Citation : 2009 Latest Caselaw 2997 Del
Judgement Date : 4 August, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP No.393/2009
% Date of decision:04.08.2009
M/S N.E. LINK EXPRESS ...Petitioner
Through: Mr. C. Mukund, Mr. Ashok Jain & Mr.
Pankaj Jain, Advocates
Versus
MAHANAGAR TELEPHONE NIGAM LTD.... Respondent
Through: Nemo
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? Yes
2. To be referred to the reporter or not? Yes
3. Whether the judgment should be reported Yes
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. The petition under Section 34 of the Arbitration Act, 1996 has
come up for admission. The counsel for the petitioner was heard for
some length on 21st July, 2009 when the hearing was adjourned to
enable him to place on record portions of the arbitral record sought
to be relied upon him for the purpose of issuance of notice of the
petition. It is stated that the documents were filed after the last
date. However, the same are not on record. The counsel for the
petitioner has handed over another set of the said documents in the
court and the same are taken on record. The counsel has been heard
today also.
2. The challenge is to the portions of the arbitral award dated 28th
March, 2009 of the General Manager (Marketing) of MP Circle,
Bhopal of the Department of Telecommunications, to the extent
against the petitioner.
3. The disputes arose out of an agreement dated 15th June, 2009
between the petitioner and the respondent Mahanagar Telephone
Nigam Limited (MTNL) whereunder the petitioner agreed to
undertake the job of distribution/delivery of all the telephone bills
and other letters to be handed over by the respondent to the
petitioner for delivery, within the jurisdiction of West-II Area. A rate
of Rs.2,100/- per one thousand bills was agreed. The agreement was
for an initial term of one year w.e.f. 15th June, 1999 with an option to
the respondent to extend the same for a further period of three
months. The work under the agreement however admittedly
continued till the month of November of the year 2000.
4. The petitioner raised the following claims before the
arbitrator:-
i. Release of Bank Guarantee in the sum of
Rs.1,10,000/-.
a) The case of the respondent was that in terms of the
agreement between the parties, the bank guarantee could
not be released unless & until the petitioner furnished a "No
Demand Certificate". It was further the case of the
respondent that under the agreement the bank guarantee
could be held in abeyance for at least six months from the
date of receipt of "No Demand Certificate". It was thus
contended that till all the claims were settled, the bank
guarantee could not be released.
b) The arbitrator has found that the bank guarantee could not
be released till the petitioner furnishing the "No Demand
Certificate" and which the petitioner had not submitted. The
claim has thus been disallowed.
ii. For refund of deductions of Rs.16,41,129/- from the petitioner's bills on the respondent.
a) Out of the said amount, Rs.10,43,622/- was deducted for non-
delivery of the bills, Rs.5,44,845/- was deducted as penalty
for non-delivery Rs.52,381/- was deducted as penalty for non-
satisfactory performance and Rs.481/- deducted towards
amount due against wrongly addressed bills. The case of the
respondent was that the said deductions had been made in
accordance with the terms of the agreement and after the
decision for recovery of the said amounts had been taken by
two committees of high level officials. It was further
contended that under Clause 10 of the agreement, the
decision of the MTNL with respect to the said
deductions/penalty was final and binding on the petitioner. It
was further the case of the respondent that the penalty in the
case of non-delivery of bills was provided in the agreement as
surcharge payable by the customers plus 5% of the total
amount subject to a minimum of Rs.100/-
b) The arbitrator found that a number of complainants were
received by the respondent with respect to non-receipt of
bills, certain complaints were made to Lok Adalat as well,
complaints were also received of burning of bills as well as
finding of bundels of bills in public places; on investigation by
the Vigilance Cell of MTNL it was found that the said bills
had been handed over to the claimant for delivery to the
subscribers but which the claimant had failed to deliver;
notwithstanding the same claimant raised its own bill on the
respondent for delivery of the said bills.
c) It was the case of the respondent that payment of 40% of
subscribers bills had been received by it after issuance of
duplicate bills. The respondent held the petitioner liable for
non-delivery of all the said 40% bills and made the deductions
aforesaid as per the formula provided in the agreement itself.
d) The arbitrator, however, found that the respondent in the
evidence has not been able to fully prove that payment of
40% bills had been received after issuance of duplicate bills.
The arbitrator, however, found that in-spite of the respondent
forwarding the complaints on non-delivery to the petitioner,
the petitioner never submitted any compliance reports. The
arbitrator also held that merely because the payments had
been made by the subscribers after obtaining duplicate bills
was not indicative of those many bills having been not
delivered by the petitioner. It was held that there could be
various other reasons/circumstances owing to which the
subscribers had made payment by way of duplicate bills. The
arbitrator, however, found that the respondent had
established receipt of number of complaints from the
subscribers of non-delivery. The arbitrator thus held that
only 40% of the payment received by MTNL after issuance of
duplicate bills could be because of non-delivery of bills by the
petitioner. The arbitrator thus directed refund back of 60%
of Rs.10,43,622/- deducted by the respondent on this account
to the petitioner. However, the arbitrator held that since the
satisfactory performance of the petitioner stood established,
the deductions in the sum of Rs.5,44,845/- & Rs.52,381/- and
Rs.481/- as penalty by the respondent was justified.
iii. Claim of Rs.1,48,000/- for wrong calculations.
This was sorted out during the arbitration proceedings
and does not survive.
iv. Claim of the petitioner of Rs.16,41,129/- by way of interest @ 18% p.a. for delayed payment of its bills.
The arbitrator held that there was no provision in the
agreement regarding interest to be paid on the bills and
as such the said claim could not be considered.
Accordingly, the claim was declined.
v. Claim of Rs.3 lacs per month for notice period.
a) The case of the claimant was that the agreement was for
one year extendable by three months; however, the
respondent continued to give work to the petitioner for
the period beyond that also and then all of a sudden in
November, 2000 terminated the agreement. The
petitioner claimed to be entitled to a reasonable notice of
three months of termination and claimed damages in lieu
thereof.
b) The arbitrator found that Clause 11 of the agreement
provided for one month‟s notice of termination during
the continuity/currency of the contract. It was held that
the contract in the present case having been terminated
after the expiry of terms thereof, the petitioner was not
entitled to any notice and hence the claim for damages in
lieu thereof was declined.
vi. Claim for additional work undertaken.
a) The argument of the counsel for petitioner before this
court is that in terms of the agreement, the petitioner
was to deliver 90000 bills @ Rs.2100/- per 1000 bills; the
contract permitted a variation of 25%; The bills
delivered by the petitioner were admittedly more than
the said variation also. The petitioner claimed for the
said excessive bills @ Rs.10 per bill i.e. instead of
Rs.2,100/- per 1000 bills, Rs.10,000/- per 1,000 bills. The
respondent paid for the said excessive bills also at the
contractual rate of Rs.2100/- for every 1000/- bill or
Rs.2.10p per bill.
b) The arbitrator found that the agreement was to deliver
all the bills in a particular territory irrespective of the
number and at the price agreed between the parties. The
arbitrator also found that the agreement nowhere
provided that the petitioner shall not deliver STD/ISD
bills of high value and the high value of the STD/ISD bills
did not give any right to the petitioner to demand
additional amount by calling it additional services; the
value of the bill had nothing to do to establish the cost of
delivery. The claim of the petitioner was thus not found
tenable even in terms of the agreement and the claim
was dismissed.
vii. Claim for the salary of two senior officers @ Rs.50,000/- per month for over 18 months.
The arbitrator found the said claim also to be without any
basis and dismissed the same.
5. The counsel for the petitioner had on 21st July, 2009
concentrated the challenge to the finding of the arbitrator‟s as to the
imposition of penalty and damages for non-delivery. It was argued
that the arbitrator having found the claim of the respondent for
Rs.10,43,622/- on the basis of 40% bills having not been delivered, to
have not been established, has arbitrarily reduced the said claim by
60%. The award to that extent was stated to be arbitrary, untenable
and without any reason whatsoever.
6. The parties had chosen their private forum of arbitration and
made the same the final arbitrator of disputes of facts as well as law
between them. The arbitrator has in the award not only dealt with
the respective case/pleadings of the parties, their documents but
also discussed the statements of the witnesses recorded before him.
It is on that basis that the arbitrator though finding unsatisfactory
performance of the petitioner, at the same time held that the case of
the respondent of non-delivery of 40% of the bills had not been
established. Undoubtedly, the arbitrator has apparently not given
any reason for reducing the said claim of the respondent by 60%.
However, it cannot be lost sight of that considering the nature of the
disputes, and the evidence led before the arbitrator it is very difficult
for any court or fora to find the precise number, out of thousands of
bills per month, remaining undelivered. A generalization in this
regard becomes necessary. Such generalization by a fora of the
parties choosing cannot be interfered with. Neither in the OMP nor
during arguments also, it has been shown/disclosed that on the basis
of any material before the arbitrator, the exact number can be so
determined or is less than that attributed by the arbitrator to the
petitioner. In the absence of the same it cannot be said that the
percentage should be something other than that arrived at by the
arbitrator. The finding of fact of arbitrator of petitioner being
otherwise guilty of non-delivery, is final and has not been challenged.
7. It cannot also be lost sight of that the only ground under
Section 34 of the Act which can be attracted is that provided under
Section 34 (2) (b) (ii) i.e. of the award being in conflict with the
public policy of India. In-spite of the interpretation of the Supreme
Court in ONGC Ltd. Vs. Saw Pipes Ltd. AIR 2003 SC 2629 of the
same meaning contrary to the substantive law of India, I cannot find
the award in this respect to be contrary to any substantive law. As
far as the requirement in Section 28 of giving reasons is concerned,
there can be straight jacket definition of reasons. Whether "reasons"
exist or not for a particular finding/award, depends upon the nature
of dispute and the facts and circumstances of each case. "Reason" is
a ground or motive for a belief or course of action, a statement in
justification or explanation of belief or action. It is in this sense that
the award must state reasons for the amount awarded. "Reason" is
the link between the materials by which certain conclusions are
based and the actual conclusions. This aspect is dealt in detail in Jai
Singh Vs. DDA 2008 (3) Arb. LR 667 (Delhi) and in DDA Vs.
Sunder Lal Khatri & Sons 157 (2009) DLT 555. It is in this light
that it is to be seen whether the award to this extent is without
reasons.
8. In Gujarat Water Supply & Sewerage Board Vs. Unique
Erectors (Gujarat) Pvt. Ltd. (1989) 1 SCC 532, it was held that
sufficiency of reasons depends upon the facts and circumstances of
the case.
9. Section 65 (g) of the Indian Evidence Act empowers the person
who being skilled to do so, has examined the documents which are
voluminous, to give secondary evidence of their effect and for
general result. I find the position to be the same over here. The
arbitrator who has gone into the entire record and before whom
witnesses have been examined and cross examined has on the basis
thereof returned a finding of the number of bills remaining
undelivered and with respect whereto deductions could be made
from the bills of the petitioner. Such finding, being factual cannot be
set aside for the reason of being without any reasons. The Supreme
Court recently in Kwality Manufacturing Corporation Vs.
Central Warehousing Corporation (2009) 5 SCC 142, even though
in relation of Sections 30 & 33 of the 1940 Act, restated that findings
of facts recorded by the arbitrator ought not to be interfered, unless
inconsistent.
10. In Madhya Pradesh Housing Board Vs. Progressive
Writers & Publishers (2009) 5 SCC 678 also, the challenge to the
arbitral award under the 1940 Act was inter-alia on the ground of
same being based on conjectures and surmises. The Supreme Court
however in-spite of finding that the arbitrator took judicial note of
certain facts which were in the realm of conjectures and surmises,
posed the question as to what was the effect thereof held that the
award even after ignoring the same continued to be valid and
binding between the parties. It was held that issue of fact
determined by arbitrator by taking into account the overall
agreement was not interferable by the court.
11. The counsel for the petitioner has fairly stated that the
imposition of penalty of Rs.5,44,845/- is also in terms of the
agreement. He has however urged that no loss has been proved and
which is essential for imposition of penalty. He has further urged
that for the same non-performance i.e. of non-delivery of bills,
deduction as well as penalty cannot be imposed. It is argued that the
effect thereof would be that the petitioner would be left with no
earning whatsoever out of the contract and which would make the
award unjust and unfair.
12. Once the agreement is found to provide for deduction from the
bills for non-delivery as well as for penalty, it cannot be said that the
view taken by the arbitrator is improbable which no reasonable
person could have taken. Further, I do not find any inconsistency in
the two deductions. While the first is for charging for the services
proved to have been not rendered, the second is for the loss caused
owing to such non-delivery. The said penalty has been arrived at in
accordance with the formula in the agreement. As far as the
contention of the counsel for the petitioner of the penalty being not
leviable without proof of loss, I may notice that the Supreme Court in
Saw Pipes Ltd. (Supra) has held that the conditions of proving of
loss are different where public interest is involved; it is very difficult
to prove the loss when there is a delay in construction of a road or a
bridge. In such cases, the penalty mentioned in the agreement can
be imposed even without proof of loss. In the present case, I do not
find that even to be the position. From the formula for levying of
penalty given in the agreement it is clear that the penalty is for the
loss which would be occasioned to the respondent owing to delay in
receiving payments owing to non-delivery of bills. Moreover, if such
challenges are to be entertained in a proceeding under Section 34,
the jurisdiction exercised by this court would be akin to appellate
and which is not permitted.
13. The counsel for the petitioner has today challenged the award
in so far as disallowing the interest and the claim for extra work.
14. As far as the claim for interest is concerned, it is stated that
the award is perverse. Reliance is placed on Executive Engineer,
Dhenkanal Minor Irrigation Division, Orissa Vs. N.C. Budharaj
(2001) 2 SCC 721 in paragraph 22 whereof it has been held by a five
judge bench that deprivation of monies leads to interest. It is urged
that the arbitrator has declined interest merely on the premises of
there being no provision therefor in the agreement and has not
considered that the petitioner otherwise in law is entitled to interest.
It is further urged that there is no term in the agreement prohibiting
payment of interest. Reliance is also placed on T.P. George Vs.
State of Kerala (2001) 2 SCC 758; However, in this case all that
has been held is that the arbitrator is empowered to grant interest.
15. The question which arises is, should this court interfere with
the award declining interest. It is not as if any substantive law
mandates the arbitrator to, in all circumstances award interest. The
counsel for the petitioner during the hearing also agreed that even
under the Interest Act, relied upon by him the award of interest is
discretionary. Once that be the position, in my view Section 34 does
not permit interference with such an award declining interest.
16. As far as the claim of the petitioner before the arbitrator for
additional work was concerned, admittedly there was no agreement
between the parties for the rate to be paid therefor. A perusal of the
Tender Document pursuant to which the agreement was entered into
between the parties, only in Annexure „B‟ titled "Specifications"
thereto mentions that the bills for delivery will be approximately
94000 per month. The agreement does not limit the number of
bills which were to be delivered. The counsel for the
petitioner also during the hearing did not invite attention to any
such clause. In the absence of any limitation on the number of bills
which the petitioner was to deliver, nothing wrong can be found with
the finding of the arbitrator of the petitioner being entitled to the
same rate as agreed for all the bills and being not entitled to any
higher rate for the bills over and above 94,000 per month.
17. The Division Bench of this court in Gyan Chand Totu Vs.
Subhash Chand FAO (OS) No.1 of 2004, as quoted in NTPC Ltd.
Vs. Wig Brothers Builders & Engineers Ltd. 160 (2009) DLT 642
has held that the pivotal principle while deciding the scope for
interference with awards on ground of public policy is that the award
can be set aside if it is patently illegal, but the illegality must go to
the root of the mater and if the illegalities are of trivial nature, it
cannot be held that the award is against public policy. It was further
held that the award can be set aside, if it is so unfair and
unreasonable, so as to shock the conscience of the court.
18. The necessary ingredient for exercise of jurisdiction under
Section 34, i.e. of perversity shocking the judicial conscience is
found to be missing in this case.
19. Resultantly, the petition is not found deserving of issuance of
notice even and is dismissed. No order as to costs.
RAJIV SAHAI ENDLAW (JUDGE) August 4th, 2009 pp
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!