Citation : 2008 Latest Caselaw 1818 Del
Judgement Date : 15 October, 2008
IN THE HIGH COURT OF DELHI AT NEW DELHI
ARB.P. 251/2007
Date of decision : 15.10.2008.
IN THE MATTER OF :
SH. R.N. GUPTA ..... Petitioner
Through : Mr. A.K. Trivedi with
Mr. D.C. Saxena, Advs.
versus
UNION OF INDIA ..... Respondent
Through : Mr. Sanjay Katyal, Adv.
CORAM * HON'BLE MS.JUSTICE HIMA KOHLI
1. Whether Reporters of Local papers may be allowed to see the Judgment? No
2. To be referred to the Reporter or not? No
3. Whether the judgment should be reported in the Digest? No
HIMA KOHLI, J. ( O R A L )
1. The present petition is filed by the petitioner under Section
11 (6) of the Arbitration & Conciliation Act, 1996 praying inter alia for
appointment of an arbitrator to adjudicate upon the disputes and
differences between the parties.
2. Briefly stated, the facts of the case are that the petitioner is
in the work of construction and entered into an agreement with the
respondent for execution of Construction of Office Building for NATP at
CTP Complex, Pusa, New Delhi-110012 on a tendered amount of
Rs.1,63,85,453/-. As per the agreement, the date of commencement
of the work was 26.4.2003 and the date of completion was 25.10.2003.
As per the counsel for the petitioner, the petitioner started and
completed the work on 8.3.2004, to the satisfaction of the respondent.
Thereafter, the petitioner submitted a statement of claim to the
respondent, vide letter dated 26.8.2005, claiming a sum of
Rs.8,66,550/-. It is stated that despite the aforesaid demand, the
respondent did not release the payment to the petitioner and as a
result, the petitioner issued a legal notice dated 27.1.2007 to the
respondent invoking Clause 25 of the agreement which provides for
appointment of an adjudicator to decide the disputes between the
parties within a period of 28 days of the receipt of a notification of a
dispute.
3. It is stated by the counsel for the petitioner that despite his
invoking the aforesaid clause and appointment of Mr. P. Krishnan,
Former DGW, CPWD, as an adjudicator, no further action was taken for
adjudication, thus compelling the petitioner to issue yet another legal
notice dated 11.5.2007, invoking the arbitration clause governing the
parties being Clause No.25. As the respondent failed to respond to the
aforesaid legal notice, counsel for the petitioner submits that the
petitioner was compelled to file the present petition.
4. The present petition was filed on 12.7.2007 and notice was
issued thereon on 13.7.2007. Appearance was entered on behalf of
the respondent on 29.9.2008. A reply has been filed to the petition. It
is not disputed in the reply that the respondent failed to act after
receiving the notice dated 11.5.2007 from the petitioner and that the
respondent did not appoint an arbitrator to adjudicate the disputes
that have arisen between the parties. Instead, the stand of the
respondent is that the respondent has already paid the entire amount
due and payable to the petitioner and no dispute subsists.
5. Considering the fact that the respondent has failed to
appoint an arbitrator in terms of Clause 25.3(f) of the agreement
governing the parties, this Court has no option but to allow the present
petition and appoint an arbitrator to adjudicate the disputes between
the parties.
6. In the case of Datar Switchgears Ltd. Versus Tata Finance
Ltd. & Anr., reported in (2000) 8 SCC 151, the Supreme Court has
held that if the vacancy of an arbitrator is not filled till the party
approaches the Court and files a petition for appointment of an
arbitrator by the designated authority of the Chief Justice of that Court
under Section 11(6) of the Arbitration and Conciliation Act, the right to
supply the vacancy by the opposite party stands extinguished. The
ratio of the aforesaid case was approved by the Supreme Court in Punj
Lloyed Ltd. Versus Petronet MHB Ltd., reported in (2006) 2SCC 682
and it was again followed by a Division Bench of this Court in the case
of Delkon (India) Pvt. Ltd. Versus G.M. Bharat Heavy Electricals Ltd.,
reported in 120 (2005) DLT 542 (DB).
7. In view of the aforesaid judgments, the respondent has lost
its right to appoint an Arbitrator, it having failed to do so within 30
days from the date of receipt of the notice from the petitioner for
appointment of an Arbitrator or even prior to the date of institution of
the present petition.
8. In these circumstances, the present petition is allowed.
Justice Manju Goel (Retd.) is appointed as the sole Arbitrator to
adjudicate all the disputes arising between the parties. The parties
shall share the fee equally, which shall be fixed by the Arbitrator.
9. The parties shall appear before the Arbitrator on 12 th
November, 2008 at 4.30 P.M. The Registry is directed to forward a
copy of the order to the Arbitrator forthwith. The parties are also
directed to intimate the Arbitrator about the order.
10. The petition is disposed of.
HIMA KOHLI,J OCTOBER 15, 2008 sk/KA
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!