Citation : 2022 Latest Caselaw 6451 Chatt
Judgement Date : 21 October, 2022
1
AFR
HIGH COURT OF CHHATTISGARH, BILASPUR
Arbitration Request No. 25 of 2021
Ram Singh Yadav S/o Shravan Yadav Aged About 68 Years R/o Basera
Colony, Gali No. 2 Bhartiya Nagar, Ward No. 11 Bilaspur District Bilaspur
Chhattisgarh.
---- Applicant
Versus
1. Union of India Ministry of Railway, Through The Principal Chief
Commercial Manager All Zonal Railway, New Delhi.
2. Director Traffic, Coll. Chhattisgarh Railway Board New Delhi.
3. Senior Divisional Commercial Manager South East Central Railway
Bilaspur Chhattisgarh.
4. Station Director South East Central Railway Bilaspur Chhattisgarh.
---- Respondents
(Cause Title taken from Case Information System)
For Applicant : Ms. Saumya Sharma, Advocate.
For Respondents : Mr. Ramakant Mishra, Deputy Solicitor General
Date of Hearing : 26.08.2022
Date of Order : 21.10.2022
_________________________________________________________
Hon'ble Shri Arup Kumar Goswami, Chief Justice
CAV Order
Heard Ms. Saumya Sharma, learned counsel for the
applicant. Also heard Mr. Ramakant Mishra, learned Deputy Solicitor
General, appearing for the respondents.
2. This is an application under Section 11(6) of the Arbitration
and Conciliation Act, 1996, for short, 'A&C Act' for appointment of an
arbitrator.
2
3. Pursuant to Notice Inviting Tender (NIT) issued on 29.10.2019
to run the Bilaspur Junction Two-Wheeler Stand for three years, the
applicant participated in the tendering process and, being successful, a
letter of acceptance was issued to the applicant on 07.12.2019. An
agreement was also executed, being agreement No. COM-PS-TWO
WHEELER-BSP, by the applicant and by the respondent No.3 on
behalf of South Eastern Central Railways (SECR). However, the
agreement is not dated.
4. Facts
necessary for disposal of the petition, in short, are that
due to Covid-19 pandemic, the train services were stopped and in such
circumstances the Two-Wheeler stand (for short, 'the stand') was more
or less closed till September, 2020. In such circumstances, railway
authorities had sent a letter dated 02.09.2020 to the applicant seeking
his consent to operate the stand for the remaining period of contract
indicating therein that the period from 25.03.2020 to 22.06.2020 to be
treated as dies-non and for the rest period same terms and conditions
would apply. Subsequently, by letter dated 30.09.2020, the applicant
was asked as to whether he will operate the stand on the condition of
"footfall" based calculation of license fee. Under duress, the applicant
agreed to operate the stand although detailed explanation with regard
to "footfall" method was not explained to him for informed consent. It
transpired that by letter dated 29.08.2021, the applicant requested the
authorities to revise the calculation of license fee. As no reply was
received, letter dated 08.09.2021 was issued for appointment of an
independent arbitrator to resolve dispute. In reply, a letter was sent
from the Office of the General Manager (Arbitration) dated 08.09.2021,
requiring the applicant to convey his willingness/ unwillingness
regarding waiver of Section 12(5) & Section 31A (5) of the A&C Act. A
prescribed proforma was also attached to the letter with a further
request to send item-wise claim as well as total claim amount. In the
meantime, the respondents continued to send demand notices and the
applicant deposited whatever revenue he could generate. The
applicant by his letter dated 14.09.2021 informed that he did not agree
to waive off applicability of Section 12(5) of the A&C Act and
accordingly, expressed his unwillingness to waive off his right. The
break-up of the claim, indicating the same to be not necessarily the
final claim, was indicated, further stating that his claim, on that date, is
Rs.10,06,266/-. By the said letter, request was also made to the
General Manager (Arbitration) to take appropriate decision on the
matter of appointment of the arbitrator and to respond back at the
earliest.
5. On 26.10.2021, Deputy General Manager (G) on behalf of
General Manager wrote a letter to the applicant informing that the
competent authority had nominated a panel comprising 04 (four)
Retired Railway Officers of SA Grade and above, in terms of Clause
64(3)(b)(i) of General Conditions of Contract (GCC) for the applicant to
indicate 02 (two) names as his nominees from the panel of names
given in the letter within 30 days from the date of dispatch of the letter,
from which the Competent Authority would appoint one of them as
arbitrator, failing which, it was indicated that all the names appearing in
the panel will be presumed as his approved nominees. The applicant
did not respond to the said letter and filed this application on
26.11.2021 for appointment of arbitrator.
6. In the reply filed by the respondents, it is stated that it had
appointed one Shri Mahesh Kumar Jain, whose name was also one of
the four names mentioned in the letter dated 26.10.2021, by an order
dated 02.12.2021 as a sole arbitrator and therefore, the petition
deserves to be dismissed.
7. Ms. Sharma submits that the applicant having approached
this Court due to failure of the respondents to appoint arbitrator, the
respondents had forfeited their right to appoint arbitrator after filing of
this petition on 26.11.2021. She submits that neither the GCC was
signed by the parties nor the GCC was made part of the agreement
between the parties and therefore, requiring the applicant to nominate
two persons, as indicated by the letter dated 26.10.2021, in terms of
Clause 64(3)(b)(i) of the GCC, was misconceived as Clause 33 of the
agreement entered into between the parties had laid down the manner
of appointment of the arbitrator. In support of her submissions, she
relies on decisions of the Hon'ble Supreme Court in Punj Lloyd Ltd. Vs.
Petronet MHB Ltd., reported in (2006) 2 SCC 638 and in M/s.
Continental India Private Limited Vs. General Manager Northern
Railway, reported in AIR 2022 SC 3526. She also relies on a judgment
of this Court dated 09.05.2022 passed in ARBR No. 38 of 2019
(Central Electronics Limited Vs. South East Central Railway ).
8. Mr. Mishra submits that the respondents waited for 30 days
for the response of the applicant to the letter dated 26.10.2021 and
when no reply was forthcoming, had immediately taken steps for
appointment of arbitrator and therefore, no occasion arises for this
Court to appoint the arbitrator. Mr. Mishra has relied on a decision of
the Hon'ble Supreme Court in Civil Appeal No. 4914 of 2022 dated
25.07.2022 in the case of Mahanadi Coalfields Limited & Another Vs.
M/s. IVRCL AMR Joint Venture.
9. The copy of the present application was served on the
learned counsel for the respondents on the very date of filing, i.e., on
26.11.2021. Admittedly, the order of appointment is subsequent to the
filing of the present petition.
10. Clause 33 of the agreement reads as follows :
"33. All disputes, questions or differences arising
out of or in any way touching or concerning this
agreement (except those the decision whereof is
otherwise here in force specifically provided for) shall
be referred to the sole arbitration of any person
appointed by the General Manager (Arbitration), SEC
Railway at the time of such appointment. There will be
no objection to any such appointment that the person
appointed is a Government Servant, that he has to
deal with the matters to which the agreement relates
and that in the course of his duties as such
Government Servant he had expressed the views on
all or any of the matters in dispute or difference. The
award of such arbitrator shall be final and binding on
the parties to the agreement. It is a term of this
Agreement that in the event of such arbitrator to whom
the matter is originally referred being transferred or
vacating his office or being unable to act for any
reason such General Manager (Arbitration), SEC
Railway as aforesaid at the time of such transfer
vacation of office or inability to act, shall appoint
another person to act as Arbitrator in accordance with
terms of this agreement, such person shall be entitled
to proceed with the reference from the stage at which
it was left by his predecessor. It is also a term of this
agreement that no person other than a person
appointed by the General Manager (Arbitration), SEC
Railway as aforesaid should act as Arbitrator and if for
any reason that it is not possible the matter is not to be
referred to arbitration at all. Subject as aforesaid, the
provision of the Arbitration and Conciliation Act 1996
or any statutory modification or re-enactment thereof
and the rules made there-under from time to time shall
apply to such arbitration. The Arbitrator may with the
consent of parties extend from time to time, the tenure
for making and publishing the award. The venue of
arbitration shall be _________."
11. Perusal of the above would go to show that the manner of
appointment of arbitrator is specifically laid down therein. There is no
reference to the GCC in Clause 33. Mr. Mishra is also unable to show
that there is any reference to GCC in the agreement.
12. In M/s. Continental India Private Limited (supra), the clause of
arbitration at Clause 32 was substantially similar to the arbitration
clause in the present case. Clause 32 reads as follows :
"32. Arbitration.
(a) In the event of any question, dispute or
difference arising under or in connection with this
Agreement (except as to matters the decision of which
is specially provided for by this Agreement) the same
shall be referred to the sole arbitration of a person
appointed to be the arbitrator, by the General Manager
or the Railway. It will be no objection if the arbitrator is
a Government servant, that he had to deal with
matters to which the Agreement relates or that in the
course of his duties as a Government servant he has
expressed views on all or any of the matters in dispute
or difference. The Award of the arbitrator shall be final
and binding on the parties to this Agreement.
Provided always that the decision of the
General Manager of the Railway as to the disputes
which fell within the 'excepted matters' referred to
above shall be final and binding on the parties hereto
and such decision of the General Manager shall not be
called in question before the arbitrator by either of the
parties hereto.
(b) In the event of the arbitrator dying, neglecting
or refusing to act, or resigning or being unable to act
for any reason, or his award being set aside by the
Court for any reason it shall be lawful for the authority
appointing the arbitrator to appoint another arbitrator in
place of the outgoing arbitrator in the manner
aforesaid.
(c) It is further a term of this Agreement that no
person other than the person appointed by the
authority as aforesaid should act as arbitrator and that
if for any reason that is not possible, the matter is not
be referred to arbitration at all."
13. The Hon'ble Supreme Court in M/s. Continental India Private
Limited (supra) held that the decision of the High Court to constitute an
Arbitral Tribunal in terms of Clause 64(3)(b) of the GCC was
unsustainable as neither the GCC was signed by the parties nor the
GCC was made part of the agreement between the parties and
therefore, the parties are not governed by the GCC at all. It is further
held that as the respondents failed to appoint arbitrator as per the
agreed procedure and in terms of the agreement, the respondents had
forfeited their right to appoint an arbitrator in terms of the agreement
and therefore, the appellant was justified in filing the application before
the High Court for appointment of a sole arbitrator.
14. In Punj Lloyd Ltd. (supra), reliance was placed in the case of
Datar Switchgears Ltd. Vs. Tata Finance Limited , reported in (2000) 8
SCC 151, wherein, the Hon'ble Supreme Court had observed as
follows :
"5. ......... "[S]o far as Section 11(6) is concerned , if
one party demands the opposite party to appoint an
arbitrator and the opposite party does not make an
appointment within 30 days of the demand, the right to
appointment does not get automatically forfeited after
expiry of 30 days. If the opposite party makes an
appointment even after 30 days of the demand, but
before the first party has moved the court under
Section 11, that would be sufficient. In other words, in
case arising under Section 11(6), if the opposite party
has not made an appointment within 30 days of
demand, the right to make appointment is not forfeited
but continues, but an appointment has to be made
before the former files application under Section 11
seeking appointment of an arbitrator. Only then the
right of the opposite party ceases."
(emphasis in original)"
15. In Central Electronics Limited (supra), this Court had
observed as follows :
"8. In Durga Welding Works vs. Chief Engineer,
Railway Electrification, Allahabad and Another ,
reported in 2022 SCC Online SC 11, it is reiterated
that once an application under Section 11(6) of the
Act has been filed for appointment of an Arbitrator
before the High Court, the respondent forfeits its right
to appoint an arbitrator and the High Court alone has
jurisdiction to appoint an arbitrator in exercise of
power under Section 11(6) of the Act.
9. In this petition, the appointment of the arbitrator
was made by the respondent after the petitioner had
filed this petition under Section 11(6) of the Act.
10. In that view of the matter, I am of the considered
opinion that the petitioner has made out a case for
appointment of an arbitrator."
16. Reliance placed by Mr. Mishra on Mahanadi Coalfields
Limited & Another (supra) is misconceived. In Mahanadi Coalfields
Limited & Another (supra), the issue that was considered was as to
whether Clause 15 of the contract agreement constitutes or does not
constitute an arbitration agreement within the meaning of Sections 2(b)
and 7 of the A&C Act and on consideration of Clause 15, the Hon'ble
Supreme Court had come to the conclusion that though Clause 15 of
the Contract Agreement is titled "settlement of disputes" / arbitration,
substantive part of the provision makes it abundantly clear that there is
no arbitration agreement between the parties agreeing to refer either
present or future disputes to arbitration. Clause 15 reads as follows :
"15. Settlement of Disputes/Arbitration :
15.1. It is incumbent upon the contractor to avoid
litigation and disputes during the course of execution.
However, if such disputes take place between the
contractor and the department, effort shall be made
first to settle the disputes at the company level. The
contractor should make request in writing to the
Engineer-in-Charge for settlement of such disputes/
claims within 30 (thirty) days of arising of the case of
dispute/claim failing which no disputes/claims of the
contractor shall be entertained by the company.
15.2. If differences still persist, the settlement of
the dispute with Govt. Agencies shall be dealt with as
per the Guidelines issued by the Ministry of Finance,
Govt. of India in this regard. In case of parties other
than Govt. Agencies, the redressal of the disputes
may be sought in the Court of Law."
17. In the instant case, the respondents had not disputed
arbitration clause and rather had also appointed arbitrator, albeit, after
the applicant had filed his application before this Court. Therefore, the
ratio of Mahanadi Coalfields Limited & Another (supra) is not applicable
in the facts and circumstances of the case.
18. On due consideration, I find that the applicant has made out a
case for appointment of an arbitrator.
19. Accordingly, Hon'ble Mr. Justice Dhirendra Mishra (Retd.) is
appointed to act as the Arbitrator to resolve the disputes between the
parties.
20. The Registry is directed to communicate this order to Hon'ble
Mr. Justice Dhirendra Mishra (Retd.) in his Lordship's proper address.
21. The arbitration application, accordingly, stands allowed.
Sd/-
(Arup Kumar Goswami) CHIEF JUSTICE
Chandra
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!