Citation : 2008 Latest Caselaw 1696 Del
Judgement Date : 22 September, 2008
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMPs No. 51/2007 & 52/2007
% Date of decision: 22.09.2008
M/S P.C. SHARMA & CO. ....... Petitioner
Through: Mr. Sandeep Sharma, Advocate
Versus
DELHI DEVELOPMENT AUTHORITY ...... Respondents
& ANOTHER
Through: Mr Gaurav Sarin, advocate for
the Respondent /DDA in OMP.No.51/2007.
Mr Bhupesh Narula, Advocate for the
Respondent/DDA in OMP No.52/2007.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? Yes
2. To be referred to the reporter or not? Yes
3. Whether the judgment should be reported
in the Digest? Yes
RAJIV SAHAI ENDLAW, J.
1. Both the petitions with respect to separate arbitration
proceedings, but between the same parties and involving identical
facts, have been preferred under Sections 5, 11 and 12 of the Old
Arbitration Act, 1940 with the prayer for removal of the respondent
No.2 (also same in both the petitions) appointed as the sole
arbitrator by the respondent No.1 DDA and for appointment of an
independent arbitrator. Replies have been filed by the respondent
No.1 to both the petitions. However, the counsel for the petitioner,
during the hearing, did not press for the relief of change of
arbitrator but only pressed/argued for extension of time under
Section 28 of the Act for extension of time for making of the award.
The counsel for the respondents in each of the cases have opposed
the said prayer for extension of time on the ground of the same being
barred by time. The power of the court to extend the time for
making of the award was not disputed and ,in fact, Mr Gaurav Sarin,
counsel for the respondent in one of the cases himself, cited Hari
Krishna Wattal v Vaikunth Nath Pandya AIR 1973 SC 2479 and
The Hindustan Construction Co Ltd v Governor of Orissa and
Others AIR 1995 SC 2189.
2. In the facts of the cases, three questions fall for
adjudication i.e., (1) In the absence of the petitioner having filed the
petition under Section 28 of the Act for extension of time, can an
order extending the time for making of the award be made in the
present petition; (2) Whether the prayer of the petitioner for
extension of time is barred by time; (3) If the aforesaid two
questions are answered in favour of the petitioner, whether in the
facts and circumstances of the case, grounds for extension of time
for making of the award are made out.
3. The two cases have had a chequered history. The
agreements from which disputes and differences have arisen appear
to be of the year 1985. Disputes and differences having arisen
between the parties, the petitioner on 20th April, 1993 invoked the
arbitration clause in the agreements. Alleging failure of the
respondent No.1 to appoint the arbitrator, the petitioner in or about
1994 instituted suits for appointment of arbitrator and which were
allowed on 25th August, 1995 with direction to respondent No.1 to
appoint an arbitrator. The respondent No.1 in terms of direction of
this court, appointed an arbitrator on 22.09.1995. The petitioner
filed its claims before the arbitrator. The arbitrator appointed by the
respondent No.1 was changed from time to time. On 15th
September, 1998, the then arbitrator adjourned the proceedings sine
die owing to time for making award having expired and no request
for extension having been received from both the parties. After
considerable time, the petitioner in or about 2001 instituted OMPs in
this court under Sections 5, 11 and 12 of the Act for removal of the
arbitrator and for appointment of an independent arbitrator. The
said OMPs (being OMPs No 28/2001 and 29/2001) were dismissed by
this court vide order dated 28th February, 2006. A perusal of the
said order shows that the petitioner had therein stated that the
petitioner had declined to give its consent to enlargement of time on
the ground that in terms of arbitration agreement, the arbitrator
could only be appointed by name and not by designation, as had
been done by the respondent No.1. However, at the time of hearing
of the said OMPs, removal of the arbitrator was sought only on the
ground that the arbitration proceedings had dragged on for too long
and which called for removal of the arbitrator appointed by the
respondent No.1 and appointment of an independent arbitrator. This
court in the order dated 28th February, 2006 found that the
petitioner itself was to blame for the delay in the arbitration
proceedings and it was the petitioner who had not acceded to
enlargement of time to enable the arbitrator to give the award. The
OMPs were accordingly dismissed.
4. The petitioner preferred appeals against the said order
being FAO(OS) 319/2006 and FAO(OS) 320/2006 to the Division
Bench of this Court against the said order. The Division Bench held,
vide order dated 3rd May, 2006 that the appellant remained silent for
over four years after the proceedings were adjourned sine die and
the delay in the disposal of the arbitration proceedings was
attributable to the petitioner and dismissed the appeals in limine. I
may clarify that the arbitration proceedings were adjourned sine die
on 15th September, 1998 and OMPs were filed in the year 2001 i.e.,
after nearly three years and not four years, as apparently
erroneously recorded in the order of the Division Bench.
5. The petitioner, after the dismissal of the appeals aforesaid,
applied for revival of the arbitration proceedings. The
SE(Arbitration) of the respondent No.1 vide his letter dated 4th July,
2006 directed both the parties to appear before him on 3rd August,
2006 for clarification in the matter. On 3rd August, 2006, the
respondent No.1 sought time to seek legal opinion from the legal cell
for enlargement of the time. The petitioner enlarged the time for
making the award till the date of the award. In these circumstances,
the matter was adjourned to 4th September, 2006. On 4th September,
2006 the respondent No.1 sought further time for seeking legal
opinion. The matter was, thereafter, adjourned to 26th September,
2006 and then again to 19th October, 2006 when the respondent No.1
intimated that the proceedings were adjourned sine die long back
and the arbitrator had become functus officio and, therefore, the
time could not be extended by mutual consent of the parties. It was
thereafter that the present petitions came to be filed in or about
February, 2007.
6. Though, as aforesaid, the hearing was only on the issue of
extension of time and the limitation thereof but I may record that the
reply of the respondent in both OMPs admits the power of the court
to extend the time and, in fact, in reply to OMP 51/2007 the plea of
limitation has not even been taken. The counsel for the respondents
have fairly conceded that the replies have been filed on the premise
that the petitions were for extension of time for making the award.
7. In my view, the petitions as drafted for appointment of an
independent arbitrator even though not pressed for the said relief
were misconceived. Similar prayer had been made by the petitioner
in OMP Nos 28/2001 and 29/2001 filed earlier and which prayer at
the time of hearing of the said OMPs was pressed only for the reason
of delay and which reason had not found favour with the Single
Judge of this court in the order dated 28th February, 2006 and by the
Division Bench in order dated 3rd May, 2006. Thereafter, there was
no subsequent event entitling the petitioner to again seek for
appointment of independent arbitrator. After the dismissal of the
appeal, the arbitration proceedings could not take place owing to the
refusal of the respondent No.1 to consent to extension of time for
making of the award. The respondent No.1 was fully justified in so
refusing and such refusal by the respondent No.1, entitled the
petitioner to only approach this court for extension of time for
making of the award and did not entitle the petitioner to again apply
for appointment of an independent arbitrator. No fault could be
attributed to the arbitrator for not proceeding with the arbitration
owing to the refusal of the respondent to extend the time. Thus the
petitions as filed for appointment of an independent arbitrator
were/are not maintainable.
8. The petitioner has, in the rejoinder filed to the replies of
the respondent No.1 in these petitions, made a prayer for extension
of time, in addition to the prayer for appointment of an independent
arbitrator. As aforesaid, during hearing only extension of time for
making the award was pressed.
9. In Sakalchand Moti v. Ambaram AIR 1924 Bombay 380
and in Madura Mills Co. v. Krishna Ayyar, AIR 1937 Madras 405,
both under the Arbitration Act, 1899, it was held that time could be
extended under Section 12 of the 1899 Act, which was narrower in
language, though corresponding to Section 28(1) of the 1940 Act,
even on an oral prayer made in that behalf and further that the court
was empowered to exercise the power for extension of the time for
making the award even without a party asking for it.
10. In Narsing Das v. Firm Bisandaval AIR 1954 Orissa 29,
it was held that Section 28(1) of the 1940 Act is very wide and
confers full discretion on the court to enlarge time for making award
at any time. In Prahallad Rai v. F.C.I. AIR 1980 Orissa 16, power
under Section 28 of the 1940 Act was exercised on the strength of a
letter sent by someone who was neither a party to the arbitration
proceedings nor a member of the panel of arbitrators. It was held
that the court could extend the time even suo moto in a fit case, of
course, after giving opportunity of hearing to all the parties. This
court also in Union of India v Messrs Khanchand Bhagat Ram
Jain & Sons 6(1970) DLT 460 held that power under Section 28
could be exercised by the court suo moto.
11. Thus, it appears that the courts have always favoured
enlargement of time for making the award even when one of the
parties to the arbitration expressed disinclination or even opposition
to such extension, where the party seeking such extension had not
been guilty of condemnable delay or contumacious conduct. In this
regard see Hari Om Properties v B Datta 80 (1999) DLT 103.
12. The case law was again reviewed in Fertilisers and
Chemicals Travancore Ltd v. Industry Side Pvt. Ltd and Others
1988 (009) Arbitration Law Reporter 0059 Kerala where it was
again held that (a) no application as such is necessary for the court
to exercise the power under Section 28 of the Act; (b) if any
application is filed it is only to be treated as a reminder of the court's
power and if circumstances would justify enlargement of time, it
should be granted in appropriate cases. If the power is exercisable
without any formal application, there is no question of Article 137 of
the Limitation Act coming into play when a court proposes to enlarge
time; (c) exercise of such powers cannot be refused merely because
it is requested for through an application nor could any such
application be dismissed as barred by limitation.
13. The aforesaid judgment in Fertilisers and Chemicals
Travancore Ltd was concurred by this court in Delhi Development
Authority v Girdhar Engineers and Contractors Manu/DE/
0991/2005.
14. Thus, the absence of a petition under the provisions of
Section 28 of the Act could not come in the way of this court
exercising the power under Section 28 of the Act. In the present
case, of course, the petitioner has, in the rejoinder as aforesaid,
made such a prayer. This court even while dismissing the petition
can suo moto exercise the power under Section 28 of the Act.
15. Similarly, argument of the counsel for the respondent that
exercise of power to extend the time is circumscribed by limitation is
no good, it having been held in the judgment (supra) that the same is
not circumscribed by laws of limitation. It is the argument of the
counsel for the respondent that the cause of action for extension of
time had accrued to the petitioner when the proceedings were
adjourned sine die on 15.09.1998 as aforesaid and under Article 137
of the Schedule to the Limitation Act, the time under Section 28 of
the Act could have been extended within a period of three years only
therefrom. It was also argued that the petitioner then, instead of
applying for extension of time had filed OMPs No 28/2001 and
29/2001 for appointment of independent arbitrator and the exercise
of power to extend time would also be barred under Order 2 Rule 2
of the CPC. I do not agree with either of the said contentions.
Independently of the judgment (supra) that the exercise of the power
is not circumscribed by any limitation, I find that the right, if any, to
the petitioner to seek extension of time accrued only in October 2006
when the respondent No.1 refused to concur in extension of time.
The arbitration proceedings were adjourned sine die on 15.09.1998
owing to the petitioner itself having declined to extend the time - the
respondents at that time had not declined to extend the time. Thus,
even if the provisions of Article 137 of Schedule I to the Limitation
Act were to apply, the cause of action for applying for extension of
time would accrue only in October, 2006 and the present petitions
(and the rejoinders therein) were filed within three years.
Irrespective of the applicability of the provisions of Order 2 Rule 2 of
the CPC to the arbitration proceedings, the cause of action for
extension of time and the cause of action for applying under Sections
5, 11 and 12 of the Act are independent and applying under one
would not bar the application under the other.
16. That takes me to the last aspect as to whether in the facts and
circumstances the power to extend the time should be exercised or
not. I may in this regard notice the judgment of this court in
Mahalingashetty & Co. Ltd v NPCC Ltd & Ors 126 (2006) DLT
142 wherein a Single Judge of this court held while agreeing with
the judgment (supra) that the powers under Section 28 are vast and
vide and time can be enlarged even against the intention expressed
in the agreement not to extend time and even suo moto, nevertheless
held that if the delay has been caused on account of a party which
seeks enlargement of time, normally, the court should not enlarge
time, as a person who has caused the delay cannot be allowed to
take advantage of his own wrong and extension of time cannot be
allowed to work injustice to the other party. This court had thus
declined to extend the time.
17. In the present case there is already a finding in the OMPs No
28/2001 and 29/2001 and appeals preferred there from of the
petitioner itself being guilty of delay. However, I find that the delay
on the part of the petitioner was in keeping quiet from 15.09.1998
when the proceedings were adjourned sine die and till 2001 when
OMPs No. 28/2001 and 29/2001 were filed. There is nothing to show
that prior thereto, when nearly 4-5 arbitrators were changed by the
respondent No.1 and when the arbitration proceedings remained
pending from 1995 till 15.09.1998, there was any delay on the part
of the petitioner. The petitioner also cannot be blamed for OMPs No.
28/2001 and 29/2001 having remained pending before this court
from 2001 till 28th February, 2006. No person ought to suffer for the
action (in this case delay) of the court. The petitioner in 2001
aggrieved by the frequent changes in the arbitrators and under the
then legal advice that appointment of arbitrator ought to have been
by name and not by designation had applied for appointment of an
independent arbitrator. The same did not find favour with this court.
The petitioner after the dismissal of the appeal approached for
revival of the arbitration but it could not take place in the
circumstances aforesaid. Of course, the action of the petitioner in
filing the present petitions, again for the same relief which had been
declined earlier, cannot be approved of.
18. However, the fact remains that when the petitioner had
agitated its claim initially within time, merely because the petitioner
has been guilty of delay in pursuing the arbitration from 15.09.1998,
can the petitioner be condemned unheard. The courts, finding a
litigant to be indulging in vexatious practice normally does not throw
out his case or shut his defence but puts him to terms. In the
present case also, in my opinion, it would be too harsh to shut out
the claims of the petitioner and equities would be balanced by
extending the time for making of the award but on the following
terms: (1) the petitioner in the event of succeeding in the arbitration
proceedings and in the event of any award in favour of the petitioner,
would not be entitled to any interest therein from 15.09.1998 till the
date of this order, inasmuch as the petitioner itself is to blame for
the said delay. Though I have held that the petitioner is not to blame
for delay in disposal of OMPs 28/2001 and 29/2001 but the petitioner
at the time of disposal thereof having not requested the court for
extension of time and having again filed the present misconceived
petitions is not entitled to interest, if any, till date; (2) the petitioner,
as a pre-condition to the revival of the arbitration proceedings to pay
costs of Rs 25,000/- in each case to Delhi Legal Services Authority
and furnishes proof thereof to the arbitrator; (3) The petitioner is
directed not to take any adjournment before the arbitrator and to
cooperate in the early disposal thereof.
19. Subject to the petitioner complying with the aforesaid terms, I
extend the time for making of the award by four months w.e.f. first
date before the arbitrator. The respondent No.1 is directed to
appoint /intimate the arbitrator to the petitioner within four weeks
here from. The arbitrator shall proceed with the arbitration from the
point at which the same were discontinued.
With these directions, both petitions are disposed of.
RAJIV SAHAI ENDLAW (JUDGE) September 22, 2008 M
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!