the court would in such cases not be entitled to exercise powers
under Section 9.
9. The counsel has further argued that unless the present petition
is held to be maintainable, the petitioner would be remediless. He
has further explained the delay in filing the present petition by
submitting that after the letter dated 29th August, 2005 (Supra)
review was applied for before the arbitrator and which was
ultimately dismissed on 10th May, 2006, copy of the order of which
date was received by the petition on 6 th June, 2006 and immediately
whereafter this petition was preferred.
10. Per contra, the counsel for the respondent has while
reiterating his submissions as to the non-maintainability of the
present petition drawn attention to NTPC Ltd. Vs. Siemens
Atkeingesellschaft 2007 (3) SCALE 657 whereunder with reference
to Section 16 of the Act it has been laid down that the remedy of
appeal is available to a party against the order allowing the objection
taken thereunder.
11. The counsel for the petitioner has in rejoinder submitted that
no objection under Section 16 had been raised by the respondent
qua the counter claim of the petitioner and hence the remedy of
appeal was not available to the petitioner.
12. The present is a classic case of how the arbitral proceedings
can be derailed. It is informed that the arbitration qua the claims of
the respondent is also held up before the arbitrator owing to the
pendency of the present petition since 2006.
13. The arbitrator appears to have treated the proceedings before
him as a reference under the 1940 Act whereunder the disputes had
to be referred to the arbitrator for adjudication and the arbitrator
was empowered to settle/adjudicate only the referred disputes and
none else. The 1996 Act, does not envisage reference of disputes to
arbitrator and only provides for the appointment of the arbitrator.
The arbitration clause in the present case also names the Director
General of the Deptt. of Telecommunications or officer of equivalent
rank/designation as the arbitrator, also empowers him, if unwilling,
to appoint any other arbitrator. All that was thus required was for
the claims to be raised by either party before the named arbitrator
or his nominee and no reference was to be made. The order dated
27th January, 2005 of appointment of the arbitrator is also with
reference to the agreement and the order in the writ petitions. The
order is further for adjudication by arbitration of disputes so
arbitrable.
14. Even though in the opinion of the court the arbitrator ought
not to have rejected the counter claim of the petitioner but the fact
remains that the remedy, if any, of the petitioner against the said
order is not by way of the present petition. In fact the arbitrator
himself had shown the way to the petitioner which the petitioner
failed to follow. The simplest step for the petitioner to take was to
again approach the appointing authority for clarification that the
counter claim also could be entertained by the arbitrator. However,
the petitioner instead of doing so after following the route of review
before the arbitrator ultimately invoked wrong remedy for its
genuine/correct grievance.
15. The contention of the counsel for the petitioner that Section 9
(ii) (e) ought to be read/interpreted so as to vest power in this court
to correct such errors committed by the arbitrator cannot be
permitted. Section 9 (ii) (e) empowers the court only to pass orders
of interim nature. The said power cannot be said to be encompassing
within itself the right to correct the errors committed during the
course of arbitral proceedings and with respect whereto the party
may be needing protection.
16. The contention of the petitioner that the petitioner has no
other remedy against the order aforesaid of the arbitrator is also not
found correct. The said order of the arbitrator amounts to dismissal
of the counter claim of the petitioner and has a finality about it and
is in the nature of an award and the remedy thereagainst under
Section 34 was available to the petitioner.
17. I also find that Section 16 empowers the arbitral tribunal to
rule on its jurisdiction suo moto also without any plea being taken in
that regard. Section 16 (1) empowers the arbitral tribunal to do so,
including ruling on any objections with respect to the existence or
validity of arbitration agreement. Thus, it appears that the remedy
of an appeal under Section 37 (2) (a) was also available to the
petitioner.
18. I have also toyed with the idea of treating the present petition
under Section 34. However, in view of the bar of limitation as laid
down in UOI Vs. M/s Popular Construction Co. AIR 2001 SC 4010
the same is not possible. I have also suggested to the counsel for the
respondent to, for the sake of expediency, consent to treating the
present petition as an appeal under Section 37 (2) (a) of the Act in as
much as no period of limitation appears to have been prescribed
therefor. However, the counsel for the respondent states that he is
unable to give any consent and the petitioner may prefer the
appropriate remedy if so advised.
19. Since the powers exercised by this court are under the
Arbitration Act, 1996 and Section 5 whereof limits the extent of
interference by the court, it is not felt appropriate, to without any
prayer in this regard, treat the present petition as an appeal under
Section 37 (2) (a) of the Act.
20. The petition is accordingly dismissed as not maintainable.
However, in the facts of the case the parties are left to bear their
own costs.
RAJIV SAHAI ENDLAW (JUDGE)
August 10th, 2009 PP
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!