Citation : 2008 Latest Caselaw 1107 Del
Judgement Date : 23 July, 2008
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS) 2652A/1987
Reserved on: July 10,2008
Pronounced on July 23, 2008
PURI AND CO. ......Plaintiff.
Through Mr. V.K. Mishra, Advocate.
Vs.
INDIAN INSTITUTE OF TECHNOLOGY ......Defendant.
Through Mr. Suresh Sinha, advocate
with Mr. L.P. Sinha, Advocate.
CORAM:
Hon'ble Mr. Justice S. Ravindra Bhat
1. Whether reporters of local papers may be
allowed to see the judgment? Yes
2. To be referred to the Reporter or not? Yes
3. Whether the judgment should be reported
in the Digest? Yes
Hon'ble Mr. Justice S. Ravindra Bhat:
1. In this suit, the claimaint/objector (hereafter referred to
as the plaintiff) challenges the award dated 20.7.1987 of a sole
arbitrator appointed by the parties, to adjudicate their inter se
disputes.
2. The plaintiff was awarded the work of construction of a
building for the Association of Indian Universities, at 16 Kotla Road,
CS(OS) 2652A/1987 page No.1 of 12
New Delhi which included the building portion, Water supply,
Sanitary installation and Drainage. The works were awarded by the
defendant/Indian Institute of Technology (hereafter called "IIT").
Clause 25 of the agreement enjoined the parties to refer inter se
disputes to arbitration. The plaintiff raised certain demands which
were referred to the arbitration of Prof. N.M. Swani, a Director of the
IIT. He entered upon reference on 11.11.1986. After considering
materials on record and the rival pleadings, the arbitrator published
his award on 20.7.1987. As against 20 claims of the plaintiff, the
arbitrator awarded six claims and partially allowed one claim. He
directed payment of 12% per annum simple interest to the claimant.
The IIT, respondent in the arbitration proceedings had counter
claimed on six heads which were rejected.
3. In these proceedings, during the course of hearing arguments
were addressed on the findings of the arbitrator in respect of claim
No.1, claim No.2 and claim Nos. 15 & 16.
4. The plaintiff had claimed refund of Rs.85,000/- on account of
2% rebate withheld by the IIT. The background to this head of claim
is that the plaintiff while tendering for the works, on 9.7.1982
offered this rebate if the contract were awarded within 30 days. It is
common ground that by letters dated 22.7.1982 and 7.8.1982 this
offer of rebate was extended if the agreement were to be finalized by
31.8.1982. The plaintiff claims to have received confirmation of
acceptance of its tender after 10.9.1982. It , therefore, argued before
the arbitrator that deduction of 2% on account of rebate was
inadmissible since the contract was awarded beyond the stipulated
time granted to the IIT in that regard. In defence, the IIT had
contended about having accepted the offer and awardrd the contract
to the plaintiff, through its letter dated 30.8.1982. The said
document was produced as Ex. C-1 with the counter statement of
facts in arbitration proceedings. The arbitrator rejected the
plaintiff's submission and held that acceptance of the tender was
conveyed before relevant date i.e. 31.8.1982 and thus the IIT was
justified in regard to the 2% rebate
5. It was contended by Mr. V.K. Mishra, learned counsel that the
findings in the award with regard to the 2% rebate are factually
untenable and legally unsound. He urged that the IIT had never
dispatched any such letter, dated 30.8.1982 and that it saw the
light of the day for the first time in arbitral proceedings. It was
contended that in terms of the contract all previous correspondence
were deemed part of the agreement. The previous letters, it was
contended by counsel, on the subject were a part of the agreement
and exchanged by the parties. Yet the letter of 30.8.1982 found no
mention and was never a part of the contract or the correspondence.
In these circumstances and in the absence of any corroborative
evidence that the contract was awarded on 30.8.1982 the IIT could
not have legitimately claimed the rebate.
6. Counsel for the IIT, on the other hand, contended that the
findings of the arbitrator are pure questions of facts based on
inferences drawn from the materials available on record. It was
argued that the plaintiff did not deny receiving the other letters
which extended the time up to 30.8.1982; it did not also deny
receiving the letter dated 10.9.1982. Counsel relied on that
document and submitted that it contained a clear reference to the
previous letter awarding the contract, on 30.8.1982 with details of
such letter. Counsel further urged that the plaintiff never protested
or commented about absence of such letter or correspondence in
time or immediately after 10.9.1982 and sought to claim refund of
the rebate for the first time in arbitral proceedings. This, it was
urged, was clearly inadmissible.
7. The court has considered the award on claim No.1. The
Arbitrator considered the letter dated 30.8.1982 which was Ex. 1 of
the counter claim of IIT. He also noticed that IIT's letter of
acceptance dated 10.9.1982 was a part of the contract at page 125
and that it clearly adverted to the previous letter of 30.8.1982
through which acceptance of the tender was conveyed. He,
therefore, concluded that the plaintiff was informed about the
acceptance of the offer before the stipulated date 31.8.1982. The
findings of the arbitrator on this claim in the opinion of the court
cannot be termed as conjectural or based on no evidence. Also the
discussion in the award shows that the arbitrator deliberated on the
rival contentions and drew his independent inference. It may be
possible for a court, while exercising its original jurisdiction to arrive
at a contrary view, in such cases. Yet that is not the standard to be
applied while judging whether the award has to be set aside for legal
misconduct. The view taken by the arbitrator is certainly a
plausible one. In these circumstances, the objections to the
findings on claim No.1 are held to be without foundation and are
therefore rejected.
8. The second challenge to the award centers round findings on
claim No.2. The plaintiff had claimed Rs.42,500/- as refund of 1%
rebate deducted from monthly running payments. The Arbitrator
allowed a portion of this claim except holding that the
respondent/IIT was entitled to retain the deduction to the extent of
Rs.9731.75. It is contended that the deduction of Rs.9731.75
permitted is in error of law as the IIT could not have adjusted this
amount against the security deposit. It is urged that this deduction
was an afterthought since a guarantee bond remained in force till
September, 1985 to indemnify the IIT. Reliance is placed on
documents such as Ex. C-68 and C-75.
9. While tendering for the work, the claimant had offered a 1%
rebate if monthly running bills were paid within one week of their
submission for the work done. This was accepted by the IIT in its
letter dated 10.9.1982. A careful reading of the award would show
that besides noticing a plaintiff's contention, the arbitrator also
independently examined other relevant documents such as Ex. 4
running bills and Ex. C-15 and C-75. Factually the findings can
hardly be characterized as errors of law or betraying an approach or
findings of fact unsupported by evidence amounting to legal mis-
conduct. Therefore, the objections on claim No.2 are also held to be
without basis.
10. The claimants have claimed Rs.62,000/- for non-issue of
cement to their work force on Respondent's off-days and also for late
issue of the cement at 9.00 a.m. instead of 8.00 a.m. on working
days. The plaintiff referred to Ex. C-27, C-28 and C-105 of P-1 in
support of its claim. They claimed that by late issue of cement i.e. at
9.00 a.m. instead of 8.00 a.m., 12.5% of their labour output was
wasted. Non-issue of ement on Institute off-days (Ex. C-27 of P-1)
in addition to the weekly off-days was contrary to provision 2c(i)
page 42 of contract Agreement (R-1). The plaintiff alleged that total
wages paid to the workers and the masons dealing with the cement
work was Rs.4,53,893.50, of which 12.5% was wasted, which the
plaintiff demanded for late issue and the balance for off-days. The
plaintiff gave reports for masons and labour employed on work
involving use of cement. The IIT argued that the plaintiff had been
making lump sum claims giving details neither in the letter asking
for arbitration nor in the statement of claims. The plaintiff, it is
claimed had not given details of their workforce which remained idle
on off-days on account of non-issue of of cement. The IIT averred it
had been issuing cement to the plaintiff continuously whenever it
sought for it, as was evident from the Registrar of cement, which
showed issue of cement on Saturdays and even on some Sundays
and other holidays. Cement could not be issued when the work was
not in progress and the plaintiff did not want it. The Register of
Cement was relied to show long gaps in the progress of work and
that the plaintiff did not work on such days. The IIT therefore,
inferred that plaintiff was not interested in doing the work regularly
and had not mustered sufficient workforce.
11. The arbitrator had rejected this claim after considering the
entries in the register of cement dated 7.3.1983, 9.3.1983,
10.3.1983, 20.3.1983, 26.3.1983 and 27.3.1983. He also
considered the testimony of Shri. J.P. Jain, Junior Engineer IIT.
The questions put to the witness and the answers given by him were
produced verbatim in the award. This court has considered the
arbitrator's findings in this regard. They can hardly be characterized
as errors in law or findings of facts unsupported by evidence. The
arbitrator noted that no written complaints had been
contemporaneously made, when the contract itself was being
worked out in 1982-83 and 1983-84. It was also noticed that the
plaintiff did not keep any particulars about its workers (who
remained idle due to lapses of the IIT in not issuing cement) or
mention at the relevant time, or disclose other relevant particulars
in that regard. In these circumstances the findings of the
arbitrator, attacked as contrary to law are unfounded; certainly also
not on the basis of any lack of consideration of evidence. After all,
the informality attached to arbitration proceedings does not imply
that every claim of a litigant, bereft of supporting proof is to be
regarded as legitimate. There may certainly be some relaxation in
the mode and manner of proving facts; yet the underlying obligation
to adduce evidence continues to rest on those who make claims,
based on factual assertions. The plaintiff failed to prove its facts
here; its objection, to the findings on the claim, have to, therefore,
fail.
12. Claim No. 16 is for the sum of Rs. 52,000 towards additional
charges on scaffolding for the work of aggregate plastering on the
surface of the building. The arbitrator had denied this claim. The
plaintiff had been awarded two contracts for separate parts of the
building. It is contended that the work of plastering could not be
taken up since IIT delayed its decision on construction of "chajjas"
and projections. The claim on this head was Rs. 4000/- per month
for 13 months. The IIT had denied this lump-sum claim as not
tenable. The arbitrator observed that the contract in question
involved construction up-to the roof slab of the third floor; the
fourth and fifth floors were covered by another contract. The
arbitrator reasoned that if the contracts for the other floors had
been awarded to another agency, these questions could possibly
have been legitimately raised. However, since the plaintiff was
awarded the contracts for both parts of the building, (the arbitrator
reasoned) as use cost of the materials was un-spelt, in the later
contract, it could be reasonable to conclude that the plaintiffs used
the materials and equipment available with it for one contract, in
the execution of another. This reasoning, in the opinion of this
court, is unexceptionable. Besides, the plaintiff did not show how it
could claim Rs. 4,000/- per month, for 13 months.
13. A court's power to interfere with an arbitration award, under
Section 30 and 33 of the old Act is well established. From Union of
India -vs- A.L. Ralia Ram AIR 1963 SC 1685 down to Food
Corporation of India -vs- Chandu Construction 2007 (4) SCC 697, it
has been ruled that to constitute misconduct implies something
unreasonable which would fall outside the jurisdiction of the
arbitrator. The standard to be applied for judging the legality of an
award is irrationality, caprice, arbitrariness or the adjudicator-
arbitrator acting beyond the terms of the agreement. (Ref. Bhagwati
Oxygen Ltd. -vs- Hindustan Copper Ltd. 2005(6) SCC 462; Rajasthan
State Mines and Minerals Ltd. v. Eastern Engineering Enterprises and
Another, (1999) 9 SCC 283). It has been further held (U.P. State
Electricity Board v. Searsole Chemcials Ltd. (2001) 3 SCC 397), that
where the arbitrator applies his mind to the pleadings, considers the
evidence adduced before him and passes an award, the Court
cannot interfere by reappraising the matter as if it were an appeal.
14. Another test indicated by the Supreme Court, in - Chandu
Construction(supra) and Bharat Coking Coal Ltd. v. M/s. Annapurna
Construction, (2003) 8 SCC 154,) is that where the arbitrator travels
beyond the contract he acts in excess of jurisdiction in which case,
the award passed by him becomes vulnerable and can be questioned
in an appropriate Court. In this case, the arbitrator, agreed to be
appointed by the parties, was a technical man, whose experience
and judgment was relied on by both parties, and has not been
impeached in these proceedings. He has rendered an award, which
contains reasoning on each contention raised, concerning every
claim; the award is a 100 page document. Neither his approach, or
appreciation of pleadings or evidence betrays any flaw which would
vitiate the findings, in the award.
15. In view of the above reasons, the court is of the opinion that
plaintiff's objections to the award have to fail. They are accordingly
dismissed. Subject to these findings, the award has to be made a
rule of court; the suit is decreed in its terms. No costs.
July 23, 2008 (S. RAVINDRA BHAT)
JUDGE
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!