Citation : 2009 Latest Caselaw 1766 Del
Judgement Date : 30 April, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: April 29, 2009
Date of Order: April 30, 2009
+ OMP 234/2009
% 30.04.2009
Rajendera Sethia ...Petitioner
Through : Mr. Jayant Bhushan, Sr. Adv. with Ms. Preeti, Advocates
Versus
Gail (India) Limited ...Respondent
Through: Mr. Rakesh Munjal with Ms. Rakhi Ray and Mr. S.S. Ray,
Advocates
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?
JUDGMENT
1. By this application under Section 9 of the Arbitration & Conciliation Act,
1996 (for short, "the Act"), the petitioner has made a prayer that the
respondent should be restrained from acting any further in receiving of
tender No.GAIL/ND/BD/C&P/PW8004/2002234 1 (Bid Invitation
No.8000001069) dated 3rd April 2009, inviting Bids for "Transportation of
Polymer from Gail‟s Petrochemical Complex Pata to various Zones across the
Country", particularly with regard to inviting of Bid in respect of Zones West-1
and West-2. The contention of the petitioner is that the petitioner was a
successful bidder in respect of these Zones in the previous tender invited by
the respondent and as per the terms and conditions contained in bid
documents dated 12th August 2008, the petitioner was required to submit
bank guarantee towards earnest money/ bid security. The petitioner had
OMP 234/2009 Rajendra Sethia v. Gail (India) Ltd. Page 1 Of 5 submitted the bank guarantee and the petitioner was duly awarded the
contract pursuant to bid of document dated 12th August 2008 for Region
West-1 and West-2. The respondent had issued a fax of intent dated 16 th
December 2008 awarding the contract for Zones West-I and West-II for an
estimated value of approximately Rs.19.49 crore and in accordance with the
terms and conditions of the contract; the petitioner was required to furnish
the performance bank guarantee. The petitioner was already having contract
vide acceptance letter dated 19th May 2008 in respect of regions Daman and
Maharashtra, falling in the said two zones. Only additional contract was to be
awarded to the petitioner for regions Madhya Pradesh, Silvasa and Goa. The
petitioner wrote a letter that since he was already having the contract for two
regions, he should be allowed to furnish the bank guarantee only in respect of
remaining three regions viz Madhya Pradesh, Silvasa and Goa and sought
clarification regarding this from the respondent. The respondent should have
clarified this and asked the petitioner to give performance bank guarantee
only for three regions but instead the respondent insisted on contract
performance bank guarantee for the entire zones and threatened that in case
of failure, the respondent would be constrained to initiate actions as per the
provisions of the contract. After this threat, the petitioner approached this
Court under Section 9 of the Act and sought an injunction against
encashment of the bank guarantee towards earnest money for a sum of
Rs.21,50,000/-. Since the respondent had retendered the same region again
for which the letter of intent was issued to the petitioner, the petitioner has
approached this Court with this second application under Section 9 of the
Arbitration & Conciliation Act, 1996.
2. Counsel for the respondent submitted that there was no concluded
OMP 234/2009 Rajendra Sethia v. Gail (India) Ltd. Page 2 Of 5 contract between the petitioner and the respondent. Issuance of letter of
intent does not amount to conclusion of contract in terms of clause 1.1.1.0.
The tender documents very categorically provided that the contract shall
mean the agreement between the employer and the contractor for execution
of work including therein all contract documents. The contract documents
have been defined as collective tender document designs, drawings,
specifications, schedule of quantity, rates, letter of acceptance and agreed
variations, if any and such other documents constituting the tender and
acceptance thereof. It is submitted that pursuant to acceptance of tender, no
agreement was executed between the parties as required under the tender
document and mere acceptance of tender does not tantamount to a
concluded contract. Counsel for the petitioner rebutted this argument by
stating that the tender invitation amounted to an offer on behalf of the
petitioner and once this offer was accepted by sending an acceptance letter,
a concluded contract came into force and therefore there was a concluded
contract.
3. Counsel for the respondent further submitted that the tender document
specifically provided that this tender was for „zero deviation‟ tender as
provided in clause 16.2. and the offer was to be made by the parties based on
terms and conditions as specified in the tender document, general conditions
of contract, special condition of contract and instructions to bidder, scope of
work, technical specifications etc. It was also provided that no commercial
clarification or technical clarification will be sought by the bidder after receipt
of bid and in case of any deviation/ non-confirming, the bid was liable to be
rejected. It is submitted that the petitioner‟s non giving of performance bank
guarantee in respect of zones for which he gave bid, amounted to non
OMP 234/2009 Rajendra Sethia v. Gail (India) Ltd. Page 3 Of 5 conformity to the conditions of the tender and the bid therefore stood
rejected despite letter of intent given by the respondent. The acceptance
letter was an indication to the petitioner that if he fulfils all the conditions as
given in the bid, then only the contract will become concluded contract and
the contract will come into force. No concluded contract can come into force
without fulfilling all the conditions.
4. An application under Section 9 of the Act can be made by a party to the
contract where there is an arbitration clause, in the event of a dispute having
arisen and the party intends to refer the dispute to arbitration. The dispute
sought to be referred to the Arbitrator therefore must be specified in the
application. In the present case, the petitioner has not stated as to what
dispute is sought to be referred to the arbitrator.
5. However, the dispute seems to be made out by the petitioner is that
the retendering was bad and was contrary to the contract and amounted to
breach of contract. If, the petitioner‟s contention that there was a concluded
contract is accepted, at the most petitioner would be entitled to the damages
from the respondent for not awarding the contract to be performed despite
alleged fulfilling of the conditions by the petitioner. The petitioner cannot
come to the Court and say that the respondent should be stopped from giving
the contract to anyone else because the petitioner considers that the
respondent had breached the contract with the petitioner. The purpose of
Section 9 is not to keep the broken contract surviving. The intent and purport
of Section 9 is to preserve the interim custody of any goods or order sale of
any goods which are the subject matter of the contract or to secure amount
of the dispute in the arbitration or detention or preservation or inspection of
OMP 234/2009 Rajendra Sethia v. Gail (India) Ltd. Page 4 Of 5 any property which is the subject matter of the disputes or appointment of a
receiver etc. The Court cannot stop a party from breaching the contract nor
can give directions under Section 9 to the Respondent not to breach the
contract. Breaching a contract is a cause which gives rise to arbitration and it
is the arbitrator who has to decide which of the parties is at fault and what
compensation/ damages are to be given.
6. The application filed by the petitioner seeking a relief that the
respondent should be given directions to keep the contract of the petitioner
surviving, presuming that the petitioner had fulfilled all the conditions, is
misconceived. The respondent is at liberty to float tenders in respect of any
services that the respondent requires. If the petitioner considers that its
earlier contract has been breached, the petitioner would be at liberty to raise
this dispute before the Arbitrator and claim compensation. The petitioner
itself pleaded that even the earlier regions for which the petitioner was
having the contract were retendered and the petitioner had participated in
the retendering of the earlier tender on August 2008. The documents filed by
the petitioner show that even in the present tendering process, the petitioner
is participating and has taken part in the conference of the contractors.
7. In view of foregoing facts, I consider that the present application under
Section 9 is not maintainable and is hereby dismissed. No orders as to costs.
April 30, 2009 SHIV NARAYAN DHINGRA J. rd OMP 234/2009 Rajendra Sethia v. Gail (India) Ltd. Page 5 Of 5
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!