Citation : 2008 Latest Caselaw 998 Del
Judgement Date : 11 July, 2008
* HIGH COURT OF DELHI AT NEW DELHI
+ FAO(OS) No.385/1996
HARI VANSH CHAWLA ....Appellant
Through:Mr.G.N.Aggarwal, Advocate
Versus
M/S.PREM KUTIR COOPERATIVE GROUP
HOUSING SOCIETY LIMITED ..... Respondent
Through Mr.Manish Kumar, Mr.Amit Kumar and
Mr.Nitin Bhatia, Advocates
CORAM:
HON'BLE THE CHIEF JUSTICE
HON'BLE DR. JUSTICE S.MURALIDHAR
1.Whether reporters of the local news papers be allowed to see the judgment?y
2.To be referred to the Reporter or not ?y
3. Whether the judgment should be reported in the Digest ?y
JUDGEMENT
% 11.07.2008
1. This appeal which arise out of the judgment and order dated
29th February, 1996 passed by the learned single Judge revolves
around the question as to whether an arbitration clause in a
contract survives despite the settlement which had been arrived at
between the parties.
2. The respondent Society is registered under the Cooperative
Societies Act. The Society was allotted land by the Delhi
Development Authority for construction of low income group flats
for its members. The respondent Society appointed M/s. R.K
&Associates as their architects who in turn invited tenders for
construction of flats. In pursuance thereto the appellant submitted
his tender in the prescribed form on 17th September, 1986 and an
agreement was entered into between the parties on 26th April,
1987. The total value of the work envisaged in the contract was
Rs.1.70 crores (aprox.) and the work was to be completed within
the period of 30 months i.e. by September, 1989. But the
appellant was not able to complete the same and the work was
abandoned in between. The appellant used to raise various bills
towards the work done. A third running bill dated 3rd October, 1989
was raised by the appellant which was subsequently revised as a
final bill on 4th November, 1989. It appears that after some
negotiations, the matter was settled between the parties and the
full and final settlement was arrived on 4th December, 1989. Under
the settlement, duly witnessed by the architect, a total sum of
Rs.24,03,000/- was assessed to be due and payable to the
appellant being the value of the work done by him. After deducting
the value of all the material supplied to him by the respondent and
another sum of Rs.50,000/- being income tax deducted at source, a
sum of Rs.14,75,000/- was found to be due and payable to the
appellant. From out of this amount, a sum of Rs.13,75,000/-
(including the amount of mobilization advance) already stood paid
and a balance of Rs.1 lac was, therefore, paid by the respondent to
the appellant by means of a cheque.
3. It appears that in spite of the full and final settlement of all
the claims, the appellant again raised the same claim before the
architect and this was followed by another letter dated 4th
December, 1990 written by the advocate of the appellant to the
respondent Society inviting their attention that in spite of
submitting claims to the architect, no decision has been conveyed
to him and as such the same amounts to withholding of certificate
under the agreement and the claims are required to be referred to
arbitration. He appointed Mr.J.R. Bhalla, Architect, 5, Sunder
Nagar, New Delhi as his arbitrator for adjudication of the disputes
between the parties and called upon the respondent to agree to
Mr.Bhalla's appointment as the sole arbitrator and in case he was
not acceptable as the sole arbitrator, the respondent was
requested to exercise its option by appointing an arbitrator within
15 days of the receipt of the said letter. As no reply had come from
the respondent to the abovesaid letter, the appellant by letter
dated 6th April, 1990 appointed Mr.J.R. Bhalla as the sole arbitrator
and requested him to proceed with the reference.
4. Mr.J.R. Bhalla entered upon reference and made and
published his award dated 14th November, 1990 awarding a sum of
Rs.7,37,699/- in favour the appellant and further directed the
respondent to pay interest @12% p.a on the amount awarded by
him from the date of the award till the date of payment.
Respondent was also directed to issue a certificate in favour of the
claimant towards recovery of income tax deducted at source.
5. After this award had been filed in Court, objections were filed
by the respondent. The main objection of the respondent under
Sections 30 and 33 of the Arbitration Act, 1940 was that after the
parties had entered into the agreement dated 4th December, 1989,
the matter came to an end and all the claims of the appellant were
finally settled and consequently, not only that the main agreement
stood superseded but no reference could also be made to arbitrator
for adjudication of any disputes raised by the appellant. It was also
contended that in any case the claims preferred by the appellant
fell in the category of excepted matters and the same could not,
therefore, be referred to the arbitrator. There being no subsisting
agreement between the parties, the appointment of Mr.J.R. Bhalla
as the sole arbitrator was also challenged and it was urged that he
had no jurisdiction to adjudicate upon the claims raised by the
appellant.
6. The learned single Judge upon consideration of the material
placed on record held that by virtue of the settlement which had
been arrived between the parties by agreement dated 4th
December, 1989, the main contract extinguished and the
arbitration clause contained therein also perished along with it. No
dispute/claims could be referred to the arbitrator and the award of
the arbitrator is therefore wholly without jurisdiction. Consequently
the award dated 14th November, 1990 was set aside.
7. Before us, learned counsel for the appellant strenuously
contended that whether there was discharge of the contract by
accord and satisfaction or not is a dispute arising out of the
contract and is liable to be referred to arbitration. He contended
that despite coming to end of the contract, the arbitration clause
survives and all questions arising out of or in relation to the
execution of the contract are referrable to arbitration. Reliance in
this connection has been placed on the decisions of the Supreme
Court in Damodar Valley Corporation v. K.K.Kar reported in
(1974) 1 SCC 141, M/s. Bharat Heavy Electricals Limited
Ranipur v. M/s.Amar Nath Bhan Prakash reported in (1982) 1
SCC 625, M/s.Bharat Coking Coal Limited v. M/s.Annapurna
Construction reported in AIR 2003 SC 3660, and Chairman &
MD, NTPC Ltd v. Reshmi Constructions, Builders and
Contractors reported in AIR 2004 SC 1330.
8. On the other hand, learned counsel appearing for the
respondent contended that the arbitration would arise only when
there is a subsisting dispute/difference between the parties. Once
there is a settlement of the claims admittedly made by the
appellant, there is no pending dispute and the question of
arbitration of the dispute thereafter would not arise. In view of the
fact that the appellant admittedly accepted the payment in full and
final settlement, there was no arbitrable dispute for reference. He
contends that in view of the settlement, the earlier agreement
between the parties stood perished by substitution of the new
contract in the nature of settlement. He placed reliance on the
decisions of the Supreme Court in M/s.P.K.Ramaiah and
Company v. Chairman & Managing Director, National
Thermal Power Corporation reported in 1994 Supp (3) SCC 126,
State of Maharashtra v. Nav Bharat Builders reported in 1994
Supp(3) SCC 83 and Nathani Steels Ltd v. Associated
Constructions reported in 1995 Supp (3) SCC 324.
9. It is not in dispute that the appellant had settlement with the
respondent in writing. The question emerges whether there exists
arbitrable disputes between the parties. Arbitration clause as
contained in the special conditions of contract was in the following
terms:-
"6. Settlement of Dispute, Arbitration
All disputes and differences of any kind whatever arising out of or in connection with the contract or the carrying out of the works(whether during the progress of the works or after their completion, and whether before or after the determination, abandonment or breach of the contract) shall be referred to and settled by the Architects who shall state their decision in writing. Such decision may be in the form of a final certificate or otherwise. The decision of the Architect with respect to any of the accepted matters shall be final and without appeal. But if either the employer or the contractor be dissatisfied with the decision of the Architect or may matter question or the dispute of any (except any of the accepted matters) or as to the withholding by the Architect of any certificate of which the contractors may within 28 days after receiving notice to such decision give a written notice to the other party through the Architects requiring that such matters in dispute be arbitrated upon such written notice shall specify the matters which are in dispute and such dispute or difference of which such written notice
as has been given and no other shall be and is hereby referred to the arbitration and final decision of a single arbitrator being a fellow of the Indian Institute of Architects to be agreed upon and appointed by both the parties or in case of disagreement to the appointment of a single arbitrator to the arbitration of two arbitrators being both fellow of Indian Institute of Architects or fellow of Institute of Engineers or equivalent one to be appointed by each party, which arbitrators shall before taking upon themselves the burden of reference appoint an umpire.
The Arbitrator, Arbitrators or the Umpire shall have power to open up, review, and revise may certificate, opinion, requisition or notice, save in regard to the excepted matters to determine all matters in dispute which shall be submitted to him or them of which notice shall have been given as aforesaid."
A reading of the above arbitration clause would clearly establish
that all questions in connection with the contract or carrying out of
the works shall be referred to arbitration in the manner prescribed
by the said clause. Thus, it is clear that if there is an arbitrable
dispute it shall be referred to the arbitrator in accordance with the
arbitration clause, but there must exist a subsisting dispute.
Admittedly the parties entered into an agreement dated 4th
December, 1989 on the following terms:
" FULL & FINAL SETTLEMENT
Prem Kutir Coop Group Housing Society Ltd. 9/7 Patodia Hotel, Shakti Nagar, Delhi-110 007 executed an agreement for the construction of 100 flats with M/s. H.V.Chawla & Associates, M- 203, Greater Kailash-I, New Delhi-110048.
Due to some unavoidable circumstances the work was incomplete and the full and final settlement made on 4th December, 1989.
Work done under the contract agreement
Value of the work done 24,03,000.00
Less material supplied 8,78,000.00
15,25,000.00
Less income tax 50,000.00
14,75,000.00
Less already paid 13,75,000.00
Now payable 1,00,000.00
========
A sum of Rs.1,00,000/- (Rs.One lac only) has been paid vide cheque No.115658 drawn on Bank of India, Kamla Nagar Branch, Delhi.
It is agreed by the contractor that the payment was made to all sub-contractors, labour & employee engaged at site for the work done till date. There is any charges for water,electricity, labour, sub-contractors, employees etc., shall be the liability of the contractor.
WITNESS:
President Secretary
R.K. & Associates Treasurer
16-17 Ahluwalia Chambers for Prem Kutir
Near Pushpa Bhawan, Coop GHS Ltd
New Delhi.
Ms/.H.V Chawla &
Associates,
Contractor
Place: New Delhi"
10. The question is whether with the settlement which had been
arrived at between the parties by the aforesaid agreement, the
main contract had extinguished and the arbitration clause
contained therein also perished along with it. The claims which had
been raised by the appellant in his letter dated 23rd December,
1989 were also the claims which had been made in the third
revised final bills submitted to the architect and these were claims
which ultimately referred to the arbitrator for adjudication on which
the arbitrator made and published his impugned award. It was
specifically recorded that due to some unavoidable circumstances
the work was incomplete and the full and final settlement had
arrived at between the parties. The work done under the contract
was assessed at Rs.24,03,000/- and after deducting therefrom the
value of the material supplied and income tax paid as well as
amount already paid as per the running bills, the net amount of
Rs.1 lac was found to be due and payable to the appellant. At the
time of entering into the settlement the parties were aware that
the contractor had raised certain claims, which, according to him,
arose under the terms of the agreement. Taking all these facts into
consideration the parties entered into full and final settlement on
4th December, 1989 whereby the total amount to be paid under the
agreement to the appellant was a sum of Rs.1 lac. The parties
having arrived at a settlement under the aforesaid agreement with
regard to their subsisting disputes and having acknowledged in
writing the full and final satisfaction of their disputes, there was
complete accord and satisfaction by accepting final settlement of
claims.
11. In P.K.Ramaiah's case (supra) the Supreme Court
considered the ambit of accord and satisfaction by the parties
voluntarily entered into and disputation raised thereunder. The
Court after considering the entire controversy held that:
"Admittedly the full and final satisfaction was acknowledged by a receipt in writing and the amount was received unconditionally. Thus there is accord and satisfaction by final settlement of the claims. The subsequent allegation of coercion is an afterthought and a devise to get over the settlement of the dispute, acceptance of the payment and receipt voluntarily given.... Having acknowledged the settlement and also accepted measurements and having received the amount in full and final settlement of the claim, there is accord and satisfaction. There is no existing arbitrable dispute for reference to the arbitration."
In the above case the appellant had admittedly accepted the
amount in full and final settlement and given the receipt. Later it
disputed its correctness on the ground that it was obtained by
coercion. When proceedings were laid for reference to arbitration
the trial court upheld the contention and referred the matter for
arbitration. On appeal the High Court set aside the order. When
the appeal was filed in the Supreme Court, the Court concurred in
the above findings and held that there was no arbitrable dispute.
12. In Nathani Steels case (supra) the Court held that once
there is full and final settlement in respect of any particular dispute
or difference in relation to a matter covered under the arbitration
clause in the contract and that dispute or difference is finally
settled by and between the parties, the said dispute or difference
does not remain to be an arbitrable dispute. Arbitration cannot be
invoked even though for certain other matters the contract may be
in subsistence. Once parties have arrived at a settlement in
respect of any dispute or difference arising out of any contract or
that dispute or the difference is amicably settled by way of final
settlement by and between the parties, unless that settlement is
set aside in appropriate proceedings, it cannot lie in the mouth of
one party to the settlement to spurn on the ground that it was a
mistake and to proceed to invoke arbitration clause. If this is
permitted, the sanctity of the contract, the settlement also being a
contract, would be wholly lost and it would be open to one party to
take the benefit under the settlement and then to question the
same on the ground of mistake without having the settlement set
aside. In the circumstances it was held that since the dispute or
difference was finally settled and payments were made as per the
settlement, it was not open to the respondent unilaterally to treat
the settlement as non est and proceed to invoke the arbitration
clause.
13. In State of Maharashtra v. Nav Bharat Builders (supra)
the respondent therein filed a suit under Section 20 of the
Arbitration Act, 1940 for filing agreement so as to refer the dispute
to the arbitrator. Pending the suit he submitted a letter to the
government on 8th September, 1986 and pursuant to this and
further correspondence, the government constituted a sub-
committee to go into the question of labour escalation claimed by
the respondent. The sub-committee in its report had submitted to
the government for acceptance of the claim of the respondent
subject to the terms mentioned in paragraph 8.0 of its report.
Pursuant thereto, when it was addressed to the respondent, the
respondent in his letter dated 3rd March, 1989 had agreed to
receive the amount of the price escalation on account of labour
component worked out by the committee stating that : "I further
agree to accept the payment as decided by the Government till
completion of the work". Thereafter the recommended amount
was tendered to the respondent and he had accepted the payment
in his letter dated 7th May, 1990 thus: "In continuation of our above
letter as instructed by you we will withdraw from our special suit
No.134, claim in respect of labour escalation". Thereafter the
respondent had disputed the correctness of the amount quantified
contending that it was obtained by coercion and therefore he is
not bound by it. When an objection was raised, the trial judge
accepted the same. On appeal, the High Court held that it is an
arbitrable dispute and arbitrator would decide the same. Allowing
the appeal the Supreme Court held as follows:
"The respondent -contractor acknowledged the receipt of the amount paid to him and stated that he was unconditionally withdrawing his claim in the suit in respect of labour escalation. Thus, there was full and final settlement of the claim and thereby there was no arbitrable dispute in respect of labour escalation. But, any other claims which the respondent made in the suit, the court is to consider whether arbitrable disputes arose under the contract for reference to arbitration and if so whether the respondent is entitled to any amount so claimed."
14. The learned single Judge has referred to the decision in
Union of India v. Kishorilal reported in AIR 1959 SC 1662
wherein after execution of the contracts, the parties entered into
three fresh contracts on successive dates purporting to settle the
disputes on the terms contained therein. By the first of the two
settlements, the respondent agreed to pay certain monies in
settlement respectively of the disputes regarding the first two
original contracts. By the last of these settlements, the respondent
agreed to pay to the appellant in specified instalments certain
monies in settlement of the disputes relating to the third original
contract as also the monies which had then become due on the
first two settlement contracts and had not been paid. In the end , it
provided as follows:
" The contracts stand finally concluded in terms of the settlement and no party will have any further or other claim against the other."
On a question whether arbitration clause in the original contract
had ceased to have any effect and the contract stood finally
determined as a result of the settlement, the Supreme Court held
that the third settlement contract was in substitution of the third
contract and after its execution all the contracts were extinguished
and the arbitration clause contained therein also perished along
with them. After review of the relevant case law, Subba Rao, J, as
he then was, speaking for the majority enunciated the following
principles:
"(i) An arbitration clause is a collateral term of a contract as distinguished from its substantive terms; but none the less it is an integral part of it; (2) however comprehensive the terms of an arbitration clause may be, the existence of the contract is a necessary condition for its operation; it perishes with the contract; (3) the contract may be non est in the sense that it never came legally into existence or it was void ab initio; (4) though
the contract was validly executed, the parties may put an end to it as if it had never existed and substitute a new contract for it solely governing their rights and liabilities there under; (5) in the former case , if the original contract has no legal existence, the arbitration clause also cannot operate, for along with the original contract, it is also void; in the latter case, as the original contract is extinguished by the substituted one, the arbitration clause of the original contract perishes with it; and (6) between the two fall many categories of disputes in connection with a contract, such as the question of repudiation, frustration, breach etc. In those cases it is the performance of the contract that has come an end; but the contract is still in existence for certain purposes in respect of disputes arising under it or in connection with it. As the contract subsists for certain purposes, the arbitration clause operates in respect of these purposes."
15. In the light of the principle enunciated, in the present case it
is clear that after signing of the full and final settlement on 4th
December, 1989 the contract came to an end and there exist no
arbitrable disputes which could be referred to arbitration.
16. In our opinion various decisions referred to by the learned
counsel for the appellant are clearly distinguishable and have no
bearing on the facts of the present case. In Damodar Valley
Corporation case (supra) the Court noted the facts thus:
"It is the case of the appellant that these payments including the return of the deposit amount finally settled the claims of the respondent. No doubt the respondent was asked to submit his bill along with a receipt stating that he received the payment in full and final settlement of all payments and that there was no other claim. But the respondent while submitting his bill did not give the receipt as desired. The amount of the bill was, however, paid after receipt of which the respondent claimed further sums from the appellant including damages for repudiation of the contract."
17. On these facts the Court held that although there was
alleged payment as final satisfaction of the contract, yet as the
respondent did not give any receipt accepting the settlement of the
claim, the payment was unilateral, so the dispute still subsisted and
therefore it was arbitrable dispute and the reference was valid. In
fact the decision in Damodar Valley Corporation case was
considered and held to be distinguishable on facts in the later
decision of the Supreme Court in State of Maharashtra v. Nav
Bharat Builders (supra).
18. In Bharat Heavy Electricals case (supra) the Supreme
Court held that there was no full and final settlement and the
payment was not received under a receipt.
19. The decision in Bharat Coking Coal case (supra) also turns
on its own facts. There the Court held that the fact the respondent
had accepted the final bill would not mean that it was not entitled
to raise any claim. The Court noted that the respondent had not
unequivocally stated that he would not raise any further claim.
20. In Chairman & MD, NTPC case (supra) parties had entered
into an agreement for a project at Kayamkulam. Upon completion
of the work, the respondent therein submitted final bill which was
allegedly not accepted by the appellant, whereafter they
themselves prepared the final bill and forwarded the same along
with a printed format being a "No Demand Certificate". The said
No Demand Certificate was signed by the respondent therein on
the same date. The respondent sent a letter stating that the said
No Demand Certificate was obtained under coercion. The
respondent thereafter invoked the arbitration clause by way of a
letter through his advocate dated 21st December, 1991 with a
request to refer the disputes and difference to the sole arbitrator
for arbitration and the request was accepted by the appellant
through its letter dated 13th February, 1992. Subsequently a
clarificatory letter was sent to the effect that in view of the No
Demand Certificate the contract had come to an end. In these
circumstances, the Court held that the finding that prima facie
there are triable issues before the arbitrator so as to invoke the
provisions of Section 20 of the Arbitration Act, 1940 cannot be said
to be perverse and unreasonable. In our opinion this decision is
also of no assistance to the case of the appellant.
21. In view of the above discussion, we are of the considered
opinion that the learned single Judge has rightly come to the
conclusion that no disputes/claims could be referred to the
arbitrator and that the award of the arbitrator is without
jurisdiction. We find no merit in this appeal. The same is
accordingly dismissed.
CHIEF JUSTICE
S.MURALIDHAR
JULY 11, 2008 (JUDGE)
'v'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!