Citation : 2009 Latest Caselaw 3037 Del
Judgement Date : 7 August, 2009
THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment delivered on: 07.08.2009
+ OMP 23/2007
NATIONAL HIGHWAYS AUTHORITY
OF INDIA ... Petitioner
- versus -
M/S ITD CEMENTATION INDIA LTD ... Respondent/ Claimant
(Formerly M/s Skanska Cementation India Ltd)
Advocates who appeared in this case:
For the Petitioner : Mr Chetan Sharma, Sr Advocate with Mr Vikas Goel and Mr R. N. Sharma For the Respondent : Mr George Thomas with Mr G. K. Jose and K. J. Joseph
CORAM:-
HON'BLE MR JUSTICE BADAR DURREZ AHMED
1. Whether Reporters of local papers may be allowed to see the judgment? YES
2. To be referred to the Reporter or not? YES
3. Whether the judgment should be reported in Digest? YES
BADAR DURREZ AHMED, J
1. Through this petition under Section 34 of the Arbitration and
Conciliation Act, 1996 (hereinafter referred to as the ‗said Act'), the
petitioner is seeking the setting aside of the Award dated 11.10.2006
made by the Arbitral Tribunal comprising of Sh. K. K. Madan
(Presiding Arbitrator), Lt. Gen. A. K. Puri (retired) and Justice A. B.
Rohtagi (Retired) in the matter of arbitration for the work of widening
of four lane and rehabilitation of existing two lane carriageway of NH-
4, Pune-Satara stretch from Satara (Km 725) to Wathar (Km 760),
Package-I. The respondent herein had preferred six claims. The
petitioner herein is aggrieved by the decision of the Arbitral Tribunal in
respect of the claim Nos. 1-5.
2. As indicated in the impugned Award a contract bearing
agreement No. NHAI/13011/17/97-P1/182 dated 10.05.2001 had been
entered into between the petitioner and the respondent for the execution
of the work of widening the existing two lane highway to four lanes as
well as rehabilitation of the existing two lane carriageway of National
Highway-4 in the Pune-Satara stretch. The contract was in respect of
the portion of the road between Satara (Km 725) and Wathar (Km 760)
which, in other words, implied a stretch of 35 Km. The contract value
was Rs 95,97,02,707/-. It may be pointed out that initially the contract
was between the National Highway Authority of India (employer)
(hereinafter referred to as the ‗NHAI') and M/s Skanska Cementation
India Limited (contractor), whose name was subsequently changed to
the present name -- ITD Cementation India Limited (hereinafter
referred to as ‗ITD Cementation').
3. The scope of the works involved the widening of the existing
two lane stretch of 35 km between Pune-Satara, constructing new
bridges and flyovers, widening and repairing existing bridges,
constructing toll plaza, junctions and intersections including service
roads and all road appurtenances and miscellaneous works. The date of
commencement of the work was agreed to be 01.07.2001 and the date
of completion, as per the contract, was 31.12.2003, which meant a
period of 30 months for completing the work. The work was actually
completed on 30.03.2004, that is, in 33 months. Disputes had arisen
between the parties and, therefore, the respondent/ claimant invoked
arbitration by its letter dated 29.06.2004 and simultaneously nominated
Justice A. B. Rohtagi (retired) as an arbitrator. In response to the said
invocation of the arbitration clause, the petitioner nominated Mr A. K.
Puri as an arbitrator and the two arbitrators appointed Mr K. K. Madan
as the Presiding Arbitrator. The following claims were made by the
respondent / claimant:-
(1) Claim No.1: Amounts payable by NHAI for varied work done by
claimant (ITD Cementation) and payment due under price
adjustment on the basis of rebate offered in the tender.
The modified claim under claim No.1 was of
Rs 9,14,71,312/-. As against this, the Arbitral Tribunal awarded
an amount of Rs 2,34,23,656/-.
(2) Claim No. 2: Payment due on account of redesigning of
pavement layers.
This claim was split into four parts being claim Nos. 2(a), (b), (c)
and (d). Claim No. 2(a) related to the effect of deletion of CTSG
(cement treated sub-grade). The amount awarded by the Arbitral
Tribunal was a sum of Rs 41,57,025/- in respect of the claim 2(a)
as against a modified claim of Rs 1,05,49,494/-. Claim No. 2(b)
was in respect of the effect of deletion of CTUSB (cement treated
upper sub-base). The Arbitral Tribunal awarded an amount of
Rs 32,73,618/- under this head as against the modified claim of
Rs 1,27,49,618/-. Claim No. 2(c), which pertained to under
utilization of key plants and equipments and quarry infrastructure
was withdrawn by the NHAI by their letter dated 29.03.2006.
Claim 2(d) pertained to additional cost of borrow material. The
Arbitral Tribunal awarded an amount of Rs 51,41,202/- to the
claimant (ITD Cementation) on account of additional cost
incurred towards additional borrow material against the modified
claim of Rs 1,48,79,786/-.
(3) Claim No.3: Payments due on account of change in the
thickness of DBM (Dense Bitumen Macadem) layer of 100 mm
for new carriageway (NCW) from one layer into two layers of 65
mm each and due to reduction of thickness of DBM for existing
carriageway (ECW) from 100 mm to 80 mm. This claim
comprises of two parts. The first part pertains to the new
carriageway (NCW) and the second part pertains to the existing
carriageway (ECW). Insofar as the claim pertaining to NCW was
concerned, the Arbitral Tribunal awarded an amount of
Rs 91,11,070/- as against the original claim of Rs 2,34,69,654/-.
The second part of the claim pertaining to ECW was rejected by
the Arbitral Tribunal.
(4) Claim No. 4: Reimbursement of increase in royalty charges.
The Arbitral Tribunal awarded an amount of Rs 68,66,175/- on
account of increase in royalty charges consequent upon the
notification dated 28.10.2002 issued by the Government of
Maharashtra.
(5) Claim No. 5: Interest.
The Arbitral Tribunal awarded interest at the rate of 12% per
annum compounded monthly in respect of the pre-reference
period, pendente lite interest as well as future interest on the
amount awarded under claims 1-4.
(6) Claim No. 6: Costs of arbitration, which the claimant (ITD
Cementation) claimed at Rs 10 lacs.
This claim was rejected and the Arbitral Tribunal directed that
the cost of arbitration be shared equally. The summary of the
Award in respect of claim Nos. 1-4 and 6 as given in the
impugned Award itself is set out herein below:-
Claim Brief description Amount Amount
No: Claimed (Rs) Awarded
(Rs)
1. a) Varied work Quantities 6,74,02,347 1,07,90,139
b) Additional Structures 1,26,33,517 1,26,33,517
c) Price Adjustment 1,14,35,448 Nil
Total 9,14,71,312 2,34,23,656
2. a) Loss of overhead and 1,05,49,494 41,57,025
profits due to deletion of
cement stabilized upper
sub grade
b) Loss of overhead and 1,27,49,618 32,73,618
profit due to deletion of
cement treated upper sub
base
c) Under utilization of Key 1,15,24,775 Nil
Plants and Equipments and (withdrawn
Quarry structures subsequently)
d) Additional cost of 1,48,79,786 51,41,202
borrow material
Total 3,81,78,898 1,25,71,845
3. a) Change in thickness of 2,34,69,654 91,11,070
DBM layer, 100 mm to
two layers of 65 mm each
in NCW
b) Change in thickness of 30,25,260 Nil
DBM layer 100 mm to 80
mm on ECW
Total 2,64,94,914 91,11,070
4. Reimbursement of increase 68,66,175 68,66,175
in royalty charges
6. Cost of Arbitration 10,00,000 Nil
Grand Total of Claims 1 16,40,11,299 5,19,72,746
to 4 and 6
4. I shall take up the objections to the Award claim-wise.
Claim No. 1: Amounts payable by NHAI for varied work done by claimant (ITD Cementation) and payment due under price adjustment on the basis of rebate offered in the tender.
5. In the summary of bill of quantities, which is Annexure P-2
to the impugned Award, as against the total bid amount of
Rs 115,07,22,670/-, the respondent (ITD Cementation) had offered a
rebate of 16.6% on all items and, therefore, the final bid amount, after
rebate, was indicated as Rs 95,97,02,707/-. The issue that arises under
claim No. 1 is whether the rebate of 16.6% would be applicable only to
the bill of quantities (BOQ) or it would also extend to any variations
and/ or additional work. According to the claimant (ITD Cementation),
it gave a rebate of 16.6% on the BOQ items only and the rebate did not
extend to variations. Furthermore, the rebate definitely did not extend
to additional structures. Since the petitioner (NHAI) had made
payment to the respondent (ITD Cementation) on the basis of 16.6%
rebate not only on the BOQ items but also on variations and additional
structures, the respondent (ITD Cementation) was seeking a refund of
such rebate on the variations and additional structures.
6. It is the case of the petitioner (NHAI) that the rebate of
16.6% offered by the respondent (ITD Cementation) applied to all
work including variations and additional structures. According to the
petitioner the whole contract was an item rate contract and, therefore,
the rate of the rebate could not have a separate existence.
7. The Arbitral Tribunal, while considering the issue of
variations, interpreted clauses 51.1, 51.2, 52.1 and 52.2 of the General
Conditions being part of the Conditions of Contract for Works of Civil
Engineering Construction issued by the Federation Internationale Des
Ingenieurs- Counseils (FIDIC). The said provisions read as under:-
Alterations, Additions and Omissions
Variations 51.1 The engineer shall make any variation of the form, quality or quantity of the works or any part thereof that may, in his opinion, be necessary and for that purpose, or if for any other reason it shall, in his opinion, be appropriate, he shall have the authority to instruct the contractor to do and the contractor shall do any of the following:
(a) increase or decrease the quantity of any work included in the contract,
(b) omit any such work (but not if the omitted work is to be carried out by the employer or by another contractor),
(c) change the character or quality or kind of any such work,
(d) change the levels, lines, position and dimensions of any part of the works,
(e) execute additional work of any kind necessary for the completion of the works, or
(f) change any specified sequence or timing of construction of any part of the works.
No such variation shall in any way vitiate or invalidate the contract, but the effect, if any, of all such variations shall be valued in accordance with Clause 52. Provided that where the issue of an instruction to vary the works is necessitated by some default of or
breach of contract by the contractor or for which he is responsible, any additional cost attributable to such default shall be borne by the contractor.
Instructions 51.2 The contractor shall not make any such for variations variation without an instruction of the engineer. Provided that no instruction shall be required for increase or decrease in the quantity of any work where such increase or decrease is not the result of an instruction given under this Clause, but is the result of the quantities exceeding or being less than those stated in the Bill of Quantities.
Valuation of 52.1 All variations referred to in Clause 51 and any variations additions to the contract price which are required to be determined in accordance with Clause 52 (for the purposes of this Clause referred to as ―varied work‖), shall be valued at the rates and prices set out in the contract if, in the opinion of the engineer, the same shall be applicable. ―If the contract does not contain any rates or prices applicable to the varied work, the rates and prices in the contract shall be used as the basis for valuation so far as may be reasonable, failing which, after due consultation by the engineer with the employer and the contractor, suitable rates or prices shall be agreed upon between the engineer and the contractor.‖ In the event of disagreement the engineer shall fix such rates or prices as are, in his opinion, appropriate and shall notify the contractor accordingly, with a copy to the employer. Until such time as rates or prices are agreed or fixed, the engineer shall determine provisional rates or prices to enable on-account payments to be included in certificates issued in accordance with Clause 60.
Power of 52.2 Provided that if the nature or amount of any engineer to varied work relative to the nature or amount of fix rates the whole of the works or to any part thereof, is such that, in the opinion of the engineer, the rate or price contained in the contract for any item of the works is, by reason of such varied
work, rendered inappropriate or inapplicable, then, after due consultation by the engineer with the employer and the contractor, a suitable rate or price shall be agreed upon between the engineer and the contractor. In the event of disagreement the engineer shall fix such other rate or price as is, in his opinion, appropriate and shall notify the contractor accordingly, with a copy to the employer. Until such time as rates or prices are agreed or fixed, the engineer shall determine provisional rates or prices to enable on-account payments to be included in certificates issued in accordance with Clause 60.
Provided also that no varied work instructed to be done by the engineer pursuant to Clause 51 shall be valued under sub-clause 52.1 or under this sub-Clause unless, within 14 days of the date of such instruction and, other than in the case of omitted work, before the commencement of the varied work, notice shall have been given either:
(a) by the contractor to the engineer of his intention to claim extra payment or a varied rate or price, or
(b) by the engineer to the contractor of his intention to vary a rate or price.
According to the Arbitral Tribunal the basic difference between the
points of view of the parties appears to arise from different
interpretation and meaning of the term rebate given by the respondent
(ITD Cementation) in the tender and the BOQ rates. The basis of the
respondent's stand is that the rebate and unit rates are two distinctly
separate and independent terms as defined in the contract documents.
The unit rates and prices for the items are to be used for arriving at the
bid price while the discount/ rebate is to be used to arrive at a contract
price. Thus, as per the respondent, the rebate offered did not amount to
change in the quoted unit rate and price but was a discount offered in
the BOQ items and was applicable for BOQ quantities of various items
and not for items executed under Clause 51 of the General Conditions
of Contract for which the relevant contract provisions would apply. On
the other hand, it was the contention of the petitioner that the rebate
was a reduction in the unit rates of each BOQ item and the rate was the
net rate after reducing the unit rate by the percentage of rebate offered.
As per the petitioner, the rebate applied to all BOQ quantities as well as
deviated quantities. As per the Arbitral Tribunal, there are two kinds of
variations. The first is the automatic increase or decrease in the
quantity of any work included in the work as indicated in Clause
51.1 (a). Similar is the position, with the variation indicated in Clause
51.1(c), (d) and (e). Referring to Clause 51.2 the Arbitral Tribunal
observed that all variations which are to be made by the Contractor
under Clause 51.1 are to be made only upon instructions of the
engineer. The proviso to Clause 51.2 indicates that no instruction
would be required for increase or decrease in the quantity of any work
where such increase or decrease is not the result of an instruction given
under the said clause, but is the result of the quantities exceeding or
being less than those stated in the bill of quantities. On the basis of
this, the Arbitral Tribunal was of the view that there were two kinds of
variations. One, which was on the basis of instructions and, therefore,
could be regarded as instructed variations and, two, variations for
which no instruction was necessary and was merely the result of the
quantities exceeding or being less than those stated in the bill of
quantities. The latter kind of variation was regarded by the Arbitral
Tribunal as automatic.
8. The Arbitral Tribunal took the view that the automatic
changes in quantities which resulted from any inaccuracy in the bills of
quantities did not constitute a variation inasmuch as the employer had
at the very beginning in the preamble to the BOQ in Clause 2 made it
clear that ―the quantities given in the BOQ are estimated and
provisional and are given to provide a common basis for bidding‖.
Further reference was made to the clause to indicate that the basis of
payment will be the actual quantities of work ordered and carried out,
as measured by the contractor and verified by the engineer and valued
at the rates and prices bid in the priced BOQ, where applicable, and
otherwise at such rates and prices that the engineer may fix in terms of
the contract.
9. In view of the line of reasoning adopted by the Arbitral
Tribunal, it came to the conclusion that it is only the increased
quantities ordered by the engineer in writing which constituted varied
work and such variation must be paid at the rates and prices set in the
contract without deduction of rebate. The automatic increase or
decrease as a result of inaccuracy in the BOQ cannot be considered as
varied work and in respect of such changes, the rebate of 16.6% would
apply. Thus, the Arbitral Tribunal drew a clear distinction between
instructed variations, which, according to it, constituted varied work
and automatic changes which did not constitute varied work. The
Arbitral Tribunal came to the conclusion that it is only for the varied
work that the BOQ rates without rebate would apply ―because the
contractor did not promise rebate on varied works as defined above‖.
Consequently, as against the claim of Rs 6,74,02,347/- under the head
of variations, the Arbitral Tribunal awarded an amount of
Rs 1,07,90,139/-.
10. Considering the arguments advanced by the counsel for the
parties on both sides which were reiterations of their stands before the
Arbitral Tribunal, I am of the view that the Arbitral Tribunal has come
to the aforesaid conclusion on the basis of a particular interpretation of
the relevant clauses of the contract. It is well settled that the
interpretation of a contract is within the domain of the arbitrator. Even
if the Court does not agree with the interpretation given by the Arbitral
Tribunal, the Award cannot be set aside if the interpretation employed
by the Arbitral Tribunal is a plausible one and is not absurd [see: (i)
McDermott International Inc. v. Burn Standar Co. Ltd: 2006(2)
Arb.L.R. 498 (SC); (ii) Pure Helium India (P) Ltd v. ONGC: 2003(8)
SC 593; (iii) Himachal Pradesh State Electricity Board v. R. J. Shah
& Co.:JT 1999(3) SC 151; (iv) Union of India v. Suchita Steels:
2005(4) RAJ 378 (Delhi); and (v) Sudershan Trading Co. v. Govt. of
Kerala: AIR 1989 SC 890]. It is also a well settled principle that the
Court while examining a petition under Section 34 of the said Act does
not sit as a Court of appeal over the findings of fact or law of the
Arbitral Tribunal. The Court is not required and, in fact, does not
reappraise the evidence. The interpretation of a contract or the terms
thereof is also within the jurisdiction of the Arbitral Tribunal [see:
State of UP v. Allied Constructions: 2003(7) SCC 396]. Of course, if
the interpretation or construction given to a particular clause of a
contract by the Arbitral Tribunal is absolutely implausible or absurd,
the same can be interfered with by the Court under Section 34 of the
said Act. Furthermore, if a particular clause of the contract admits of
only one interpretation and if the Arbitral Tribunal chooses to ignore
the only plausible interpretation and comes up with an interpretation
which does not appear plausible, the Court is not obliged to accept that
interpretation [see: Wee Aar Constructive Builders v. DDA & Ors:
2001(2) Arb. L. R. 71 (Delhi)]. Also, the arbitrator is not a conciliator
and cannot ignore the law or misapply it in order to do what he thinks
is just and reasonable. The Arbitral Tribunal is selected by the parties
to decide their disputes according to law and if it does not, its Award
can be set right by the Court [see: Continental Construction Co. Ltd. v.
State of M.P: AIR 1988 SC 1166]. It is clear that an arbitrator being a
creature of the agreement between the parties, has to operate within the
four concerns of the agreement and if he ignores the specific terms of
the contract, it would be a question of jurisdictional error on the face of
the Award and the same could be corrected by the Court [see: Food
Corporation of India v. Chandu Construction and Another: (2007) 4
SCC 697].
11. These principles, which have been culled out from the
decisions cited by the counsel for the parties on both sides, are clear.
The sum and substance is that the Arbitral Tribunal cannot ignore terms
of the contract or go contrary to the same. But, where the Arbitral
Tribunal arrives at one of the plausible interpretations of the terms of a
contract, the Court does not interfere under Section 34 of the said Act.
The Court also does not interfere with findings of fact unless and until
there is perversity writ large in the impugned Award.
12. In the present case the Arbitral Tribunal has examined
clauses 51.1, 51.2, 52.1 and 52.2 and has, upon such examination,
gleaned a distinction between an instructed variation and an increase or
decrease in the quantity of any work which is not a result of an
instruction given by the engineer but is the result of the quantities
exceeding or being less than those stated in the bill of quantities.
Clause 51.1 indicates that any variation in the work, as indicated
therein, will not, in any way, vitiate or invalidate the contract but the
effect, if any, of all such variations are to be valued in accordance with
Clause 52. Clause 52.1 deals with valuation of variations. It specifically
provides that all variations referred to in Clause 51 shall be valued at
the rates and prices set out in the contract if, in the opinion of the
engineer, the same shall be applicable. According to the Arbitral
Tribunal, the expression ―rates and prices set out in the contract‖
referred to the unit prices mentioned in the BOQ prior to the
application of rebate of 16.6%. Interpreting the clauses in such
manner, the Arbitral Tribunal came to the conclusion that the
respondent (ITD Cementation ) was entitled to a refund of the rebate
only in respect of instructed variations which fell within the expression
―varied work‖ as appearing in Clause 52.1 of the GCC. The Arbitral
Tribunal, therefore, rejected the respondent's claim of refund of rebate
in respect of the increase in the quantity of work which was not
consequent upon any instruction issued by the engineer, but was the
result of quantities exceeding those stated in the bill of quantities.
According to the Arbitral Tribunal, such increase was to be expected as
was apparent from the preamble of the bid document and, therefore,
when the contractor (ITD Cementation) made the bid it was aware that
the 16.6% rebate would apply to such increase or decrease in
quantities.
13. I feel that the interpretation given by the Arbitral Tribunal to
the relevant clauses of the contract between the parties is certainly a
plausible interpretation. Once I come to this conclusion, there is no
scope for any further challenge on this aspect of the matter.
Consequently, the finding of the Arbitral Tribunal with regard to the
refund of the rebate on variations does not call for any interference.
14. The conclusion of the Arbitral Tribunal with regard to
additional structures also does not call for any interference. The
Arbitral Tribunal held:-
―3.1.33 The AT is of the view that for prices set out in the contract to be applicable to varied work, it is essential that it must be similar work executed under similar conditions. If time and sequence show that the additional work was ordered to be executed months after the commencement of the original work and after the contractor has made all arrangements for completion and demobilization then in that case time, sequence and changed conditions as a whole, will have to be taken into account in fixing the price for varied work. To apply rebate to altered and additional work executed under changed conditions as explained above, when prices had increased, is to misapply it, since the claimants had offered the rebate in 2001, when tenders were invited, while varied work was ordered much later after considerable progress has been made.
3.1.34 In this case six underpasses were architecturally sufficient as originally designed and conceived. But additional eight structures were ordered as per demand of the local population, which were not provided in the contract as these were not originally designed, planed or conceived. Therefore the AT holds that these structures cannot be strictly covered under clause 51.1(e) of GCC i.e. necessary for completion of the work.
3.1.35 AT is, further of the view that the rebate was given on original contract work and to extend it to varied work in all circumstances and condition, favourable and unfavourable, is not justified. If we do so, the result will be that under the guise of ―additional work‖, the employer can get any amount of work executed at the rebated rate. Therefore in case of varied work, its nature, extent, timing and sequence must be seen in each case, before applying the rebated rate. In changed conditions and in changed circumstances, additional work will certainly call for fixing a rate on a reasonable basis.
3.1.36 AT therefore holds that the rebate given on overall contract price and grossed up by the contractor while tendering has no application to additional work in the facts of this case and awards an amount of Rs 1,26,33,517 to the claimants on account of rebate deducted on additional structures as per his modified claim (vide Annexure-2 of written arguments on pg. 73), against original claim Rs 2,14,53,873 as per SOC.‖
The reasoning adopted by the Arbitral Tribunal is plausible.
Consequently, no interference is called for.
Claim No. 2: Payment due on account of re-designing of pavement layer.
15. There was a change in the pavement design. This is
indicated by the diagram indicated below:-
From the above diagram, it is apparent that two items have been
omitted from the original pavement design. Those two items are
150 mm CTUSB (cement treated upper sub base) and 150 mm CTSG
(cement treated sub grade). According to the respondent/ claimant
(ITD Cementation), the omission of these items resulted in loss of
profits/ overheads. As noted in the impugned Award in paragraph
3.2.4, there is no dispute between the parties to the change in the design
of the road crust and the consequent omission of the items. The
claimant / respondent valued the effect of the deletion of the two items
due to loss of overheads and profits by considering the same as
analogous to existing BOQ items 2.06(a) and 3.01(a), respectively, and
claimed the rate difference between the two. On the other hand, the
petitioner contended that the BOQ items 2.06 (a) and (b) as also items
3.01(a) and (b) were not analogous and thus the effect of variations
claimed by the respondent / claimant was not correct. According to the
petitioner, the Arbitral Tribunal has given no reasons for treating the
said items as analogous items. However, in paragraph 3.2.10 of the
impugned Award, it is clearly indicated that the items were treated or
considered to be analogous because the only different was the cement
content. Items 2.06 (a) and (b) and items 3.01 (a) and (b) are as under:-
Item Description 2.06 Construction of subgrade /shoulder with approved
materials from borrow pits complete as per Technical Specification Clause 305 with all leads and lifts and as directed by the Engineer:
(a) Lower Subgrade of 450 mm thickness
(b) Cement Treated Upper Subgrade of 150 mm thickness (with 2% cement content) 3.01 Constructing Granular Subbase full width or part width with approved materials:
(a) Lower Granular Subbase (GSB) as per Technical Specification Clause 401 conforming to Grading-I of Table 400-1.
(b) Cement Treated Upper Subbase with 4% cement content as per Technical Specification Clause 403 conforming to Grading as shown in Table 400-4 and as directed by the Engineer.
16. An examination of the above BOQ items clearly shows that
the Arbitral Tribunal has not taken an unreasonable view in treating
items 2.06 (a) and (b) as analogous as also items 3.01 (a) and (b) as
analogous. The only different being the absence or presence of cement.
Consequently, I do not see any reason to interfere with the finding of
the Arbitral Tribunal that the said items are to be considered analogous
for working out the loss of overheads and profits. The claims 2(a) and
2(b) to the extent awarded by the Arbitral Tribunal are, therefore,
upheld. Similarly, I see no reason to interfere with the award of the
amount of Rs 51,41,202/- to the respondent on account of additional
cost incurred towards additional borrow material.
Claim No. 3: Payment due on account of change in the thickness of DBM layer of 100 mm for new carriageway from one layer into two layers of 65 mm each and due to reduction of thickness of DBM for existing carriageway (ECW) from 100 mm to 80 mm.
17. In the present petition I am not concerned with the claim in
respect of the existing carriageway inasmuch as the same has not been
granted by the Arbitral Tribunal and the respondent has not made any
grievance in respect of this. I am concerned with the change in the
thickness of DBM in respect of the new carriageway (NCW). As can
be seen from the diagram given earlier in this judgment with regard to
the change in the pavement design, the original pavement design
indicated a thickness of 100 mm for the DBM. This has been increased
to 130 mm in the new pavement design. As per the applicable
technical specifications, it is only permissible to lay a single layer of
DBM up to 100 mm thickness. Since the new pavement design
required the DBM to be of 130 mm, it could not be executed by laying
a single layer and consequently, had to be executed by laying two
layers of 65 mm each. As per the claimant / respondent (ITD
Cementation), the BOQ rate for DBM in the contract was quoted for
laying of 100 mm thickness DBM in a single layer. Due to reduction in
the thickness of the layers of DBM to be laid in two layers of 65 mm
each, the efforts and resources required per cubic meter of the finished
DBM layer had increased. On the other hand, the petitioner contended
that the rate quoted in the BOQ had to be adhered to inasmuch as it was
on the basis of per cubic meter of DBM, irrespective of the thickness of
the DBM. It may be pointed out that the engineer acknowledged the
fact that additional efforts would be required as a result of the increase
of the thickness of the DBM from 100 mm to 130 mm and he allowed
an additional payment of Rs 78 per cubic meter which was
subsequently revised to Rs 82 per cubic meter in respect of the DBM
for the new carriageway. This was, however, not acceptable to the
respondent / claimant, who claimed a much higher amount. The
respondent had claimed an additional amount at the rate of Rs 407 per
cubic meter. The Arbitral Tribunal noted that insofar as the question of
laying the second layer of DBM was concerned, it entailed further
operations. There was a need to return for laying of the second layer of
DBM over the previously laid surface after every 48 hours, inasmuch
as prior to laying the second layer several operations such as cooling of
the first layer, taking core from the first layer and getting test result of
the core taken also needed to be completed before the second layer
could be put in place. Computing the figures, as noted in the impugned
Award, the Arbitral Tribunal held:-
―3.2.8 In this analysis, AT has considered as reasonable the overall loss of efficiency for laying the DBM into two layers as 25% for each layer and accordingly the incremental rate works out to be Rs 158 per cum. Based on the above A/R the amount payable to the Claimant is Rs 91,11,070/- against the original claim of Rs 2,34,69,654.‖
The incremental rate which was computed on the basis of the analysis
taken by the Arbitral Tribunal was Rs 240/- per cubic meter. It is to be
noted that the increment recommended by the engineer and which had
already been paid by the petitioner to the respondent was Rs 82/- per
cubic meter. The difference in the incremental rate, therefore, worked
out to Rs 158/- per cubic meter (Rs 240 - Rs 82). Consequently, the
amount payable to the claimant/ respondent was worked out at
Rs 91,11,070/-.
18. The learned counsel for the petitioner referred to the above
conclusion arrived at by the Arbitral Tribunal and submitted that the
computation was erroneous. He further submitted that in any event the
Arbitral Tribunal has considered the loss of efficiency for laying the
DBM in two layers ―to be 25% for each layer‖. It was contended that
there could not have been a loss of efficiency in respect of the first
layer and it is only in respect of the second layer that such a
computation could have been done. The overall logic adopted by the
Arbitral Tribunal with regard to the loss having been occasioned to the
respondent/ claimant on account of two layers having to be laid rather
than one cannot be found to be faulty. However, I do agree with the
submission of the learned counsel for the petitioner that the loss of
efficiency of 25% would only be in respect of the second layer and not
in respect of the first because, the first layer would have to be laid in
either eventuality, whether it was the original design or the new design.
It is only because the new design required two layers to be laid rather
than one that there has been a loss of efficiency. Thus, the 25% loss of
efficiency would not be in respect of each layer but only in respect of
the second layer. Consequently, the amount of Rs 91,11,070/- would
have to be halved and the awarded amount under this claim would
stand reduced to Rs 45,55,535/-.
Claim No. 4: Reimbursement of increase in royalty charges.
19. The claim under this head was based upon the notification of
the Government of Maharashtra under Section 15 of the Mines and
Minerals Act, 1957 which took effect from 28.10.2002 whereby royalty
charges on stone, sand and earth were increased. The respondent/
claimant (ITD Cementation) had requested for price adjustment
consequent to the increase in the rates of royalty. It may be pointed out
that the engineer had certified payments for increased royalty and the
employer (the petitioner herein) had made payment for about one year
as certified by the engineer. In October, 2003 the engineer reversed his
decision and directed recovery of the amounts already paid to be
claimant on the ground that this increase in royalty charges could not
be paid separately as the same was covered under the price variation
sub clause 70.3(B), for general materials. Upon an interpretation of the
relevant clause of the contract between the parties, the Arbitral
Tribunal held the claim of Rs 68,66,175/- on account of increase in
royalty charges consequent upon the said notification issued by the
Government of Maharashtra with effect from 28.10.2002 to be justified
and accordingly awarded the same to the respondent/ claimant.
20. A similar conclusion had been arrived at in the case of
another contract between the same parties by the Arbitral Tribunal in
that case. However, after arriving at such a conclusion, namely, that
the claimant was entitled to be compensated for the increase in the
royalty charges, the Arbitral Tribunal in that case had left the amount to
be quantified by the National Highway Authority of India. That Award
became the subject matter of OMP 432/2006 which was dismissed by a
learned Single Judge of this Court vide his judgment dated 14.05.2007.
The same was made the subject matter of an appeal being
FAO(OS) 216/2007 before a Division Bench of this Court. The issues
which arose before the Division Bench were essentially two in number.
One issue touched upon the interpretation of the terms of the contract
and the other related to the quantification of the extra cost allegedly
incurred by the claimant therein. By a judgment delivered on
30.11.2007 [NHAI v. ITD Cementation India Ltd: 2008 (100) DRJ
431 (DB)], the Division Bench was of the view that insofar as the first
issue was concerned, no interference was called for in respect of the
decision on the interpretation placed by the Arbitral Tribunal. The
Division Bench specifically noted that it had been well settled by a long
line of decisions rendered by the Supreme Court that a Court dealing
with a petition under Section 34 of the said Act does not sit in appeal
over the Arbitral Tribunal. After noting the decision of the Supreme
Court in the case of ONGC v. Saw Pipes Ltd: AIR 2003 SC 262, the
Division Bench concluded that there was no reason for it to take a view
different from the one taken by the learned Single Judge that the Award
made by the arbitrators could not be interfered with simply on the
ground that another interpretation of the terms of the contract, no
matter equally plausible, was possible. However, on the issue of
quantification, since the same had been left to the one of the parties to
the dispute, the Division Bench set aside the order passed by the
learned Single Judge as also that part of the impugned Award. The
Division Bench observed that it was incumbent upon the Tribunal to
have quantified the amount payable as revised seigniorage fee and the
Tribunal could not have permitted one of the parties to the dispute to
determine that issue. Consequently, the Division Bench set aside the
Award on the question of quantification of the amount and remitted the
matter to the Arbitral Tribunal for deciding the issue.
21. From this discussion it is apparent that the issue with regard
to reimbursement on account of the increase in royalty charges is no
longer open to debate. In the present case, unlike in the earlier case
reported in 2008(100) DRJ 431 (DB), the Arbitral Tribunal has not left
the issue of quantification open but has arrived at a specific figure of
Rs 68,66,175/- and, therefore, even that lacuna is not there in the
present Award. Consequently, the conclusion of the Arbitral Tribunal
in respect of claim No. 4 cannot be interfered with.
Claim No. 5: Claim for interest.
22. The plea of the petitioner with regard to claim No. 5, which
pertains to the rate of interest to be computed, also does not call for any
interference. It is within the domain of the Arbitral Tribunal to fix the
rate of interest within reasonable bounds and as permissible under the
contract. The Arbitral Tribunal noted that as per Section 37(7) of the
said Act, it had the power to award interest from the date of the cause
of action till the date of actual payment. It also noted that as per
provision made in the appendix to the bid of the contract and sub-
clause 60.8 of the contract agreement, the rate of interest payable on
unpaid sums was 1/30th of 1 % per calendar day, which worked out to
12% per annum compounded monthly. According to the petitioner, the
stipulated amount of interest was only in respect of undisputed sums
certified by the engineer and did not extend to the amounts ultimately
awarded by the Arbitral Tribunal. However, I agree with the
submission made by the learned counsel for the respondent that in
terms of the contract, the parties could have easily envisaged that if an
amount was found to be due the compensation for the delay in making
the payment cannot be computed at 12% per annum compounded
monthly. Furthermore, there is no reason to distinguish between the
undisputed sums certified by the engineer and uncertified payments as
a result of succeeding in a claim before an Arbitral Tribunal. The
learned counsel for the respondent submitted that the interest awarded
at the rate of 12% per annum to be computed monthly would
approximately equivalent to 14% simple interest. He submitted that
even Section 31(7)(b) of the said Act contemplated interest at the rate
of 18% per annum. In view of these submissions, I agree with the
submissions made by the learned counsel for the respondent that the
interest awarded was not unreasonable and not beyond the
contemplation of the parties at the time they entered into the contract.
Consequently, there is no reason to interfere with this part of the Award
either.
23. As a result of the aforesaid discussion, the impugned Award
is upheld except in respect of claim No. 3 where the awarded amount is
reduced from Rs 91,11,070/- to Rs 45,55,535/-. To this extent only, the
petition is allowed. All the other objections raised by the petitioner in
respect of the impugned Award are rejected. The petition stands
disposed of accordingly. There shall be no order as to costs.
BADAR DURREZ AHMED (JUDGE) August 07, 2009 SR
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!