Citation : 2008 Latest Caselaw 1675 Del
Judgement Date : 18 September, 2008
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS (OS) No.2765/1993
Date of decision : 18.9.2008
IN THE MATTER OF
A.R. KHANNA & SONS ..... Petitioners
Through Mr.Raman Kapur with
Mr.Honey Taenja, Adv.
Versus
D.T.C. & ORS. ..... Respondents
Through Mr.Jyotinder Kumar, Adv.
CORAM
* HON'BLE MS.JUSTICE HIMA KOHLI
1. Whether Reporters of Local papers may be
allowed to see the Judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in
the Digest?
HIMA KOHLI, J. (ORAL)
I.A. No. 4917/1994 (by respondents objections u/S 30 & 33 of the Arbitration Act, 1940 and CS (OS) No.2765/1993
1. By way of the present order, this Court proposes
to dispose of the objections filed by the respondent DTC to
the award dated 30.11.1993, passed by Sh.Swami Dial,
Sole Arbitrator, Chief Engineer, CPWD (Retd.).
2. Briefly stated, the facts of the case are that an
agreement was entered into between the petitioner
contractor and the respondent DTC on 10.8.1983, for
construction of Wazirpur Depot-II, Delhi at an estimated
cost of Rs.11,51,333/- plus 93.90% above DSR 1977 i.e.
at a total cost of Rs.22,32,434.69paise. The stipulated
date for the start of the work was 29.7.1983 and the
stipulated date for completion of the contract was
28.1.1984. The time for completion was extended upto
30.9.1984 and the work was actually completed on
16.10.1984. Thereafter, as disputes and differences arose
between the parties at the time of submission of final bill,
the petitioner contractor invoked the arbitration clause
governing the parties and raised certain claims. The
respondent DTC appointed Dr.P.S. Rana as a sole
Arbitrator to adjudicate the claims and counter claims of
the parties and complete the arbitration proceedings with
a direction that the award should be a speaking award. As
the petitioner contractor raised an objection to the
appointment of the aforesaid Arbitrator, he approached
this Court by filing a petition for appointment of any other
Arbitrator, which was disposed of vide order dated
16.5.1989, and Sh.Swami Dial was appointed as a sole
Arbitrator to adjudicate the disputes between the parties
with the direction that the said Arbitrator shall give a
speaking award.
3. Counsels for the parties state that prior to the
passing of the impugned award dated 30.11.1993, an
interim award dated 12.12.1990 was also passed by the
sole Arbitrator whereunder it was directed that the
respondent DTC shall pay a sum of Rs.79,337.75paise to
the petitioner contractor on account of the fact that the
said amounts were accepted by the respondent DTC in the
final bill prepared by them and admitted before the
Arbitrator. This was followed by passing of the impugned
award dated 30.11.1993.
4. Counsel for the respondent DTC assails the
findings given by the learned Arbitrator in respect of
claims no.1, 3 and 5. Under claim no.1, the petitioner
contractor claimed a sum of Rs.14 lakhs on account of
balance payment which was still recoverable by it from the
respondent DTC. Claim no.3 was raised on account of
increase in rates as damages for the work executed after
the expiry of the stipulated date of completion of work and
claim no.5 was on account of reimbursement of statutory
hike under clause 10 (c) of the contract.
5. Counsel for the respondent DTC submits that the
learned Arbitrator erred in awarding an amount of
Rs.3,62,470/- collectively against the aforesaid claims
raised by the petitioner contractor and that he failed to
furnish any details thereof. He states that the learned
Arbitrator did not care to justify the increase beyond the
stipulated date of completion from the agreed
enhancement of 93.91% to 125% and that the learned
Arbitrator failed to take into consideration the actual
measurements of work taken jointly and duly signed and
accepted by the parties. He further submits that the Local
Commissioner appointed by the learned Arbitrator visited
the site but did not take any measurement himself and
that there were many errors in the Local Commissioner's
report which the respondent DTC had raised, but which
were not considered by the learned Arbitrator while
passing the impugned award. It is lastly submitted that
the learned Arbitrator misconducted the proceedings by
directing payment of statutory increase in labour and
material under Clause 10(c) for the reason that for
claiming an amount under Clause 10(c), the petitioner had
to present the records such as muster roll, paid vouchers
etc.,and show them either to the respondent or the
learned Arbitrator, which was not done.
6. Counsel for the petitioner contractor, however,
supports the impugned award and states that it must be
kept in mind that the impugned award was given by an
expert in the field being a Chief Engineer (CPWD) and that
he was well conversant with the kind of disputes which
were being adjudicated by him. He relies on the
judgments rendered in the cases of DDA vs. Bhagat
Construction Co. (P) Ltd. and Anr. reported at 2004 (3)
ALR 548 (Delhi) and DDA vs. Bhagat Construction Co.
Pvt. Ltd. reported at 2004 (3) ALR 481 (Delhi) DB to
state that the Arbitrator need not disclose the
mathematical calculations in the award and if the award
shows application of mind and a view taken by the learned
Arbitrator, which is a plausible view, the same can be
taken to be correct. Counsel for the petitioner contractor
states that the learned Arbitrator has given his decision on
the basis of the evidence of the parties and the decision is
based on questions of facts, which this Court ought not to
interfere with while exercising its powers under Sections
30 and 33 of the Arbitration Act, 1940 (in short, `the
Act').
7. Insofar as the objections raised by the counsel
for the respondent DTC in respect of claims no.1, 3 and 5
are concerned, counsel for the petitioner states that the
learned Arbitrator made his award with regard to the
measurements only after visiting the site and even the
Local Commissioner appointed by him was a retired Chief
Engineer, NDMC and thus an expert in the field. He
further submits that measurements were partly recorded
in the Measurement Book by the respondent DTC at the
relevant time when the work was still going on.
8. A perusal of the impugned award shows that
after referring to the brief facts of the case, the learned
Arbitrator rendered an award wherein he took notice of
the objections of the respondent to the effect that there
was no discrepancy in the record of measurements in the
Measurement Book and whatsoever was due and payable
to the petitioner contractor, had been paid by the
respondent DTC under the interim award. Thereafter, it
was observed that efforts were made to reconcile the
measurements and a Local Commissioner was appointed
who submitted his report. It was also observed that the
representatives of the respondent DTC did not co-operate
fully with the Local Commissioner and opposed his
appointment. Later on, they raised objections to his
findings. As a result, the learned Arbitrator visited the site
personally with the parties. It is noted in the award that
the Arbitrator visited the site of the work and inspected
the various points on the spot by holding an inspection on
10.4.1993. The learned Arbitrator thereafter arrived at
certain conclusions after considering the various disputed
measurements and rendered the award in respect of
claims no.1, 3 and 5.
9. As regards the claim for payment of Rs.14 lakhs
on account of balance payment under claim no. 1, the
award shows that the learned Arbitrator sifted through the
claims prepared by the claimants and identified five sub
heads on the basis of the claims. He assessed the claims
put forward by the petitioner contractor and finally
awarded Rs.3,62,470/- against the claim made for Rs.14
lakhs. The contention of the counsel for the petitioner
contractor to the effect that the Arbitrator was not to
disclose the basis of the mental process for arriving at a
figure and when called upon to give a reasoned award, is
still not required to give a detailed award like Judges do, is
well founded. It is reiterated that as long the Arbitrator
has indicated his trend of mind and indicated the basis on
which he has arrived at such figure, the same is sufficient
for the purposes of giving a reasoned award. The said
trend of mind can be deciphered from a perusal of the
award. (Refer:Kochhar Construction Works Vs. DDA & Anr.
74 (1998) DLT 118. It is also settled law that giving a
collective award by clubbing different claims, cannot be a
ground for assailing an award. [Refer:Firm Madanlal
Roshanlal Mahajan Vs. Hukumchand Mills Ltd, Indore AIR
1967 1030). Hence the objections taken by the
respondent DTC in that regard are rejected being devoid
of merit.
10. Insofar as payment of amounts @ 125%
above the scheduled rate of the respondent DTC is
concerned, the learned Arbitrator while dealing with claim
no.3 took note of the submissions of the petitioner
contractor that the said amount was claimed for the value
of the work done beyond the date of completion, but
observed that the petitioner contractor was not able to
fully justify the said claim and thus the said claim was only
partly accepted, as included in claim no.1. Claim no.1
included subhead (d), whereunder the petitioner
contractor claimed that payment should be made for the
work actually executed beyond the reasonable deviation
limit and that the said work should be paid at a reasonable
market rate or on actual basis. In view of the above, the
petitioner contractor claimed that the value of the work
done after the completion date was for more than Rs.9
lakhs and hence an extra amount of Rs.2,79,900/- was
claimed. However, as noted above, the learned Arbitrator
collectively awarded a sum of Rs.3,62,470/- against claims
no.1, 3 and 5 to the petitioner contractor. In other words,
as against claims no. 1 and 3 for a sum of Rs.14 lakhs and
Rs.2,79,900/- respectively, the petitioner contractor was
paid only a sum of Rs.3,62,470/- in respect of claims
no.1, 3 and 5. There is no reason to interfere in the
impugned award insofar as the aforesaid claims are
concerned, as there appears no error apparent on the face
of the award for the purposes of interference.
11. Counsel for the respondent DTC has also
challenged the findings of the learned Arbitrator in respect
of claim no.4, which pertains to the claim made by the
petitioner contractor for refund of Rs.4,034.50paise, on
account of excess recovery effected by the respondent
DTC against water charges. Counsel for the respondent
DTC states that the petitioner contractor was provided
water by the respondent against 1% charges and that
excess recoveries had already been made from the
petitioner for Rs.4,992.83paise and that the award of
Rs.4,034.50paise against the said claim was wrong.
Counsel for the petitioner contractor denies the same and
states that on the contrary, his clients had made their own
arrangements for water at the site both for construction
and labour and that the respondent DTC had supplied
water only after 26.3.1984, as negotiated, for the work of
cement plaster and for second and third coats of WMB and
therefore, a claim of Rs.9,000/- was made against water
charges. He submits that after payment of the 11th
running bill, the respondent DTC liquidated
Rs.4,965.50paise from the final bill thus leaving
Rs.4,034.50paise payable to the petitioner. A perusal of
the award shows that the learned Arbitrator has returned
a finding on the basis of the material placed on record
confirming the fact that the claimants had made their own
arrangements for water and hence he awarded the
balance amount of Rs.4,034.50paise. The aforesaid
decision is based on the appreciation of the evidence and
purely, a question of fact which, as is settled law, this
Court ought not to interfere with. Re-appreciation of
evidence is not within the scope of the interference by this
Court (Refer: MCD Vs. M/s Jagan Nath Ashok Kumar &
Anr. AIR 1987 SC 2316). The Arbitrator is the final
arbiter of the facts and the law and merely because this
Court may arrive at a different conclusion than the one
arrived at by the learned Arbitrator is not a ground for
interfering with the award. In the present case, even that
is not the case as this Court does not find any error
apparent on the face of the award in respect of findings
returned against claim no.4.
12. The next claim assailed by the counsel for the
respondent DTC is in respect of claim no.8 under which
the petitioner contractor claimed interest @ 24% p.a. on
the awarded sum from the date of the claim, till the date
of payment. As against the aforesaid claim, the learned
Arbitrator granted interest @ 15% p.a. for the awarded
amount payable from 16.5.1989 (the date on which the
sole Arbitrator was appointed by the Court) to 30.11.1993
(the date of passing of the impugned award).
13. Counsel for the respondent submits that the
interest awarded by the learned Arbitrator is erroneous as
no amount whatsoever was due and payable to the
petitioner and hence there was no question of paying any
interest by the respondent. There appears no error on the
face of the award on the issue of interest. It was well
within the power of the learned Arbitrator to award
interest in respect of amounts found due and payable by
the respondent DTC to the petitioner contractor which he
did. As against the interest claimed by the petitioner
contractor @ 24%, the learned Arbitrator granted interest
@ 15%. This Court does not find any reason to interfere
with the rate of interest awarded by the Arbitrator.
14. Lastly, counsel for the respondent DTC states
that the learned Arbitrator erred in overlooking the
counter claim raised for a sum of Rs.1,15,130/- on
account of deficiency and defects in the work done by the
petitioner contractor. He submits that the Arbitrator
wrongly and without any reasons disallowed the said
amount which was levied in accordance with the clause 14
of the contract.
15. It may be noted that in the impugned award,
the learned Arbitrator made a specific mention of the fact
that the respondent DTC had not raised any counter claim
against the petitioner contractor but he proceeded to take
note of the final bill passed by the respondent DTC during
the pendency of the arbitral proceedings, for an amount of
Rs.11,996.62paise as also the recovery statement
attached to the bill. The recoveries made by the
respondent DTC have been enumerated by the Arbitrator
at page 8 of the award, totaling to Rs.4,08,455.30paise.
The learned Arbitrator held that out of all recoveries made
against the petitioner contractor, only four recoveries were
not in order which included the recovery made under
Clause 14, for compensation.
16. In the aforesaid context, the observations made
by the learned Arbitrator at page 5 of the award are
relevant. He has observed that based on the
findings/results regarding deficiency in the road metal
recovered from two trial pits which were dug, the
respondent DTC applied the same yardstick to the entire
work done in the contract. The aforesaid process of
working out the deduction and deficiency was held by the
Arbitrator to be a highly controversial method of working
and not fair to the other party. Holding so, the claim
raised by the respondent DTC by invoking clause 14 of the
contract, was shot down as unjustified. There appears no
error apparent on the record in respect of the aforesaid
finding which in any case, is a finding of fact and as
observed above, this Court should restrain itself from
interfering with the findings of fact which fall within the
domain of the learned Arbitrator. Hence, the objections
raised on behalf of the respondent DTC with regard to the
rejection of the deduction made by the respondent DTC in
its final bill are found devoid of merits.
17. For the foregoing reasons, the objections filed
by the respondent DTC are rejected. The impugned award
dated 30.11.1993, passed by Sh.Swami Dial is made rule
of the Court. The suit is disposed of. Decree sheet be
drawn up accordingly. The parties are left to bear their
own costs.
HIMA KOHLI,J SEPTEMBER 18, 2008 `ns'/KA
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!