Citation : 2009 Latest Caselaw 1689 Del
Judgement Date : 27 April, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: March 23, 2009
Date of Order: April 27, 2009
+ OMP 123/2009
% 27.04.2009
Municipal Corporation of Delhi ...Petitioner
Through : Mr. Nalin Tripathi, Advocate
Versus
M/s The Care Taker Group & Ors. ...Respondent
Through: Mr. Rajinder Nischal, Advocate for R-1 and R-2
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?
JUDGMENT
1. By this petition the petitioner has raised objections against the award
dated 16th October 2008 passed by the Arbitrator allowing the claims of the
claimant (respondent herein) with interest @ 9% per annum from the date
when the amount became due till payment and also directed for refund of
earnest money.
2. Brief facts relevant for the purpose of deciding this petition are that the
respondent /claimant under a contract had supplied 7583 numbers of red
stone benches for the parks of MCD in Delhi. The rate quoted by the
respondent/ claimant was between Rs.3100 to 3500/-. The same was
approved and a supply order was given to the respondent. After the
respondent completed the supply and raised bills, these bills were verified
and approved by MCD for payment. However, before the payment of the bills
OMP 123.09 MCD v. The caretaker Group & Ors. Page 1 Of 5 could be released, some complaints were received regarding collusion
between MCD employees and the contractor in securing the order for the
benches at a much higher rates than the rates prevalent in the market. It was
stated that the bench like this would not cost more than Rs.600 to 700 but
the supply to MCD was made at the rate of around Rs.3350/- per bench. CBI
conducted an inquiry into this and filed a challan against the
claimants/respondents and against two employees of the petitioner/ objector
namely Shri D.P. Singh, Director (Horticulture) and one junior engineer (Civil).
Since a case was registered on the basis of CBI report, the payment of the
respondent's bill was not made. The respondent, on this raised a dispute
about the non-payment of the amount and filed an application for
appointment of an Arbitrator to this Court. This Court appointed Justice Usha
Mehra (retired) as an Arbitrator who gave an award in favour of the claimant.
3. The award has been assailed on the ground that the award was beyond
the scope and ambit of the agreement between the parties. The learned
Arbitrator failed to appreciate that no payment could be released to the
Claimant during pendency of the criminal case, more so when the challan had
already been filed. It is also submitted that the claim was hopelessly barred
by limitation and the Arbitrator allowed a time-barred claim.
4. It is not disputed that the agreement between the parties had an
arbitration clause and all issues arising out of the contract between the
parties were to be referred to the Arbitrator. Non-payment of the amount of
the bills of the claim is certainly a dispute arising out of the contract and
could have been adjudicated by the Arbitrator. The plea that the claim made
by the respondent/ claimant was beyond the terms of the contract is not
OMP 123.09 MCD v. The caretaker Group & Ors. Page 2 Of 5 tenable. A perusal of record shows that after completion of supply, bills were
raised by the claimant /respondent and when no payment was received by
the claimant, the claimant served a notice on the petitioner on 8 th December
2005 asking the petitioner to release the payment. The petitioner vide its
letter dated 2nd February 2006 informed the respondent that since CBI case
has been registered against him in respect of fixing of red stone benches,
MCD issued an office order dated 23rd August 2004 that the bills would not be
released in favour of the contractor in those cases which are pending
investigation/ inquiry with Vigilance Department or CBI. After receiving this
letter from MCD, the Claimant /respondent initially filed a writ petition for
recovery of the amount before this Court, but without success and later on
invoked the arbitration clause by making an application before this court in
July 2007. Thus under no stretch of imagination, it can be said that the claim
raised by the claimant was barred by limitation. If the limitation is counted
from 23rd August 2004 when the petitioner issued an office order that
payment shall not be made in those cases where investigation /inquiry is
made even then the claim is not barred by limitation because the claimant
had raised a dispute on 11th July 2007 by asking the petitioner to appoint an
Arbitrator. When the petitioner failed to appoint an Arbitrator, the respondent
moved this Court for appointment of an Arbitrator. However, the limitation
would actually be counted from 2nd February 2006 when the petitioner
informed respondent that the bills will not be paid. If counted from 2nd
February 2006, the award itself has been made within the period of 3 years
and the claim cannot be said to be barred by limitation.
5. The plea of the petitioner that the Arbitrator could not have proceeded
because of pendency of criminal case against the respondent has been
OMP 123.09 MCD v. The caretaker Group & Ors. Page 3 Of 5 considered by the Arbitrator. The petitioner and the respondent both had
relied upon the judgments and the Arbitrator has analyzed all the judgments
and come to conclusion that there was no bar on the Arbitrator from
proceeding with the determination/ adjudication of the disputes between the
parties. The learned Arbitrator relied upon M/s Mafatlal Industries Ltd. v MTNL
2002 IV AD Delhi 769, wherein this Court has observed that investigation by a
criminal agency or registration of an FIR was no ground to refuse enforcement
of the terms of the contract. The other decision relied upon by the Arbitrator
is Iqbal Singh Marwah & Anr. v. Meenakshi Marwah & Anr. 2005 Cr.L.J 2161 SC
wherein the Supreme Court observed that the standard of proof required in
criminal and civil proceedings are entirely different and civil cases are
decided on the basis of preponderance of evidence while in criminal cases,
the entire burden lies on the prosecution. In K.G. Premshanker v. Inspector of
Police & Anr 2002(3) JCC 1975 SC, the Supreme Court had observed that
where criminal case and civil proceedings are for the same cause, the
judgment of civil court would be relevant if conditions of Section 40 to 43 of
the Indian Evidence Act are satisfied. In State of Rajasthan v. M/s Kalyan
Sundram Cement Industries Ltd. & Ors JT 1996 (3) SC 162, the Supreme Court
has held that pendency of the criminal case would not be an impediment for
proceeding with the Civil suit. Considering this law, the learned Arbitrator
came to conclusion that there was no bar in proceeding with the Arbitral
proceedings. The learned counsel for the petitioner has failed to show as to
how there was a bar on the Arbitrator in proceeding with the Arbitration
proceedings.
6. In all, 49000 red stone benches were purchased by MCD from different
contractors. The Claimant had supplied only 7583 red stone benches. The
OMP 123.09 MCD v. The caretaker Group & Ors. Page 4 Of 5 claimant before the Arbitrator proved that the rates quoted by other
contractors were either matching with the rates of the claimant or they were
higher than the rates of the claimant. The Claimant also produced evidence to
show that the red stone benches of similar quality were procured by
Ghaziabad Municipal Authority on the similar price and the plea that the
prevalent cost of a bench was between Rs.600-700 is a false and baseless
plea. MCD failed to bring any evidence to show that the rates quoted by the
Claimant in the tender were higher than the market rates. It is surprising that
MCD had procured 49000 benches almost at the same rate but the criminal
case and investigation was initiated only against the above two claimants and
not for other claimants. It is also surprising that though it is a case of MCD
that there was collusion between its employees and the contractors, but no
departmental action was initiated by the MCD against the employees
allegedly in league with the contractors and these employees were allowed to
retire and perhaps are also taking full pension benefits and were allowed to
go scot free.
7. The petitioner in this case has miserably failed to show that the award
suffers from any illegality or the Arbitrator acted beyond the terms of the
contract or without jurisdiction. It is settled law that this Court cannot go into
the merits of the award and cannot act as a Court of appeal over the
judgment/ award passed by the Arbitrator. The petitioner has also failed to
bring its case within the ambit and scope of Section 34 of Arbitration &
Conciliation Act, 1996. This petition is liable to be dismissed and is hereby
dismissed. No orders as to costs.
April 27, 2009 SHIV NARAYAN DHINGRA J. rd OMP 123.09 MCD v. The caretaker Group & Ors. Page 5 Of 5
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!