Citation : 2021 Latest Caselaw 3323 Chatt
Judgement Date : 26 November, 2021
1
NAFR
HIGH COURT OF CHHATTISGARH AT BILASPUR
WPC No. 4801 of 2021
M/s. T.B.S. Banchhor, Having Office At 29, Kadambari Nagar, Durg (Cg)
Through Its Partner Shri. Nivedit Banchhor S/o. Shri T.B.S. Banchhor, Aged
About 43 Years, R/o. 29, Kadambari Nagar, Durg Chhattisgarh
---- Petitioner
Versus
1. State Of Chhattisgarh Through Secretary, Water Resource Department,
Mantralaya, Mahanadi Bhawan, Atal Nagar, Raipur Chhattisgarh
2. Engineer - In - Chief, Mahanadi Godavari Basin, Water Resource
Department, Shivnath Bhawan, Atal Nagar, Raipur Chhattisgarh
3. Chief Engineer, Water Resource Department, Shivnath Bhawan, Atal Nagar,
Raipur Chhattisgarh
4. Chief Engineer (Tender Cell) O/o. The Engineer-In- Chief, Water Resource
Department, Shivnath Bhawan, Atal Nagar, Raipur Chhattisgarh., District :
Raipur, Chhattisgarh
---- Respondents
For Petitioner : Mr. Shishir Dixit, Advocate For Respondent : Mr. Gagan Tiwari, GA
Hon'ble Mr. Justice P. Sam Koshy Hon'ble Mr. Justice Arvind Singh Chandel Judgment on Board by Hon'ble Mr. P. Sam Koshy
26/11/2021
1. Aggrieved by the Annexure P-5 dated 02.11.2021 disqualifying the
petitioner from participating in the general proceedings vide Tender no.
81826/NIT No.12/SAC/2021-22, the present writ petition has been filed.
2. The tender was invited for the "Akoli Tank", the scope of said work was
of Renovation of Akoli Tank and Remodeling and lining of the Main
Canal and and 02 Nos. Minor with Construction of 09 Nos V.R.B. 1 Nos
Aquaduct, 01 Nos. D.C., 06 Nos. Fall and 30 Nos. Colaba fixing in Block
Dhamdha and District Durg". The probable amount of contract was of
Rs. 650.05 Lakhs. The documents were to be submitted by the
24.09.2021.
3. During the scrutiny, the respondents found the petitioner to be
disqualified as he did not fulfill the required bid capacity and he was
found short of the bid capacity criteria. Accordingly the impugned e-mail
Annexure P-5 was issued intimating the petitioner in respect of his
disqualification. The letter of disqualification clearly envisaged that in
case, if the petitioner has any explanation to the decision arrived at by
the respondents, he could make a suitable representation to the Tender
Cell within a period of two days. It was further cautioned to the petitioner
that in the event, if the petitioner fails to make a representation or to
provide for an explanation, the authorities would be at liberty to proceed
further with the tender presuming that the petitioner does not have any
objection.
4. Today, when the matter is taken up for hearing, learned State counsel
intimates the Court that subsequent to the petitioner being declared
disqualified and further that for the reason that there was no
representation or an explanation provided by the petitioner within the
stipulated period, the authorities have further proceeded with the tender
and bid have already been opened and L-1 has also been declared and
as such much water has since flown and there is hardly any scope for
this Court left with the tender.
5. It is the further objection of the State counsel since the L-one has
already been declared, a right has been accrued in favour of the L-1, in
case, the writ petition at this juncture is entertained or interfered, the
right of the said L-1 would adversely get affected and the said L-1 has
not been made a party in the present writ petition. Therefore, also the
writ petition would not be sustainable.
6. Though, learned counsel for the petitioner tried to give an explanation
that immediately after receiving the e-mail on 02.11.2021 i.e. the
impugned order Annexure P-5, the petitioner had personally approached
the Chief Engineer of the Tender Cell on the very next day and had
given their explanation orally which was rejected by the Chief Engineer
and it is only thereafter that the petitioner has made a fresh
representation vide Annexure P-6 dated 17.11.2021. However, perusal
of the record would show that there is no evidence of the fact that
petitioner did meet the Chief Engineer, Tender Cell immediately after the
impugned e-mail dated 02.11.2021 was received by him.
7. To further add to it, if we look at Annexure P-6, the first representation
which the petitioner has made again is after a period of well over 15
days from the date the impugned e-mail was served upon to the
petitioner. It is not the case of the petitioner that they have not been
served with the impugned e-mail dated 02.11.2021 on the same day
itself, the petitioner accepts the fact that it has been duly received by
them on 02.11.2021 itself. If that be so, the contents of that e-mail
becomes more relevant at this juncture. For ready reference, contents of
the e-mail dated 02.11.2021 is reproduced hereinunder :-
" During the scrutiny of your documents downloaded for tender numbers shown in the subject above, You are found disqualified due to not fulfilling Bid Capacity Criteria.
Any explanation in this regard may please be presented to the Tender Cell within 2(Two) days. Failing which the process
shall be carried forward presuming that you have nothing to say."
8. Plain perusal of the aforesaid content of the e-mail dated 02.11.2021
would clearly reflect that the Authorities holding the petitioner disqualified
on the specific ground of not fulfilling the Bid Capacity Criteria had given
the opportunity for the petitioner to represent before the Tender Cell
within a period of two days giving their explanation in respect of the
decision taken by the respondents.
9. Apparently, the petitioner has not availed the said opportunity of
submitting an explanation within two days. In a tender proceeding, it is
the time which is the essence of the contract and therefore the tender
proceedings have to be initiated and concluded as per schedule and that
is the reason why while declaring the petitioner disqualified, he was
permitted to make a representation within two days. The petitioner
having not done so and thereafter making a representation after a period
of well over two weeks' time, the same cannot be accepted to be a
genuine grievance raised by the petitioner at a belated stage. He cannot
be permitted to cry foul after having failed to avail the opportunity at the
given time and there being no cogent reason for not approaching the
authorities within the prescribed period.
10. Moreover, during the intervening period as per the contents of the e-mail
dated 02.11.2021 the respondents have in fact proceeded with the
tender, bids were opened and the L-1 have also been declared.
11. Further taking note of the objection raised by the State counsel, the L-1
has also not been made a party to the present petition in spite of the
petition being filed after L-1 was declared. For all the aforesaid reasons,
we are not inclined to entertain the writ petition as no sufficient cause
has been shown by the petitioner for not having approached the
authorities concerned as per the requirement of impugned e-mail itself.
12. The writ petition therefore deserves to be and is accordingly rejected.
Sd/- Sd/-
(P. Sam Koshy) (Arvind Singh Chandel)
Judge Judge
Rohit
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!