Citation : 2009 Latest Caselaw 1763 Del
Judgement Date : 30 April, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ Date of Decision : 30.04.2009
% O.M.P. No.158/2000
H.L. GUPTA CONSTRUCTION LTD. ..... Petitioner
Through: Mr. O.P. Khadaria, Advocate with
Mr. Deepak Khadaria, Advocate.
versus
INDIAN RAILWAY WELFARE ORGN. ..... Respondent
Through: Mr. A.K. Tewari, Advocate.
CORAM:
HON'BLE MR. JUSTICE VIPIN SANGHI
1. Whether the Reporters of local papers may
be allowed to see the judgment? No
2. To be referred to Reporter or not? No
3. Whether the judgment should be reported No
in the Digest?
VIPIN SANGHI, J. (Oral)
1. The respondent Indian Railway Welfare Organization has
challenged the award made by the Arbitral Tribunal dated 24.03.2000
arising out of the contract no. IRWO/GGN/Cont.1/15/III dated
06.05.1992 entered into between the parties, by invoking the
provisions of Section 34 of the Arbitration and Conciliation Act 1996
(The Act). The petitioner had been awarded the work of developing a
housing project for serving and retired railway personnel and their
widows by the aforesaid contract at Sector 15 -II, Gurgaon, Haryana.
Disputes arose between the parties which were initially referred to two
Arbitrators namely Sh. J.L. Kaul and Sh. V.D. Chaddha. The two
Arbitrators appointed the presiding Arbitrator Mr. Gauri Shankar and
the three of them constituted the Arbitral Tribunal. By their impugned
award, they have partly allowed the Claims made by the petitioner and
rejected the counter Claims of the respondent altogether.
2. Mr. Tewari, learned counsel for the respondent/objector has
sought to impugn the award made on the Claims raised by the
petitioner. However, no objection has been raised at the time of
arguments in relation to the rejection of the counter Claims.
3. The first objection raised by Mr. Tewari relates to the award
on Claim No. 2 towards payment of escalation. The Claimant/petitioner
had made a Claim for Rs.29,40,116.00/- towards escalation. The
Arbitrators have allowed the same to the extent of Rs.27,19,876/-. I
may, at this stage, notice a few relevant dates and facts. The date of
commencement of the work under the contract was 14.01.1992. The
stipulated date of completion under the contract was 13.07.1994. The
actual date of completion was 30.11.1995. The respondent employer
granted extension of time without levy of liquidated damages beyond
the stipulated date of completion up to 31.03.1995. The extension
beyond 31.03.1995 i.e. from 01.04.1995 to 30.11.1995, which
translates to about 35 weeks, was granted subject to levy of liquidated
damages under agreement at the rate of Rs. 10,000/- per week as
provided for under Clause 5.2.25. Consequently, liquidated damages
to the tune of Rs. 3.50 lacs were imposed upon the petitioner.
4. The learned Arbitrators, while dealing with Claim for
escalation held that as the extension of time beyond 31.03.1995 was
granted upon payment of liquidated damages (levy of which was
upheld while denying claim No.1 of the petitioner/claimant), the
petitioner contractor was not entitled to any price escalation that had
taken place after 31.03.1995. However, the Tribunal held that for
works done after 31.03.1995 and up to 30.11.1995, the petitioner
would be entitled to payment on the basis of labour/material indices
prevalent in the quarter January-March 1995, since the petitioner
contractor would have been entitled to get the rates prevalent in the
quarter January-March 1995, had the work been completed on or
before 31.03.1995.
5. Learned counsel for the respondent objector submits that the
Tribunal could not have granted the rates based on the indices
prevalent in the quarter January-March 1995. The case of the
respondent is that for work done beyond 31.03.1995, the rates
prevalent should have been based on the labour/material indices
existing at the time of tender opening way back in December 1991.
He refers to Clauses 6.4.0 and 6.4.1 of the contract between the
parties. These clauses reads as follows:
"6.4.0 Price Escalation:
If the prices of materials (not being materials supplied or services rendered at fixed prices by the Employer) and, or wages of
labour required for execution of the work increase, the Contractor shall be compensated for such increase as per provisions detailed below and the amount of the Contractor shall accordingly be valid, subject to the conditions that the compensation for escalation in prices shall be available only for work done during the stipulated period of the contract including such period for which the validity of the contract is extended under the provisions of clause 5.2.24 of the contract without any action under clause 5.8.2 and also subject to the condition that no such compensation shall be payable for a work for which the stipulated period of completion is 6 months or less. Such compensation for escalation in the prices of materials and labour when due, shall be worked out based on the following provisions:
6.4.1 The base date for working out such escalation shall be the last date on which tenders were stipulated to be received."
6. To meet this submission of the respondent, learned counsel
for the petitioner submits that for work done after 31.03.1995, not only
the petitioner had been subjected to levy of liquidated damages at the
rate of Rs.10,000/- per week aggregating to Rs. 3.50 lacs, the
petitioner had also been denied escalation during the period
01.04.1995 up to 30.11.1995. All that the petitioner had been granted
are the rates which were prevalent in the quarter January-March 1995
to which the petitioner would, in any event, have been entitled had the
work been completed on or before 31.03.1995.
7. Having considered the rival submissions and the reasoning
adopted by the learned Arbitrators who have attempted to fairly and
judiciously interpret the contract between the parties, I find the
approach of the Arbitrators to be unassailable. Since the petitioner
contractor would have been entitled to the rates prevalent in the
quarter January-March 1995, if the work had been completed by
31.03.1995, it does not stand to reason that for the left over works,
which got completed by 30.11.1995 the petitioner should be denied to
those rates and should be relegated to the rates when the tenders
were lastly received. Pertinently, the time for execution of the contract
was extended by the respondent upto 31.03.1995 without levy of
compensation. This means that the respondent was obliged to pay
the escalated rates for works done after the initial/stipulated date of
completion. These works obviously would include works done even
after the extended date of completion.
8. A perusal of the award on Claim No. 2 shows that the
escalation amount has been worked out by the Tribunal at Rs.
27,19,876/-. Though the basic reasoning of the Tribunal on which the
awarded amount is founded has been stated, further details are not
available in the award.
9. Mr. Khadaria submits that no objection has been raised by the
respondent to say that the amount of escalation worked out by the
learned Arbitrators at Rs. 27,19,876/- is erroneous or that there is an
arithmetic error in the computation made by the Tribunal. He submits
that if there was any error in the arithmetic computation of the said
amount, it was open to the respondent to have moved the Tribunal
under Section 31 of the Act within 30 days, which was never done.
10. I have been shown the figures of the amount Claimed by the
petitioner in its Statement of Claim aggregating to Rs. 29,40,116/-. It
is clear that the Arbitrators have applied their mind to arrive at the
figure of 27,19,876/- as the amount of escalation due upon application
of the above set out principle in the award. I find no error in the award
relating to Claim No. 2 and consequently uphold the same while
rejecting the respondent's objection.
11. The next objection raised by Mr. Tewari is to the refund of
ground rent awarded to the extent of Rs. 45,811/-. The respondent
had sought to impose ground rent of Rs. 55,811/- on the ground that
the petitioner had occupied the site leading to inconvenience to the
respondent due to the stacking of materials from other contracts of the
petitioner. The contract itself is silent on this aspect. The Arbitrators
interpreted Clauses 5.3.9 and 5.3.10 to hold that these clauses do not
authorize the respondent to levy damages. These clauses reads as
follows:
"5.3.9 Contractor to keep site clear:
During the execution of the work, the Contractor shall keep site reasonably free from obstructions and shall store or dispose off any constructional plant and surplus material and clear away and remove from site any rubbish or temporary work no longer required.
5.3.10 Clearance of site on completion:
On the completion of the work, the Contractor shall clear away and remove from site all constructional plant surplus materials, rubbish and temporary work of every kind. Contractor shall leave whole of the site, work of every kind, and 10 meters distance from the site periphery clear in workman like conditions to
the satisfaction of the Engineer."
12. In my view, there is no error in the interpretation accorded by
the learned Arbitrators to the aforesaid clauses, which may call for
interference at this stage. The Arbitrators, in my view, had correctly
held that if the contractor failed to clear the site, the option available
to the client/respondent is to get the job done by another agency, i.e.
to get the site cleaned, and recover the cost. However, ground rent
could not be recovered. The Arbitrator, in any event, granted an
amount of Rs. 10,000/- on account of the inconvenience stated to have
been suffered by the respondent. Mr. Khadaria has pointed out that
the respondent had led no evidence to defend the said Claim. No basis
for the deduction of Rs.55,811/- towards ground rent had been
established before the tribunal. Consequently, no error can be found
in the award in respect of Claim No. 4. The objections in this respect
are rejected.
13. The third objection raised by the respondent is in relation to
Claim No. 6 which was towards payment of the cost of bore-well. The
tribunal has awarded a sum of Rs. 40,100/- in respect of this Claim on
the basis of consent of the parties. A perusal of the objections
preferred in this court shows that it is not the case of the objector that
the consent to pay Rs. 40,100/- for the bore-well as recorded in the
award, has wrongly been recorded. The bore-well continued to remain
in the use of the respondent. Consequently, I see no merit in this
submission of the respondent and the same is rejected.
14. Learned counsel for the objector has next argued that the
award on Claim No. 5 directing refund of penal rate recovery of Rs.
95,277/- made by the respondent, has been made in violation of the
contractual terms. There were three parts to this refund Claim. Claims
in the first two parts were rejected by the Tribunal. The third part of
Claim No.5, which has partially been allowed by the Tribunal reads as
follows:
"(c) Regarding penal rate of recovery for waste steel, contract provides for recovery for wastage of steel over 5% at twice the normal rate of Rs. 11,000/- per tonne. IRWO havae not established any loss in this matter and therefore, the rate for recovery should be reasonable, since steel was freely available in the market and its sale no longer controlled by the Government. Nevertheless, wastage beyond 5% is not justified & IRWO should not suffer any loss on this account. It is, therefore, considered that BLGC should pay for the extra wastage over 5% @ actual market rate plus 12- 1/2% departmental charges. Taking the actual average purchase rate as Rs. 13,000/- per tonne, the amount of recovery works out to Rs.
95,277/- only. This part of the claim is therefore, allowed t the extent of Rs. 95,277/- only against Rs. 1,42,109/- demanded by BLGC."
15. Mr. Tewari has relied upon Clause 6.3.2 (vi) of the contract
which reads as follows:
"6.3.2 (vi) In case of steel reinforcement, the theoretical quantity of steel shall be on the basis of actual measurements plus 5% to cover for wastages, cut pieces and rolling margins. The contractor will not be required to return the cut pieces of steel, but the recovery for the 5% of the quantity over the measurements will
be made from the Contractor at a fixed price of Rs. 11000/- (Rupees eleven thousand) for Tor Steel Bars and Rs. 10,500/- (Rupees ten thousand five hundred) for MS bar per tonne. The Contractor is permitted to return the unused reinforcement bars above 3 meters to the Employer at the end of the work. The Contractor is permitted to return the unused reinforcement bars above three meters to the Employer at the end of the work."
16. Mr. Tiwari has submitted that the recovery had been made
in accordance with the contractual terms. The Tribunal could not have
ignored the agreements terms and substituted their own notion of
what they thought fair and reasonable in contradiction with the
agreement of the parties.
17. In response to this submission of Mr. Tewari, learned counsel
for the petitioner has argued that the respondent had not established
the suffering of any damages. He also argues that apart from single
rate recovery, the Arbitrators had allowed 12½% of the actual market
rate towards departmental charges.
18. Having considered the rival submissions, I am of the view that
the award of the learned Arbitrators on Claim No. 5 (c) is not
sustainable, since it is squarely in contravention of Clause 6.3.2 (vi) as
extracted above. Pertinently, the Arbitrators themselves take note of
the contractual provision in the opening line of their award on Claim
No. 5 (c) by observing "Regarding penal rate of recovery for
waste steel, contract provides for recovery for wastage of
steel over 5% at twice the normal rate of Rs.11,000 per tonne".
19. The Arbitral Tribunal is a creature of the agreement between
the parties, and it could not have disregarded the contractual terms.
Since the contract clearly provides for recovery for wastage of steel
over 5 per cent at twice the normal rate of Rs. 11,000/- per ton, not
only the parties but the Tribunal was bound by the said term and the
Tribunal was bound to enforce the rights of the parties as contained in
the said term. The Tribunal could not have, on its own, reduced the
penal rate recovery to only 12 ½ per cent by permitting it as
"departmental charges". Consequently, I set aside the award made on
Claim No. 5 (c) for Rs. 95,277/-.
20. Lastly, Mr. Tewari has argued that the Arbitrators have
unreasonably awarded 12 per cent interest in favour of the
respondent. A perusal of the award shows that the Tribunal has not
awarded any interest for the pre-litigation and pendente lite period.
However, interest has been awarded from the date of the award till
actual payment at the rate of 12 per cent per annum. Reliance placed
by Mr. Tewari on Clause 5.2.0 to object even to this award of interest
appears to be misplaced. Clause 5.2.0 merely provides that no
interest shall be payable upon the earnest money or security deposit
or any amount payable to the contractor under the contract except as
provided for under the conditions of the contract. Once the matter has
been referred to the Arbitrators and the Tribunal has crystallized the
liability of the respondent, the said clause cannot be invoked to deny
the Claim of interest for all times to come. The said clause would have
no application to the grant of interest by the Arbitral Tribunal from the
date of the award. Otherwise, it can lead to highly inequitable result,
namely, that the respondent can continue to withheld the amount due
under the award for as long as it desires without even feeling the pinch
of paying interest thereon. As has been held by the Supreme Court in
G.C. Roy Vs. Secretary Irrigation 1992 (1) SCC 508 the award of
interest is merely by way of compensation on account of the falling
value of rupee due to inflation. I, therefore, reject this objection of Mr.
Tewari.
21. For the aforesaid reasons, the petition is disposed off in the
aforesaid terms leaving the parties to bear their respective costs.
VIPIN SANGHI, J.
APRIL 30, 2009 dp
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!