Citation : 2022 Latest Caselaw 6054 Chatt
Judgement Date : 28 September, 2022
1
ARBA No.38 of 2018
AFR
HIGH COURT OF CHHATTISGARH, BILASPUR
Judgment reserved on 29-08-2022
Judgment delivered on 28-09-2022
ARBA No.38 of 2018
[Arising out of order dated 3-11-2018 passed by the Commercial
Court, Raipur, in MJC No.7/18]
1. Municipal Corporation Bilaspur Through Commissioner,
Municipal Corporation Bilaspur, Vikas Bhawan, Nehru Chowk,
Bilaspur Chhattisgarh.
---- Appellant
Versus
1. Meinhardt Singapore Pvt. Ltd. (India Branch) Having Its
Corporate Office At A-8, Sector-16, NOIDA 201 301, Uttar
Pradesh
Represented Through Arun Kumar Gupta, Director (Contracts)
Aged About 72 Years , S/o Late Sh. M K Gupta
---- Respondent
For Appellant Shri Ashutosh Singh Kachhawaha, Adv. with
Ms Pushpa Dwivedi, Advocate
For Respondent Shri Sandeep S. Tiwari, Advocate
Hon'ble Shri Justice Goutam Bhaduri &
Hon'ble Shri Justice Radhakishan Agrawal
CAV Judgment
The following judgment of the Court is delivered by Goutam
Bhaduri, J.
1) The instant appeal under Section 37 of the Arbitration
and Conciliation Act, 1996 (henceforth 'the Act, 1996')
read with Section 13(2) of the Commercial Courts Act,
ARBA No.38 of 2018
2015 (henceforth 'the Act, 2015') preferred against the
order dated 3-11-2018 passed by the Commercial Court,
Raipur, in MJC No.7/18 wherein the application filed by
the appellant herein under Section 34 of the Act, 1996
was dismissed.
2) The appellant-Municipal Corporation, Bilaspur,
incorporated under the provisions of the Chhattisgarh
Municipal Corporation Act, 1956 (henceforth 'the Act,
1956') issued a NIT/EOI (Notice Inviting Tender/
Expression of Interest) to carry out the work of planning
and designing for execution of Storm Drainage Water
System for Bilaspur City on 15-7-2010 under the
UIDSSMT (Urban Infrastructure Development Scheme
for Small and Middle Towns), a project of the
Government of India, which is a component of JNNURM
(Jawaharlal Nehru National Urban Renewal Mission).
3) Pursuant to the said NIT/EOI, the respondent herein
submitted its bid, which was accepted by the appellant
and contract agreement dated 24-1-2011 was executed
between the parties and the work order was issued on
27-1-2011 in favour of the respondent for executing the
work. The payment of consultancy fees was 1.18% of
the total project cost. Initially the cost of the project
was Rs.44.28 lacs and it was agreed that actual fees
ARBA No.38 of 2018
would be worked out based on the agreed percentage of
the total final cost of the project.
4) The respondent submitted the Inspection Report,
Preliminary Design Report and Draft Detailed Project
Report (DPR) as a part of execution of work and the
payment was made by the appellant for above work as
per the payment schedule. After approval of final DPR,
the respondent claimed Rs.4,07,03,583/- being 1.18% of
total cost project of Rs.333.93 crores. The said claim
was refused by the appellant and, as such, the dispute
was referred to the Sole Arbitrator for adjudication.
5) The respondent raised its claim for consultancy charges
at the rate of 1.18% of the total project cost i.e.
Rs.333.93 crores as per clause 4(C) of the contract
agreement before the Sole Arbitrator. The learned Sole
Arbitrator after considering the submission, evidence
adduced and documents, allowed the claim of the
respondent herein and passed the award to the tune of
Rs.4,07,03,583/-. It has also been observed by the Sole
Arbitrator that in case the award amount is not paid
within a period of three months from 7-2-2018 it would
carry interest at the rate of 9% per annum on the
awarded amount from the date of expiry of three
months.
ARBA No.38 of 2018
6) Being aggrieved by the said award, the appellant
Corporation challenged the same before the learned
Commercial Court under the provisions of Section 34 of
the Act, 1996. The same has been dismissed by the
Commercial Court by the impugned order. Hence, this
appeal.
7) Learned counsel appearing for the appellant would
submit that
▪ the Arbitrator travelled beyond the Terms of
Reference (ToR) as was envisaged under the
NIT/EOI;
▪ the Arbitrator only considered the Pre DPR
activities, but the Post DPR which contained the
Surveys, Investigation, Data Collection and
providing Implementation Support Post DPR to
BMC, was also part of contract;
▪ the expertise of the consultant/respondent was not
only limited to passing of the project but extended
even after the final project is approved while
implementation of the project;
▪ the Arbitrator was required to arbitrate within the
terms of the contract and he had no power apart
from what the parties have given to him under the
ARBA No.38 of 2018
contract;
▪ the post DPR activities which were required to be
performed by the respondent was not considered;
▪ the Arbitration Tribunal has failed to deal with the
post DPR part, therefore, misdirected itself to
decide the issue;
▪ under the scheme, the sharing of expenditure for
the project was 80:10:10 whereby 80% cost was to
be borne by the Government of India and
remaining 10% each to be shared by the
Government of Chhattisgarh and the Municipal
Corporation/appellant;
▪ the final project was not approved by the Ministry
of Urban Development and the Ministry of
Finance, Government of India, therefore, the
finality of the total project cost of Rs.333.93
crores was never approved;
▪ before this Court an application was filed by the
appellant for taking documents on record to show
the letter dated 11-4-2014 issued by the Ministry of
Urban Development JNNURM Directorate,
Government of India, a copy of the same was not
produced by the officer concerned, which shows
ARBA No.38 of 2018
that the final approval was never granted as such
by playing fraud benefit was allowed to be given to
the respondent; and
▪ apart from it the learned Sole Arbitrator and the
learned Commercial Court failed to notice the
aforesaid fact.
In support of his contention, learned counsel would
place reliance upon the decisions of the Supreme Court
rendered in PSA SICAL Terminals Pvt. Ltd. v Board of
Trustees of V.O. Chidambranar Port Trust Tuticorin
and Others 1 and Oil and Natural Gas Corporation
Limited v Western Geco International Limited 2 .
8) Learned counsel appearing for the respondent, per
contra, would submit that :
▪ as per the guidelines framed under the UIDSSMT
Scheme, the Nodal Agency of the Central
Government had already granted approval;
▪ the payment of Rs.4,07,03,583/- was required to be
paid as per the DPR and as per the agreement, DPR
submitted by the respondent was approved by the
SLSC (State Level Sanctioning Committee) and
NBCC (National Building Construction 1 2021 SCC OnLine SC 508 2 (2014) 9 SCC 263
ARBA No.38 of 2018
Corporation Ltd.), which are the nodal agencies to
approve the final DPR;
▪ initially at the inception of work, as per the
contract agreement the respondent was required to
prepare a detailed cost estimate which finally
worked out to Rs.333.93 crores as such when the
final cost of project has been approved by the
appellant, the respondent was entitled to claim;
▪ the respondent is the consultant and the
consultancy cannot act without taking any financial
sanction against the terms of agreement; and
▪ with respect to scope of jurisdiction of this Court
learned counsel would submit that this Court
cannot sit as a Court of appeal over the finding
arrived at by the learned Sole Arbitrator and it
would only exercise the supervisory role, and, as
such, no illegality can be attached to the order of
the learned Commercial Court.
To buttress his contention, learned counsel would place
reliance upon the decisions rendered by the Supreme
Court in State of Chhattisgarh & Anr. v M/s Sal
Udyog Private Limited 3 , MMTC Ltd. v M/s Vedanta
3 Civil Appeal No.4353 of 2010 (decided on 8-11-2021)
ARBA No.38 of 2018
Ltd. 4 and Associate Builders v Delhi Development
Authority 5 .
9) We have heard learned counsel for the parties and
perused the record.
10) Record shows the letter dated 27-1-2011 issued by the
Municipal Corporation, Bilaspur, addressed to the
respondent to start the work for Planning Designing for
Execution of Storm Water Drainage System. Initially the
project cost was Rs.37.53 crores and an amount of fee
was initially fixed at Rs.44.28 lacs. The contract
agreement purport that the Consultant shall perform the
services specified in Appendix VI of the RFP, Terms of
Reference, which is made an integral part of the
Contract. It is not in dispute that the respondent was the
lowest bidder picked up for the consultancy for Planning
Designing for Execution of Storm Water Drainage
System.
11) Initially, a letter under the Expression of Interest was
issued on 15-7-2010 wherein the Terms of Reference
was given, which is quoted below for ready reference :
Terms of Reference :
Getting prepared DPR for Bilaspur City, including surveys,
4 Civil Appeal No.1862 of 2014 (decided on 18-2-2019) 5 (2015) 3 SCC 49
ARBA No.38 of 2018
investigation, data collection, planning and designing various components, detailed Engineering, cost estimation and assisting in representing BMC at various levels for seeking appraisal and approvals from GOCG/GOI and from State level Nodal Agency.
Providing implementation support post DPR to BMC including detailed engineering tender documentation as defined in REP.
12) Subsequently when the contract agreement was executed
on 24-1-2011 in between the appellant and the
respondent, the services includes the services specified
in Appendix IV of the RFP, Terms of Reference, which
is made an integral part of the Contract. The contract
also includes ToR and its objective. Clauses 2.1 & 2.2
i.e. Objective is quoted below for ready reference :
2. Objective :
2.1 The objective of the consultancy is to provide detailed planning Designing for execution of Storm Water Drainage System to BMC, which includes management, design, detailed engineering services, planning procurement support.
2.2 Comprise surveys, investigations, consultancy activities leading to preparation of detailed project reports, bid documents and further procurement support. It includes all necessary investigation including but not limited to topographic and alignment surveys, geo-technical investigations, soil investigation, finalization of design concepts of Storm Water Drainage infrastructure (gravity based), preparation of
ARBA No.38 of 2018
detailed designs for Storm Water Drainage, estimation of costs, finalization of alignment and routing of drain, preparation of tender documents.
13) The Terms of Reference (ToR) also includes the planing
designing for execution of storm water drainage system
for Bilaspur City that includes the Surveys,
Investigations and Mapping of Drainage Infrastructure,
design and cost estimates, BID process management for
identification of contracts etc. for both particularly
scope of service as specified in Appendix-4 is
reproduced herein under:-
As per contract agreement (Annexure C-1) "scope of services" is specified is Appendix 4 of RFP which is reproduced hereunder:-
"3.1 Specific Services
Planning Designing for Execution of Strom Water Drainage System
(a) Surveys, Investigations and Mapping of Drainage Infrastructure.
(1) Carry out detailed Topological and Alignment surveys as needed; Carry out hydraulic, geotechnical and soil investigations, traffic surveys etc. needed to assess impacts, and design drainage infrastructure. Understand and collect information on the latest growth and development trends for Bilaspur Municipal Corporation Area.
(2) Study existing road infrastructure in the Municipality along with existing road side and
ARBA No.38 of 2018
cross drainage.
(3) Map the existing drainage assets, along with road and drainage network.
(4) Carry out surveys, study and assess drainage flows using appropriate sampling methods.
(b) Designs and Cost Estimates
(1) Based on the updated PEDRs, prepare the detailed designs of drainage infrastructure facilities comprising drainage system (includes collection and transmission based on gravity), in the project area in accordance with applicable standards (including the Manual for Drainage by CPHEEO); using standard software's.
(2) Design appropriate drainage facilities and connecting, systems for improving the access to Urban Poor based on the Urban Poor Strategy or Policy being instituted for the Project.
(3) Designing road restoration where needed subsequent to completion of drainage works as per the codes and standards of the Indian Roads Congress (IRC Codes) and Ministry of Road Transport and Highways (MoRT&H). Design and detailed engineering for restoration of roads along with drainage.
(4) Prepare detailed cost estimates; both capital and O&M (5) Prepare detailed economic analysis of the alternative chosen.
(6) Prepare detailed project reports for Bilaspur Municipal Corporation area.
(7) Prepare detailed Operation and Maintenance Plans for Drainage Systems.
(c) Bid Process Management
ARBA No.38 of 2018
and Identification of Contractors Based on the package identified, prepare Bid Documents as per world Banks model documents, Bill of Quantities (BoOs) and constitution drawings."
(Emphasis supplied)
14) As per EOI (Expression of Interest) dated 15.07.2010
providing of service of consultancy by the respondent
includes implementation support post DPR to BMC
including detailed engineering, tender documentation
and the clause 4 of the agreement speaks about the mode
of payment. For sake of brevity, clause 4 of the
agreement payment is reproduced herein under:-
" 4.PAYMENT 4(A) Schedule of payments for Strom Water Drainage System The Schedule of payments for detailed planning and design period.
Sr. Mile Stone % of total amount
No. payments i.e.
planning & design
fees
1. Submission of Inception Report 20%
2. Submission of final concept plan and 20%
updated preliminary desing reports, with maps and drawings etc.
3. Submission of draft detailed project 20% report for Bilaspur, Municipal Corporation.
4. Approved of final DPR and bid 40% documents
"4 (B) Payment conditions:-
Payment shall be made in the form of cheque of Indian National Rupees not later than 30 days following submssion of invoices in duplicate to the
ARBA No.38 of 2018
Coordinator designated paragraph 5. 4(C) FEES The total fees shall be paid at the rate of 1.18% (One point one eight percent) of the total project cost. The estimated fees workout of approximately Rs. 44.28 lakh based on the estimated cost of project. Actual fees shall be worked out based on the agreed percentage of the total final cost of the project."
15) The cost of the project was to be shared by the
Government of India, State Government and the
Municipal Corporation under the UIDSSMT (Urban
Infrastructure Development Scheme for Small and
Middle Towns). For ready reference the operational
mechanism were as under:-
Operational Mechanism : .....On receipt of Minutes from SLSC the MOUD process the proposal for release of central assistance, sign the Memorandum of Agreement (MOA) for urban reforms with State Govt. and send the release proposal to Ministry of Finance.
The sharing of funds is in the ratio of 80:10 between Central Government & State Government and the balance 10% could be raised by the nodal / implementing agencies including ULBs from the internal resources or from financial institutions......
16) Reading of it would show that the Urban local bodies
were required to prepare the detailed Project Reports
pursuant to their development plan and was required to
be submitted to State Level Nodal Agency (SLNA). The
ARBA No.38 of 2018
SLNA further was required to appraise the DPR either in
house or through outsourcing or through State Level
Technical Agencies and after appraisal it was required to
be submitted to the State Level Sanctioning Committee
(SLSC). Meaning thereby first tier was urban body
sanction from the urban body; second was State Level
Nodal Agency; and at third stage firstly it was required
to send the appraise report to all members of SLSC i.e.
State Level Sanctioning Committee including Ministry
and after approval of all projects are considered by
SLSA on approval of the minutes along with
recommendation are required to be sent by the State
Government to the Ministry of Urban Development. On
receipt of Minutes from SLSC, the MOUD process the
proposal for release of Central assistance and further
sign the Memorandum of Agreement (MoA) were
required to be performed. So the final stage of approval
was on the part of Central Govt., who was required to
pay 80% of the project cost.
17) In the instant case, the Municipal Corporation by letter
dated 13.12.2011 approved the final concept plan and
preliminary design report and further the respondent was
informed by the Municipal Corporation to proceed with
final DPR as per contract agreement clause 4(A). In the
meanwhile, as per the detailed cost estimate that is
ARBA No.38 of 2018
project cost was initially found to be 303.50 crores was
enhanced to 354.07 crores, which was approved by
Municipal Corporation and MIC (Mayor-in-Council) by
order dated 10.12.2012. Subsequently, the second tier
letter was written to the State Urban Development
Agency (SUDA) on 10.01.2014 and thereafter the State
Government written a letter on 13.01.2014 to the
Ministry of Urban Development. The respondent
claimed that on 24 t h of February, 2014 the National
Building Construction Corporation Ltd., which is the
nodal agency, approved in principal above projects
subject to the guidelines of UIDSSMT scheme. The
document shows the National Building Construction
Corporation Limited approved on 24.02.2014 the
estimated value was reduced 33393.00 Lakh. Both the
Arbitrator and the Tribunal have said that the project
was deemed to be approved by the Government of India
as also by the State Government, therefore, the non-
applicant was entitled for consultancy charges @ 1.18%
of the total project cost was of 333.93 crores as per
clause 4C of the agreement. As per the submission of
the parties, the respondent was paid the consultancy
charges as per the schedule of payment of agreement up
till stage 3. It was at the fourth stage of payment which
speaks of approval of final DPR to bid document
ARBA No.38 of 2018
wherein 40% was required to be paid, then the dispute
started.
18) The Municipal Corporation accepted the project cost
initially to 37.53 crores of which the cost of 44.28 Lakh
was paid which was on the estimated cost of project.
The appellant herein claimed thereby until the third
milestone of the payment by interim invoices, the bill
was raised and the payment was made by the BMC lastly
on 23.12.2011 but subsequently when the non-applicant
raised the invoice 4 dated 03.03.2014 at the rate of
actual project cost was of 333.91 crores and it was
refused and having the dispute being referred to
Arbitrator, the award has been passed. Arbitrator has
ordered for payment of around 4 crores the award for
payment of consultancy charges @ 1.18% of the total
project cost of Rs.333.91 crores. Having challenged the
same before the commercial Court, the same was
affirmed.
19) The Supreme Court in the case of MMTC Ltd. (supra)
has held that as far as interference with an order made
under Section 34, as per Section 37, is concerned, it
cannot be disputed that such interference under Section
37 cannot travel beyond the restrictions laid down under
Section 34. In other words, the Court cannot undertake
ARBA No.38 of 2018
an independent assessment of the merits of the award,
and must only ascertain that the exercise of power by
the Court under Section 34 has not exceeded the scope
of the provision.
20) Since the appellate power under Section 37 would be
controlled and would be within the purview of limitation
provided under Section 34 of the Act, 1996, to challenge
the arbitral award, it would be relevant to quote the
provisions of Section 34 of the Act, 1996, which is
reproduced herein below:-
34. Application for setting aside arbitral award. --(1) Recourse to a Court against an arbitral award may be made only by an application for setting aside such award in accordance with sub-section (2) and sub- section (3).
(2) An arbitral award may be set aside by the Court only if--
(a) the party making the application furnishes proof that
--
(i) a party was under some incapacity, or
(ii) the arbitration agreement is not valid under the law to which the parties have subjected it or, failing any indication thereon, under the law for the time being in force; or
(iii) the party making the application was not given proper notice of the appointment of an arbitrator or of the arbitral proceedings or was
ARBA No.38 of 2018
otherwise unable to present his case; or
(iv) the arbitral award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration: Provided that, if the decisions on matters submitted to arbitration can be separated from those not so submitted, only that part of the arbitral award which contains decisions on matters not submitted to arbitration may be set aside; or
(v) the composition of the arbitral tribunal or the arbitral procedure was not in accordance with the agreement of the parties, unless such agreement was in conflict with a provision of this Part from which the parties cannot derogate, or, failing such agreement, was not in accordance with this Part; or
(b) the Court finds that--
(i) the subject-matter of the dispute is not capable of settlement by arbitration under the law for the time being in force, or
(ii) the arbitral award is in conflict with the public policy of India.
Explanation 1.--For the avoidance of any doubt, it is clarified that an award is in conflict with the public policy of India, only if,--
ARBA No.38 of 2018
(i) the making of the award was induced or affected by fraud or corruption or was in violation of section 75 or section 81; or
(ii) it is in contravention with the fundamental policy of Indian law; or
(iii) it is in conflict with the most basic notions of morality or justice.
Explanation 2.--For the avoidance of doubt, the test as to whether there is a contravention with the fundamental policy of Indian law shall not entail a review on the merits of the dispute.
] (2A) An arbitral award arising out of arbitrations other than international commercial arbitrations, may also be set aside by the Court, if the Court finds that the award is vitiated by patent illegality appearing on the face of the award:
Provided that an award shall not be set aside merely on the ground of an erroneous application of the law or by reappreciation of evidence.
(3) An application for setting aside may not be made after three months have elapsed from the date on which the party making that application had received the arbitral award or, if a request had been made under section 33, from the date on which that request had been disposed of by the arbitral tribunal:
Provided that if the Court is satisfied that the applicant was prevented by sufficient cause from making the application within the said period of three months it may entertain the application within a further period of thirty days, but not thereafter.
(4) On receipt of an application under sub-section (1), the Court may, where it is appropriate and it is so requested by a party, adjourn the proceedings for a period of time determined by it in order to give the
ARBA No.38 of 2018
arbitral tribunal an opportunity to resume the arbitral proceedings or to take such other action as in the opinion of arbitral tribunal will eliminate the grounds for setting aside the arbitral award.
(5) An application under this section shall be filed by a party only after issuing a prior notice to the other party and such application shall be accompanied by an affidavit by the applicant endorsing compliance with the said requirement.
(6) An application under this section shall be disposed of expeditiously, and in any event, within a period of one year from the date on which the notice referred to in sub-section (5) is served upon the other party.
21) Before this Court an application to take documents on
record in the appellate stage is filed by the appellant.
Reasons assigned in that two important relevant
documents were not produced by the Officer-in-charge
Sudhir Gupta, Superintending Engineer, Municipal
Corporation, Bilaspur as he was arrested in connection
with the offence punishable under the provisions of
Prevention of Corruption Act and the relevant files were
under his possession therefore at that point of time the
documents were not produced. It is stated further that
after the Award was passed by the Commercial Court, a
communication was made by the Municipal Corporation
on 06.11.2018 seeking sanction of amount of Rs.429.932
Lacs for payment to the respondent and the said letter is
filed as Annexure A/5 which is an internal
ARBA No.38 of 2018
communication. It is further stated that in response to
the aforesaid letter an email communication dated
12.11.2018 was received whereby a letter dated
11.04.2018 issued by the Government of India, Ministry
of Urban Development, JNURM Directorate, New Delhi
was produced which purport that six DPRs submitted to
the Ministry for consideration/sanction has come to an
end. The letter of the Government of India dated 11 t h of
April, 2014 is reproduced hereunder:-
Hkkjr ljdkj Government of India 'kgjh fodkl ea=ky; Ministry of Urban Development JnNURM Directorate fuEkkZ.k Hkou Nirman Bhavan New Delhi - 110108 K-14011/39/2013/UD-1 April 11, 2014
To The Secretary & Commissioner, Urban Development Department, Govt. of Chhattisgarh Dau kalyan Singh Bhawan, Mantralaya, Raipur-492001
Subject: Sanction of projects under UIDSSMT during the Transition Phase of JnNURM-reg.
Sir, I am directed to return herewith 06 DPRs (as per list enclosed) submitted to the Ministry for consideration/sanctioned under UIDSSMT during Transition Phase of JnNURM as the mandate to sanction new projects under Transition Phase has come to an end on 31.03.2014. The DPRs may be resubmitted to the Ministry as and when called for.
Encl.: as above.
Yours faithfully
ARBA No.38 of 2018
(RAJESH JAISWAL) Under Secretary to the Govt. Of India
011-23061407
Copy to:-
1. SLNA of the concerned State
2. PS to Secretary(UD)
3. PS to JS (UD&MD), MoUD, Nirman Bhawan, NeW Delhi
4. Sh. Rakesh Raina, MIS/Team Leader, Technical Cell.
5.Chief Town Planner, TCPO (Kind Attn. Sh. K.K. Joadar, Addl. Chief Town Planner, TCPO)
22) As per UIDSSMT after receipt of the Minutes from
SLSC the MOUD process for release of central
assistance, sign the Memorandum of Agreement (MoA)
for urban reforms with State Govt. and send the release
proposal to Ministry of Finance and the sharing of the
fund would in the ratio of 80:10 between Central
Government & State Government and the balance 10%
could be raised by the nodal/implementing agencies.
The contract agreement payment clause 4 t h milestone
speaks about approval of final DPR which also includes
bid document. It is obvious that if the finance was not
accorded from the Central Government, which is a major
stake holder to finance to the extent of 80% of finance
how there can be deemed sanction because of the fact
State bodies and the agencies of the Central Government
have sent it to the Ministry. The proposal unless is
sanctioned by the Central Government by grant of
ARBA No.38 of 2018
amount for all practical purpose, it cannot be said that
approval of final DPR had passed.
23) The Supreme Court in the case of M/s Sal Udyog
Private Limited (supra) has reiterated the law laid down
in the case of Delhi Airport Metro Express Pvt. Ltd. Vs.
Delhi Metro Rail Corporation Ltd. 6 wherein the Court
has held as under:-
15. In Delhi Airport Metro Express Pvt. Ltd. (supra) referring to the facets of patent illegality, this Court has held as under:
"26. Patent illegality should be illegality which goes to the root of the matter. In other words, every error of law committed by the Arbitral Tribunal would not fall within the expression 'patent illegality'.
Likewise, erroneous application of law cannot be categorised as patent illegality. In addition, contravention of law not linked to public policy or public interest is beyond the scope of the expression 'patent illegality'. What is prohibited is for courts to re-appreciate evidence to conclude that the award suffers from patent illegality appearing on the face of the award, as courts do not sit in appeal against the Arbitral Award. The permissible grounds for interference with a 6 (2021) SCC Online SC 695
ARBA No.38 of 2018
domestic award under Section 34 (2A) on the ground of patent illegality is when the arbitrator takes a view which is not even a possible one, or interprets a clause in the contract in such a manner which no fair-minded or reasonable person would, or if the arbitrator commits an error of jurisdiction by wandering outside the contract and dealing with matters not allotted to them. An Arbitral Award stating no reasons for its findings would make itself susceptible to challenge on this account. The conclusions of the arbitrator which are based on no evidence or have been arrived at by ignoring vital evidence are perverse and can be set aside on the ground of patent illegality. Also, consideration of documents which are not supplied to the other party is a facet of perversity falling within the expression 'patent illegality."
24) Both the finding of the learned Arbitrator and also the
finding by the Commercial Court would show that the
payment of 1.18% of total cost project of Rs.333.93 has
been ordered on the premises of deemed approval of
project by Central Govt. for the reason that the final
DPR was submitted was approved by the State Body
SLSC and NBCC Limited a nodal agency of Central
Govt. The letter placed before this Court about shelving
ARBA No.38 of 2018
of project is as back as of the year 2014 and was issued
by the Government of India, Ministry of Urban
Development. Therefore, the finding by both the
Arbitrator and the Commercial Court would be a patent
illegality which goes to the root of the matter in dispute.
This finding is not of re-appreciation of the evidence.
Inasmuch as, Arbitrator has taken a view which is not
even a possible by anyone to be more specific, has
interpreted a clause in the contract in such a manner
which no fair-minded or reasonable person would.
Therefore, the both the findings and the conclusion of
the Arbitrator and the Commercial Court is based on no
evidence and only on presumption and patent wrong
interpretation. Therefore, would be perverse and can be
set aside on the ground of patent illegality. The letter
dated 11.04.2014 which is produced before this Court
was held back by the employee of the corporation for
the best reason known to them which raises fair
questions at times.
25) The Municipal Corporation is a body incorporate and
acts through its officers. The Supreme Court in the
matter of MMTC Ltd. (supra) while reiterating the view
in the case of Associate Builders (supra) also has
reiterated that after the 2015 amendments to Section 34, the
above position stands somewhat modified. Pursuant to the
ARBA No.38 of 2018
insertion of Explanation 1 to Section 34(2), the scope of
contravention of Indian public policy has been modified to the
extent that it now means fraud or corruption in the making of the
Award.
26) If certain important document is held by an officer of a
corporation, which is a body incorporate and in absence
thereof certain awards are passed, it would be an award
pursuant to fraud & corruption at the instance of some
officers of the appellant.
27) The public funds are to be maintained and protected
prudently. The public servants are bound to act in the
interest of public and in accordance with the rule of law.
Integrity and honesty must be the predominant character
of a public servant and there cannot be any leniency
either by the courts or by the State in respect of these
characters to be maintained by the public servants
without any fail.
28) This Court cannot take a hyper technical view when
general public at large are made to suffer for some
independent deliberate act of officers of State. To arrive
at a contrary view, it would amount to precipitate the
fraud by officer of a corporation to allow suffer public
exchequer by sitting at the fence.
ARBA No.38 of 2018
29) Further the Arbitrator also failed to take into account
that payment for the Clause 4 stage milestone would not
only come into play after approval of final DPR and the
BID documents. The BID documents denotes that after
final sanction followed by inviting tender for the
purpose to carry out a job necessarily of bid document
would come to fore and not before. Therefore, the
expression of interest which takes within its sweep the
terms of reference includes providing implement
support, Post DPR to BMC including detailed
engineering tender documentation etc. would in ordinary
sense points out that post DPR role was also required to
be discharged by respondent. Therefore, the Arbitrator
traveled beyond its scope and the Award was passed on
deeming fiction only on the basis of the total final cost
of project was accepted by the Municipal Corporation.
The approval of final DPR since eventually was not
approved by the Union of India as such the finding of
Arbitrator was based on no evidence more so the
Arbitrator traveled beyond the scope of reference.
30) It is the well proposition of law that the role of the
Arbitraotr is to arbitrate within the terms of the contract
and he has no power apart from what the parties have
given him under the contract. {See: PSA SICAL
Terminals Pvt. Ltd. (supra)}.
ARBA No.38 of 2018
31) In view of the aforesaid facts & circumstances of the
case and applying the well settled principles of law to
the facts of the case at hand, we are of the considered
opinion that the finding arrived at by the Arbitrator
would be perverse and is required to be set aside.
Accordingly, we allow the appeal. Consequently, the
arbitral award and the order impugned passed by the
learned Commercial Court are set aside.
32) There shall be no order as to cost(s).
SD/- SD/-
(Goutam Bhaduri) (Radhakishan Agrawal)
Judge Judge
Gowri/Ashu
ARBA No.38 of 2018
Head note
(1) An award allowed to be passed by withholding important document by officer of corporation would be a fraud and amounts to patent illegality to set aside the arbitral award.
(2) Arbitrator cannot arbitrate apart from what the parties have given under the contract.
1-fuxe ds vf/kdkjh }kjk egRoiw.kZ nLrkost vius ikl j[kk x;k Fkk fQj Hkh izdj.k eatwj dj iapkV ikfjr fd;k x;k ,slk iapkV ,d diV gksxk vkSj fof/k }kjk vekU; gksus ls ,slh e/;LFke~ iapkV vikLr fd;k tk ldsxkA
2-ftu fcUnqvksa ds vk/kkj ij vuqca/k dk fu"iknu gqvk gS e/;LFk mu fcUnqvksa ls ijs e/;LFkrk ugha dj ldrk gSA
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!